Javascript must be enabled to continue!
The Casing Cage Concept For Deepwater Structures
View through CrossRef
ABSTRACT
This paper introduces the casing cage concept and discusses the feasibility of using a casing cage to provide lateral support to the well system casings in compliant towers and deepwater jackets. The casing cage provides a solution to the problem of separating the structural functions of the platform from the well system.
INTRODUCTION
What is a Casing Cage?
The casing cage is a structure which provides lateral support to the well system casings (or conductors) [1]. The casing cage is framed nearly independently of a Compliant Piled Tower (CPT) or other deepwater jacket structure, and is located within an open area in the main structure of the platform. It is attached rigidly to the platform only at the top end, with all other attachments being slip guides that limit the horizontal movement of the casing cage, but allow vertical movement of the casing cage relative to the surrounding structure. Figure 1 shows the casing cage constructed in two sections for a 2500 ft. CPT platform. The casing cage consists of four legs with casing guide panels welded to the casing cage legs at intervals selected to provide adequate casing stability. The upper two casing guide panels have a different configuration from the others because these panels must withstand greater casing wave loading. The casing cage legs rest in guides at each CPT horizontal framing elevation. These guides allow transfer of lateral loads only. The entire casing cage is suspended from the CPT with struts located near the top of each section. The casing cage shown in Figure 1 is slightly buoyant for in-place conditions. Thus, the struts extend from the cage to the lower CPT horizontal level in order to maintain tension in the struts. Additional design refinements may suggest that a neutrally buoyant or ballasted casing cage configuration may be desired. Figure 2 shows the location of the casing cage in the upper CPT section.
Why Use a Casing Cage?
The casing cage solves a significant problem associated with conventional casing (or conductor) support systems. A conventional casing Support system is framed continuously to the CPT or deep water jacket. Previous detailed CPT analyses showed that casing support members attracted significant loads for launch and in-place conditions. The result was that the size of the casing support members had to be increased to meet allowable stress criteria. In the past, typical design practice was to ignore the secondary casing support members (i.e., not include them in analytical computer models). This practice appeared acceptable for shallow water structures. However, detailed deepwater CPT analyses showed that the casing support members attracted significant loads resulting in inefficient member sizes. The need to solve this problem led to the development of the casing cage.
Figure 3a shows a CPT horizontal elevation with conventional casing support members directly framed to the platform. Figure 3b shows the same horizontal elevation when a casing cage is used. The slip guides for the casing cage legs are evident in Figure 3b. Note in Figure 3b that CPT horizontal elevations and casing cage guide framing elevations are never in the same plane.
Title: The Casing Cage Concept For Deepwater Structures
Description:
ABSTRACT
This paper introduces the casing cage concept and discusses the feasibility of using a casing cage to provide lateral support to the well system casings in compliant towers and deepwater jackets.
The casing cage provides a solution to the problem of separating the structural functions of the platform from the well system.
INTRODUCTION
What is a Casing Cage?
The casing cage is a structure which provides lateral support to the well system casings (or conductors) [1].
The casing cage is framed nearly independently of a Compliant Piled Tower (CPT) or other deepwater jacket structure, and is located within an open area in the main structure of the platform.
It is attached rigidly to the platform only at the top end, with all other attachments being slip guides that limit the horizontal movement of the casing cage, but allow vertical movement of the casing cage relative to the surrounding structure.
Figure 1 shows the casing cage constructed in two sections for a 2500 ft.
CPT platform.
The casing cage consists of four legs with casing guide panels welded to the casing cage legs at intervals selected to provide adequate casing stability.
The upper two casing guide panels have a different configuration from the others because these panels must withstand greater casing wave loading.
The casing cage legs rest in guides at each CPT horizontal framing elevation.
These guides allow transfer of lateral loads only.
The entire casing cage is suspended from the CPT with struts located near the top of each section.
The casing cage shown in Figure 1 is slightly buoyant for in-place conditions.
Thus, the struts extend from the cage to the lower CPT horizontal level in order to maintain tension in the struts.
Additional design refinements may suggest that a neutrally buoyant or ballasted casing cage configuration may be desired.
Figure 2 shows the location of the casing cage in the upper CPT section.
Why Use a Casing Cage?
The casing cage solves a significant problem associated with conventional casing (or conductor) support systems.
A conventional casing Support system is framed continuously to the CPT or deep water jacket.
Previous detailed CPT analyses showed that casing support members attracted significant loads for launch and in-place conditions.
The result was that the size of the casing support members had to be increased to meet allowable stress criteria.
In the past, typical design practice was to ignore the secondary casing support members (i.
e.
, not include them in analytical computer models).
This practice appeared acceptable for shallow water structures.
However, detailed deepwater CPT analyses showed that the casing support members attracted significant loads resulting in inefficient member sizes.
The need to solve this problem led to the development of the casing cage.
Figure 3a shows a CPT horizontal elevation with conventional casing support members directly framed to the platform.
Figure 3b shows the same horizontal elevation when a casing cage is used.
The slip guides for the casing cage legs are evident in Figure 3b.
Note in Figure 3b that CPT horizontal elevations and casing cage guide framing elevations are never in the same plane.
Related Results
Casing Drilling with Retrievable Drilling Assemblies
Casing Drilling with Retrievable Drilling Assemblies
Abstract
Retrievable Casing Drilling* tools have been used to drill more than 600,000 ft of hole in over 120 wells encompassing six casing sizes ranging from 4-1/...
Top Drive Casing Running:Challenges and Solutions
Top Drive Casing Running:Challenges and Solutions
Abstract
Opportunity to improve rig floor safety, reduce technical casing running risk and reduce cost has motivated operators to utilise the top drive for casing...
Casing Centralization—Planned Compared to Actual: A Kuwait Case Study
Casing Centralization—Planned Compared to Actual: A Kuwait Case Study
Abstract
Several reasons can contribute to poor cementation; however, proper casing centralization can lead to uniform mud displacement with cement and can mitigate ...
Effect of Sand Production on Casing Integrity
Effect of Sand Production on Casing Integrity
Abstract
This paper documents an engineering study on sand production and its aftermaths on casing damage. Many wells were converted from production to water inje...
Casing Wear Prediction and Management in Deepwater Wells
Casing Wear Prediction and Management in Deepwater Wells
Abstract
Deepwater Gulf of Mexico wells are generally deep and they may incorporate casing designs that provide only a single-casing barrier between the wellbore and...
New Tendon and Riser Technologies Improve TLP Competitiveness in Ultra- Deepwater
New Tendon and Riser Technologies Improve TLP Competitiveness in Ultra- Deepwater
Abstract
The extensive industry experience with design, fabrication, installation, and operation of TLPs in water depths up to 4,000 ft has demonstrated the flexi...
An Evaluation Cement Method Using Gamma-Gamma Density Imaging Logging in a Double Casing Well
An Evaluation Cement Method Using Gamma-Gamma Density Imaging Logging in a Double Casing Well
Deep wells, ultradeep wells, and some offshore oil wells are characterized by high pressure and high temperature, and their cementing casing is often prone to collapse and rupture....
Sustained Casing Pressure in Offshore Producing Wells
Sustained Casing Pressure in Offshore Producing Wells
Abstract
A large number of producing wells in the OCS develop undesirable and sometimes potentially dangerous sustained pressure on one or more casing strings of ...

