Problems in Cementing Horizontal Wells

View through CrossRef
" Any casing eccentricity becomes critical In horizontal wells because ofIts effect on flow velocity distributions In the wellbore." Introduction Horizontal wells are completed by one of four methods:open hole,casing packers,slotted or perforated liner, orcemented casing or liner. Completion Methods 1 through3 generally are known as "drainhole" completions, Method 4, commonlycalled a "cased-hole" or "stimulated" completion, is the focusof this paper. Formations that ordinarily would require stimulation in a vertical wellshould be completed as a cased-hole, or stimulated, completion. Obtaining asuccessful cement job is essential in this type of completion. Parameters thatcould affect the overall cement Parameters that could affect the overall cementjob are similar to those for vertical completions, with an emphasis ondisplacement mechanics and cement slurry design. Fig. 1 represents a horizontal wellbore and the parameters that affect thecement job. A settled-solids channel is observed on the lower side of theannulus and a filter cake and gelled drilling fluid are found around thecircumference. Removal of solids, filter cake, and gelled drilling fluid fromthese two problem areas is critical to ensure proper problem areas is criticalto ensure proper cementing results. Decentralized casing compounds the problemof displacement because cement slurry and spacers tend to follow the path ofleast resistance and bypass the path of least resistance and bypass thenarrower side (bottom) of the annulus. Therefore, using the casing equipmentnecessary to provide maximum centralization is essential. Cement composition is also important to achieve a successful cement job. Thecement composition shown in Fig. 1 has permitted a top-side channel of freewater to form that could prevent the necessary confinement of a stimulationtreatment. Finally, to confirm the success of cementing or to determine requirementsfor remedial work if problems occur, the horizontal cement job must beevaluated with acoustic tools. Proper logging and log evaluation techniquesmust be considered. This paper addresses the following major areas of concern: hole-cleaningproblems and displacement mechanics, pipe centralization, cement slurry design, and evaluation of the cement job through acoustic tools. Hole-Cleaning Problems and Displacement Mechanics Displacement of drilling fluid from highangle and horizontal wellbores iscomplicated by additional factors present under these conditions. A low-side solids channel may form by deposition and settling of drilledsolids and drilling-fluid weighting material. A channel filled with solids willnot seal the annulus for the life of the well. Also, solids channels couldcause problems with communication and confinement of stimulation treatments. These channels should be prevented from forming if possible; however, onceformed, they can be removed. Thin flushes, maximum pump rates, hole-cleaningcasing attachments, and pipe movement can help remove solids. Drilling-fluidproperties must be controlled within specific properties must be controlledwithin specific ranges, particularly in highly deviated and horizontal wells. Besides the conventional parameters of yield point, plastic viscosity, parameters of yield point, plastic viscosity, fluid loss, and gel strength, thedynamic settling characteristics of the drilling fluid must also be considered. Several authors 1–3 indicate that drilling-fluid yield point is the criticalparameter that must be controlled to very specific ranges. One author suggeststhat the drilling fluid should have a yieldpoint/plastic-viscosity ratiogreater than one (with yield point in lbf/100 ft and plastic viscosity incentipoise). The drilling-fluid settling characteristic must be controlled bysome means to prevent solids settling and thus to allow an adequate flow pathfor placement of the cement slurry. placement of the cement slurry. Also, inhorizontal wells, an increased possibility of a narrow casing-to-wellborepossibility of a narrow casing-to-wellbore clearance on one side exists becauseof pipe eccentricity combined with gravitational forces. Inadequate clearanceon the narrow side of these wellbores can lead to uncemented portions of casingcircumference because of the excessive forces needed to move any material(solids or gelled drilling fluids) in this area. Any casing eccentricitybecomes critical in horizontal wells because of its effect on flow velocitydistributions in the wellbore. JPT P. 398
Society of Petroleum Engineers (SPE)
Title: Problems in Cementing Horizontal Wells
Description:
" Any casing eccentricity becomes critical In horizontal wells because ofIts effect on flow velocity distributions In the wellbore.
" Introduction Horizontal wells are completed by one of four methods:open hole,casing packers,slotted or perforated liner, orcemented casing or liner.
Completion Methods 1 through3 generally are known as "drainhole" completions, Method 4, commonlycalled a "cased-hole" or "stimulated" completion, is the focusof this paper.
Formations that ordinarily would require stimulation in a vertical wellshould be completed as a cased-hole, or stimulated, completion.
Obtaining asuccessful cement job is essential in this type of completion.
Parameters thatcould affect the overall cement Parameters that could affect the overall cementjob are similar to those for vertical completions, with an emphasis ondisplacement mechanics and cement slurry design.
Fig.
1 represents a horizontal wellbore and the parameters that affect thecement job.
A settled-solids channel is observed on the lower side of theannulus and a filter cake and gelled drilling fluid are found around thecircumference.
Removal of solids, filter cake, and gelled drilling fluid fromthese two problem areas is critical to ensure proper problem areas is criticalto ensure proper cementing results.
Decentralized casing compounds the problemof displacement because cement slurry and spacers tend to follow the path ofleast resistance and bypass the path of least resistance and bypass thenarrower side (bottom) of the annulus.
Therefore, using the casing equipmentnecessary to provide maximum centralization is essential.
Cement composition is also important to achieve a successful cement job.
Thecement composition shown in Fig.
1 has permitted a top-side channel of freewater to form that could prevent the necessary confinement of a stimulationtreatment.
Finally, to confirm the success of cementing or to determine requirementsfor remedial work if problems occur, the horizontal cement job must beevaluated with acoustic tools.
Proper logging and log evaluation techniquesmust be considered.
This paper addresses the following major areas of concern: hole-cleaningproblems and displacement mechanics, pipe centralization, cement slurry design, and evaluation of the cement job through acoustic tools.
Hole-Cleaning Problems and Displacement Mechanics Displacement of drilling fluid from highangle and horizontal wellbores iscomplicated by additional factors present under these conditions.
A low-side solids channel may form by deposition and settling of drilledsolids and drilling-fluid weighting material.
A channel filled with solids willnot seal the annulus for the life of the well.
Also, solids channels couldcause problems with communication and confinement of stimulation treatments.
These channels should be prevented from forming if possible; however, onceformed, they can be removed.
Thin flushes, maximum pump rates, hole-cleaningcasing attachments, and pipe movement can help remove solids.
Drilling-fluidproperties must be controlled within specific properties must be controlledwithin specific ranges, particularly in highly deviated and horizontal wells.
Besides the conventional parameters of yield point, plastic viscosity, parameters of yield point, plastic viscosity, fluid loss, and gel strength, thedynamic settling characteristics of the drilling fluid must also be considered.
Several authors 1–3 indicate that drilling-fluid yield point is the criticalparameter that must be controlled to very specific ranges.
One author suggeststhat the drilling fluid should have a yieldpoint/plastic-viscosity ratiogreater than one (with yield point in lbf/100 ft and plastic viscosity incentipoise).
The drilling-fluid settling characteristic must be controlled bysome means to prevent solids settling and thus to allow an adequate flow pathfor placement of the cement slurry.
placement of the cement slurry.
Also, inhorizontal wells, an increased possibility of a narrow casing-to-wellborepossibility of a narrow casing-to-wellbore clearance on one side exists becauseof pipe eccentricity combined with gravitational forces.
Inadequate clearanceon the narrow side of these wellbores can lead to uncemented portions of casingcircumference because of the excessive forces needed to move any material(solids or gelled drilling fluids) in this area.
Any casing eccentricitybecomes critical in horizontal wells because of its effect on flow velocitydistributions in the wellbore.
JPT P.
398.

Related Results

Survey Of Horizontal Gas Well Activity
Survey Of Horizontal Gas Well Activity
Abstract This paper presents the results of a survey on horizontal gas well activity throughout the world. The survey was conducted for the Gas Research Institute...
Microorganisms for Secondary Cementation: A Promising Solution for Cracks and Microchannels in Oil Well Bore Casings
Microorganisms for Secondary Cementation: A Promising Solution for Cracks and Microchannels in Oil Well Bore Casings
Abstract Secondary cementing plays a crucial role in oil and gas well operations by providing zonal isolation and ensuring the integrity of wellbore structures. Seco...
Interpretation of Estimated Horizontal Well Lengths' From Interference Test Data
Interpretation of Estimated Horizontal Well Lengths' From Interference Test Data
Abstract This study uses interference test data from an analytical solution for a horizontal well in a closed reservoir to estimate the effective length of a prod...
A Deep Dive on Stage Cementing Operations in Sub-Saharan Africa: A Case Study
A Deep Dive on Stage Cementing Operations in Sub-Saharan Africa: A Case Study
Abstract Cementing through weak sand and unconsolidated formations are a common occurrence in today's drilling operations. Main challenges include well control, poor...
Full Offline Well Cementing Implementation Resulting in Significant Time Savings and Improvement in Operational Efficiency
Full Offline Well Cementing Implementation Resulting in Significant Time Savings and Improvement in Operational Efficiency
Abstract The current global low oil price environment has driven many operators to consider having a quicker and more efficient operations and reduction of the well ...
Performance Experiment of Ultra high Temperature Cementing Slurry System
Performance Experiment of Ultra high Temperature Cementing Slurry System
Abstract The continuous development of oil and gas exploration and development to deep and ultra deep wells in China, the formation temperature is also getting higher and h...
Successful Cementing Procedures Developed for Mobile Bay
Successful Cementing Procedures Developed for Mobile Bay
ABSTRACT Many factors combine to make drilling and completing a well in Mobile Bay, offshore Alabama a difficult engineering task. Of particular concern to operat...
Experimental Investigation on Cementing Integrity of Oil/Gas Wells 
Experimental Investigation on Cementing Integrity of Oil/Gas Wells 
The integrity of cementing in oil and gas wells is vital for ensuring wellbore stability and preventing environmental contamination. However, the extreme conditions encountered dur...