The Uneven Settlement Cause and Settlement Prediction of Xi Ying Sluice

View through CrossRef
Xi Ying sluice built in Xishi River, Changzhou City, is a single span sluice with width of 6m. The chamber is pier wall structure of depressed reinforced concrete floor, when the chamber had a filling and discharging water during construction period, we found that the chamber appeared large uneven subsidence. According to the design, construction and other specific circumstances of Xi Ying sluice, by using three-dimensional finite element method to calculate and analyzed the settlement of the sluice, we studied on the genesis of the uneven settlement and predicted the settlement after the running. Analysis shows that the chamber of the uneven settlement is due to the jacking effect of concrete pile. The settlement has been basically completed caused by chamber weight, there will not be a substantial settlement; In the case of blocking water during operation period, chamber’s settlement increment outside the river side and inside the river side are respectively 0.3mm and 0.4mm; through processing, the settlement of chamber won’t affect the normal operation of sluice.
Title: The Uneven Settlement Cause and Settlement Prediction of Xi Ying Sluice
Description:
Xi Ying sluice built in Xishi River, Changzhou City, is a single span sluice with width of 6m.
The chamber is pier wall structure of depressed reinforced concrete floor, when the chamber had a filling and discharging water during construction period, we found that the chamber appeared large uneven subsidence.
According to the design, construction and other specific circumstances of Xi Ying sluice, by using three-dimensional finite element method to calculate and analyzed the settlement of the sluice, we studied on the genesis of the uneven settlement and predicted the settlement after the running.
Analysis shows that the chamber of the uneven settlement is due to the jacking effect of concrete pile.
The settlement has been basically completed caused by chamber weight, there will not be a substantial settlement; In the case of blocking water during operation period, chamber’s settlement increment outside the river side and inside the river side are respectively 0.
3mm and 0.
4mm; through processing, the settlement of chamber won’t affect the normal operation of sluice.

Related Results

Flow Measurements Using a Sluice Gate; Analysis of Applicability
Flow Measurements Using a Sluice Gate; Analysis of Applicability
This study analyzes the possibilities of using an irrigation sluice gate in submerged conditions to measure water flow rate. Hydraulic experiments on sluice gate discharge capacity...
En skvatmølle i Ljørring
En skvatmølle i Ljørring
A Horizontal Mill at Ljørring, Jutland.Horizontal water-mills have been in use in Jutland since the beginning of the Christian era 2). But the one here described shows so close a c...
The use of the sluice gate discharge equations to estimate the volumetric flow rate in the irrigation channels
The use of the sluice gate discharge equations to estimate the volumetric flow rate in the irrigation channels
The paper attempts to assess the possibility of using typical check structures equipped with sluice gates to measure the volumetric flow rate in the irrigation channels. The submer...
An investigation into gravity independent oscillating heat pipes
An investigation into gravity independent oscillating heat pipes
[ACCESS RESTRICTED TO THE UNIVERSITY OF MISSOURI AT AUTHOR'S REQUEST.] A number of oscillating heat pipes (OHPs) with unbalanced structures were investigated in an effort to develo...
Analysis of Uneven Settlement of Large Oil Storage Tank
Analysis of Uneven Settlement of Large Oil Storage Tank
Abstract The uneven settlement of large oil storage tank will not only cause the tank wall to be elliptical and the upper floating plate to be blocked, but also caus...
Continued Monitoring and Modeling of Xingfeng Solid Waste Landfill Settlement, China, Based on Multiplatform SAR Images
Continued Monitoring and Modeling of Xingfeng Solid Waste Landfill Settlement, China, Based on Multiplatform SAR Images
Continued settlement monitoring and modeling of landfills are critical for land redevelopment and safety assurance. This paper adopts a MTInSAR technique for time-series monitoring...
Designing Foundations on Natural Soil for Specified (Uniform) Settlement
Designing Foundations on Natural Soil for Specified (Uniform) Settlement
This study addresses the critical issue of differential settlement and long-term fracture prevention in building foundations. Mistakes in designing strip and column foundations on ...
Interpreting and evaluating digital soil mapping prediction uncertainties
Interpreting and evaluating digital soil mapping prediction uncertainties
There is an implicit quality associated with all soil maps which depends on a range of factors including the mapping algorithm, the extent and quality of the calibration data, and ...

Back to Top