Locomotive Crash Energy Management Coupling Tests
View through CrossRef
Research to develop new technologies for increasing the safety of passengers and crew in rail equipment is being directed by the Federal Railroad Administration’s (FRA’s) Office of Research, Development, and Technology. Crash energy management (CEM) components which can be integrated into the end structure of a locomotive have been developed: a push-back coupler and a deformable anti-climber. These components are designed to inhibit override in the event of a collision. The results of vehicle-to-vehicle override, where the strong underframe of one vehicle, typically a locomotive, impacts the weaker superstructure of the other vehicle, can be devastating. These components are designed to improve crashworthiness for equipped locomotives in a wide range of potential collisions, including collisions with conventional locomotives, conventional cab cars, and freight equipment.
Concerns have been raised in discussions with industry that push-back couplers may trigger prematurely, and may require replacement due to unintentional activation as a result of service loads. Push-back couplers (PBCs) are designed with trigger loads meant to exceed the expected maximum service loads experienced by conventional couplers. Analytical models are typically used to determine these required trigger loads. Two sets of coupling tests have been conducted to demonstrate this, one with a conventional locomotive equipped with conventional draft gear and coupler, and another with a conventional locomotive retrofit with a push-back coupler. These tests will allow a performance comparison of a conventional locomotive with a CEM-equipped locomotive during coupling. In addition to the two sets of coupling tests, car-to-car compatibility tests of CEM-equipped locomotives, as well as a train-to-train test are also planned. This arrangement of tests allows for evaluation of the CEM-equipped locomotive performance, as well as comparison of measured with simulated locomotive performance in the car-to-car and train-to-train tests.
The coupling tests of a conventional locomotive have been conducted, the results of which compared favorably with pre-test predictions. This paper describes the results of the CEM-equipped locomotive coupling tests. In this set of tests, a moving CEM locomotive was coupled to a standing cab car. The primary objective was to demonstrate the robustness of the PBC design and determine the impact speed at which PBC triggering occurs. The coupling speed was increased for each subsequent test until the PBC triggered. The coupling speeds targeted for the test were 2 mph, 4 mph, 6 mph, 7 mph, 8 mph, and 9 mph. The coupling speed at which the PBC triggered was 9 mph. The damage observed resulting from the coupling tests is described. Prior to the tests, a lumped-mass model was developed for predicting the longitudinal forces acting on the equipment and couplers. The test results are compared to the model predictions. Next steps in the research program, including future full-scale dynamic tests, are discussed.
American Society of Mechanical Engineers
Title: Locomotive Crash Energy Management Coupling Tests
Description:
Research to develop new technologies for increasing the safety of passengers and crew in rail equipment is being directed by the Federal Railroad Administration’s (FRA’s) Office of Research, Development, and Technology.
Crash energy management (CEM) components which can be integrated into the end structure of a locomotive have been developed: a push-back coupler and a deformable anti-climber.
These components are designed to inhibit override in the event of a collision.
The results of vehicle-to-vehicle override, where the strong underframe of one vehicle, typically a locomotive, impacts the weaker superstructure of the other vehicle, can be devastating.
These components are designed to improve crashworthiness for equipped locomotives in a wide range of potential collisions, including collisions with conventional locomotives, conventional cab cars, and freight equipment.
Concerns have been raised in discussions with industry that push-back couplers may trigger prematurely, and may require replacement due to unintentional activation as a result of service loads.
Push-back couplers (PBCs) are designed with trigger loads meant to exceed the expected maximum service loads experienced by conventional couplers.
Analytical models are typically used to determine these required trigger loads.
Two sets of coupling tests have been conducted to demonstrate this, one with a conventional locomotive equipped with conventional draft gear and coupler, and another with a conventional locomotive retrofit with a push-back coupler.
These tests will allow a performance comparison of a conventional locomotive with a CEM-equipped locomotive during coupling.
In addition to the two sets of coupling tests, car-to-car compatibility tests of CEM-equipped locomotives, as well as a train-to-train test are also planned.
This arrangement of tests allows for evaluation of the CEM-equipped locomotive performance, as well as comparison of measured with simulated locomotive performance in the car-to-car and train-to-train tests.
The coupling tests of a conventional locomotive have been conducted, the results of which compared favorably with pre-test predictions.
This paper describes the results of the CEM-equipped locomotive coupling tests.
In this set of tests, a moving CEM locomotive was coupled to a standing cab car.
The primary objective was to demonstrate the robustness of the PBC design and determine the impact speed at which PBC triggering occurs.
The coupling speed was increased for each subsequent test until the PBC triggered.
The coupling speeds targeted for the test were 2 mph, 4 mph, 6 mph, 7 mph, 8 mph, and 9 mph.
The coupling speed at which the PBC triggered was 9 mph.
The damage observed resulting from the coupling tests is described.
Prior to the tests, a lumped-mass model was developed for predicting the longitudinal forces acting on the equipment and couplers.
The test results are compared to the model predictions.
Next steps in the research program, including future full-scale dynamic tests, are discussed.
Related Results
Conventional Locomotive Coupling Tests
Conventional Locomotive Coupling Tests
Research to develop new technologies for increasing the safety of passengers and crew in rail equipment is being directed by the Federal Railroad Administration’s (FRA’s) Office of...
Interface and Optimizations for Crash Severity Estimation and Inevitability Modelling in Pre-Crash Safety Systems
Interface and Optimizations for Crash Severity Estimation and Inevitability Modelling in Pre-Crash Safety Systems
"In recent years, emergency braking systems were introduced to detect and prevent potentialaccidents. However, it is not always possible to avoid a crash. Hence, active safety sens...
Validation of the PC-Crash Single-Track Vehicle Driver Model for Simulating Motorcycle Motion
Validation of the PC-Crash Single-Track Vehicle Driver Model for Simulating Motorcycle Motion
<div class="section abstract"><div class="htmlview paragraph">This paper validates the single-track vehicle driver model available in PC-Crash simulation software. The ...
Collision Prediction for Irreversible Pre-Crash Safety Measures
Collision Prediction for Irreversible Pre-Crash Safety Measures
The precise and reliable prediction of vehicle movements based on information from environmental sensors such as radar, camera or LiDAR is an essential constituent of future pre-cr...
Analisis Gangguan Hasil Uji Pop Test Sebagai Parameter Kehandalan Mesin Diesel Lokomotif CC 206
Analisis Gangguan Hasil Uji Pop Test Sebagai Parameter Kehandalan Mesin Diesel Lokomotif CC 206
Locomotive CC 206 is the newest locomotive owned by PT Kereta Api Indonesia. Inside the CC 206 locomotive is equipped with a sophisticated smart display that can monitor all size p...
Integrated simulation platform for a locomotive braking system
Integrated simulation platform for a locomotive braking system
We used a locomotive and a rail car to examine the working principle of a locomotive braking system. We established models of the locomotive braking system, the locomotive dynamics...
The interaction between neural populations: Additive versus diffusive coupling
The interaction between neural populations: Additive versus diffusive coupling
AbstractModels of networks of populations of neurons commonly assume that the interactions between neural populations are via additive or diffusive coupling. When using the additiv...
Comparing Psychometric Properties of GLFS-5 With GLFS-25 for Screening Locomotive Syndrome in Community-dwelling Iranian Older People
Comparing Psychometric Properties of GLFS-5 With GLFS-25 for Screening Locomotive Syndrome in Community-dwelling Iranian Older People
Objectives: Locomotive syndrome refers to reduced mobility due to impairment of locomotive organs. Because of the importance of screening locomotive syndrome among older people, th...