Roads in Manokwari City still need a lot to be improved, especially on the Pegaf city boundary road - South Manokwari district, because this road connects the border between the City and the district.... This study aims to calculate the productivity of heavy equipment working on road improvement work, Analyzing the balance of road improvement work tools and knowing the total cost and time required in road improvement projects. So that this research is expected to be useful for optimizing the performance of road sections and being able to provide solutions to problems that occur and can provide an overview of the process of using heavy equipment that is effective and efficient. Productivity is the ability to produce something, so it can be said that heavy equipment productivity is the ability of heavy equipment to produce something per unit of time. In general, heavy equipment work production has the same calculation principles. The basic principles of calculating heavy equipment work production are 4 steps, namely calculating actual capacity, cycle time, calculating gross work production (PKK) and calculating actual work production (PKA). So it can be concluded that the productivity of ordinary embankment excavator 173.68m3 / hour, dump truck 10 tons of ordinary embankment 45.58m3 / hour, optional embankment 36.3m3 / hour, asphalt foundation layer (HRS Base) 7.91m3 / hour, Dump truck 4 tons of Class A aggregate layer 4.02m3 / hour, Class B aggregate layer 4.06m3/hour, motor grader 315m2/hour regular embankment, 174.30 m3/hour optional embankment, 561m2/hour pavement preparation, Class A aggregate layer 274.63m3/hour, Class B aggregate layer 274.63m3/hour, vibratory roller regular embankment 159.36 m3/hour, class A aggregate layer 77.02m3/hour, class B aggregate layer 77.02m3/hour asphalt distributor binder layer 4980 liters, air compressor binder work 1365.35 liters, asphalt finisher asphalt foundation layer (HRS Base) 69.85 tons, tandem roller regular embankment 39.84m3/hour, preparation of the road body 272.98m3 / hour, paving 86.59m3 / hour, wheel loader preferred embankment 117.58m3 / hour, class A aggregate layer 114.98m3 / hour, class B aggregate layer 116.53m3 / hour and tire roller paving 104.06 tons and the total cost of all equipment rental is Rp. 254,091,569.
Fakultas Teknik Universitas Cendrawasih
Title: Analisis Produktivitas Alat Berat Pada Pekerjaan Peningkatan Jalan Batas Kota Pegaf – Batas Kabupaten Manokwari Selatan
Description:
Roads in Manokwari City still need a lot to be improved, especially on the Pegaf city boundary road - South Manokwari district, because this road connects the border between the City and the district.
This study aims to calculate the productivity of heavy equipment working on road improvement work, Analyzing the balance of road improvement work tools and knowing the total cost and time required in road improvement projects.
So that this research is expected to be useful for optimizing the performance of road sections and being able to provide solutions to problems that occur and can provide an overview of the process of using heavy equipment that is effective and efficient.
Productivity is the ability to produce something, so it can be said that heavy equipment productivity is the ability of heavy equipment to produce something per unit of time.
In general, heavy equipment work production has the same calculation principles.
The basic principles of calculating heavy equipment work production are 4 steps, namely calculating actual capacity, cycle time, calculating gross work production (PKK) and calculating actual work production (PKA).
So it can be concluded that the productivity of ordinary embankment excavator 173.
68m3 / hour, dump truck 10 tons of ordinary embankment 45.
58m3 / hour, optional embankment 36.
3m3 / hour, asphalt foundation layer (HRS Base) 7.
91m3 / hour, Dump truck 4 tons of Class A aggregate layer 4.
02m3 / hour, Class B aggregate layer 4.
06m3/hour, motor grader 315m2/hour regular embankment, 174.
30 m3/hour optional embankment, 561m2/hour pavement preparation, Class A aggregate layer 274.
63m3/hour, Class B aggregate layer 274.
63m3/hour, vibratory roller regular embankment 159.
36 m3/hour, class A aggregate layer 77.
02m3/hour, class B aggregate layer 77.
02m3/hour asphalt distributor binder layer 4980 liters, air compressor binder work 1365.
35 liters, asphalt finisher asphalt foundation layer (HRS Base) 69.
85 tons, tandem roller regular embankment 39.
84m3/hour, preparation of the road body 272.
98m3 / hour, paving 86.
59m3 / hour, wheel loader preferred embankment 117.
58m3 / hour, class A aggregate layer 114.
98m3 / hour, class B aggregate layer 116.
53m3 / hour and tire roller paving 104.
06 tons and the total cost of all equipment rental is Rp.
254,091,569.
Related Results
Pengaruh Geometri Jalan Terhadap Produktivitas Alat Angkut
Pengaruh Geometri Jalan Terhadap Produktivitas Alat Angkut
Abstract. Based on the actual conditions in the field, there are several road geometries that are not in accordance with the standards resulting in high traffic density. This cause...
Analisa Kinerja Bersinyal Pada Jalan Pasca Perubahan Arus Di Kota Medan
Analisa Kinerja Bersinyal Pada Jalan Pasca Perubahan Arus Di Kota Medan
Transportasi merupakan kegiatan yang penting bagi masyarakat. Dari banyak hal, kualitas hidup masyarakat salah satunya dipengaruhi oleh transportasi dan akses ke tempat kerja, temp...
IDENTIFIKASI KARAKTERISTIK 4 SEGMEN KORIDOR JALAN UTAMA KOTA TANGERANG SELATAN (JL. PAHLAWAN SERIBU, JL. KAPTEN SOEBIANTO DJOJOHADIKUSUMO, JL. RAYA RAWABUNTU, DAN JL. BUARAN)
IDENTIFIKASI KARAKTERISTIK 4 SEGMEN KORIDOR JALAN UTAMA KOTA TANGERANG SELATAN (JL. PAHLAWAN SERIBU, JL. KAPTEN SOEBIANTO DJOJOHADIKUSUMO, JL. RAYA RAWABUNTU, DAN JL. BUARAN)
A good road corridor is one that pays attention to functionality, quality, and aesthetics, all optimized to meet road corridor planning standards. The profile of physical condition...
ANALISIS KINERJA RUAS JALAN DI WILAYAH PUSAT KOTA STUDI KASUS ( RUAS JALANANDI DJEMMA EX. JALAN JENDERAL SUDIRMAN KOTA PALOPO
ANALISIS KINERJA RUAS JALAN DI WILAYAH PUSAT KOTA STUDI KASUS ( RUAS JALANANDI DJEMMA EX. JALAN JENDERAL SUDIRMAN KOTA PALOPO
Dalam menentukan kinerja lalulintas pada ruas jalan Andi Djemma ex. Jalan Jenderal Sudirman Kota Palopo dapat digunakan beberapa populasi variabel utama, yaitu volume, kecepatan, k...
ANALISA KERUSAKAN PERKERASAN LENTUR JALAN NIKI-NIKI - OENLASI
ANALISA KERUSAKAN PERKERASAN LENTUR JALAN NIKI-NIKI - OENLASI
Kinerja jalan sebagai prasarana transportasi darat merupakan faktor yang sangat penting dalam bidang perhubungan terutama untuk kesinambungan distribusi barang dan jasa. Kinerja in...
Analisis Penerapan Jalan Satu Arah di Ruas Jalan Raya Leles-Jalan Lingkar Leles
Analisis Penerapan Jalan Satu Arah di Ruas Jalan Raya Leles-Jalan Lingkar Leles
Penelitian ini bertujuan untuk mengetahui penyebab kemacetan yang sering terjadi di ruas Jalan Raya Leles pada saat jam-jam sibuk dan mengetahui dampak penerapan jalan satu arah te...
Pengaruh Gerak U-Turn pada Bukaan Median terhadap Karakteristik Arus Lalu Lintas di Ruas Jalan Jenderal Ahmad Yani Kabupaten Ketapang
Pengaruh Gerak U-Turn pada Bukaan Median terhadap Karakteristik Arus Lalu Lintas di Ruas Jalan Jenderal Ahmad Yani Kabupaten Ketapang
Jalan Jenderal Ahmad Yani Kabupaten Ketapang merupakan jalan arteri dengan tipe lingkungan yaitu komersial dan terdapat hambatan samping yang berdampak terhadap kinerja lalu lintas...
Pendataan Ruas Jalan (Leger Jalan) pada Ruas Jalan Palembang - Betung
Pendataan Ruas Jalan (Leger Jalan) pada Ruas Jalan Palembang - Betung
AbstractAs national assets, roads are vital to establish the means of national development, especially in term of achieving balanced inter-regional development and equitable distri...