Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Hyperbaric Welding at 300 MSW

View through CrossRef
ABSTRACT Hyperbaric welding and diving capabilities down to 300 m.s.w. were the contingency techniques required to support the laying of a sea-bed pipeline across the Norwegian Trench. Two welding methods were defined to meet stringent weld property specifications. Welding, diving equipment and diving procedures were developed m simultaneous programmes involving extensive unmanned tests and three manned simulated dives. An offshore demonstration of a full scale tie-in 300 m.s w. following identification of a "damaged" pipe section was performed from a D.S.V. assigned from conventional construction activities. Destructive testing of the actual welds confirmed the suitable of the equipment and procedures to provide insurance for deep field development projects. INTRODUCTION The development of the STATFJORD field and the decision to export its gas via the EKOFISK-EMDEN network necessitated the laying of two pipelines across the Norwegian Trench in depths ranging down to 300 m.s.w. a 30" line from STATFJORD to the gas treatment plant in KARSTO and a 28tf "export" line out to the EKOFISK area. Production tie-in operations were planned for maximum depth of 145 m.s.w. but demonstration of repair capabilities in the deepest sections of the trench was an obvious necessity. Routine construction operations seldom exceed 200 m.s.w. although single open sea dives as deep as 50 m. (JANUS N, 1977) have been proved possible. Welding procedures were previously qualified at 300 m.s.w. with some manual welding test performed at 400 m.s.w. An extensive programme was compiled jointly by STATPIPE and CCMEX SERVICES. The project was identified as the Deep Dive Development Project (3DP). The objective was to develop equipment and procedures and to, verify that they could be used safely at 300 m for a pipeline repair by hyperbaric welding. Welding procedures had to be refined from previous knowledge and qualified, followed by welder team qualification. Parallel manned and unmanned development programmes were to be launched to test equipment items, validate saturation procedures and evaluate short and long term effects of repetitive welding and diving tasks. Human factor aspects were to be observed during these routine deep work activities. In addition, a diving support vessel was to be prepared and a new welding spread constructed for use at 300 m.s.w. and beyond. The programme was scheduled for completion With in 15 months (by August 1983) with a demonstration dive in a Norwegian Fjord and performance of a full scale hyperbaric welding tie-in. The methods described in this paper, not only confirm that manned hyperbaric welding is a routine pipeline repair and pipeline connection method at 300 m.s.w., but also indicate that similar techniques could be extended to even greater depths. DEFINITION OF PARAMETERS AND PREVIOUS WORK Welding Two different welding process methods were required to be defined, one for qualifying welding procedures for each of five different pipes and for a minimum of twelve welder qualifications, and the second method as a back-up system.
Title: Hyperbaric Welding at 300 MSW
Description:
ABSTRACT Hyperbaric welding and diving capabilities down to 300 m.
s.
w.
were the contingency techniques required to support the laying of a sea-bed pipeline across the Norwegian Trench.
Two welding methods were defined to meet stringent weld property specifications.
Welding, diving equipment and diving procedures were developed m simultaneous programmes involving extensive unmanned tests and three manned simulated dives.
An offshore demonstration of a full scale tie-in 300 m.
s w.
following identification of a "damaged" pipe section was performed from a D.
S.
V.
assigned from conventional construction activities.
Destructive testing of the actual welds confirmed the suitable of the equipment and procedures to provide insurance for deep field development projects.
INTRODUCTION The development of the STATFJORD field and the decision to export its gas via the EKOFISK-EMDEN network necessitated the laying of two pipelines across the Norwegian Trench in depths ranging down to 300 m.
s.
w.
a 30" line from STATFJORD to the gas treatment plant in KARSTO and a 28tf "export" line out to the EKOFISK area.
Production tie-in operations were planned for maximum depth of 145 m.
s.
w.
but demonstration of repair capabilities in the deepest sections of the trench was an obvious necessity.
Routine construction operations seldom exceed 200 m.
s.
w.
although single open sea dives as deep as 50 m.
(JANUS N, 1977) have been proved possible.
Welding procedures were previously qualified at 300 m.
s.
w.
with some manual welding test performed at 400 m.
s.
w.
An extensive programme was compiled jointly by STATPIPE and CCMEX SERVICES.
The project was identified as the Deep Dive Development Project (3DP).
The objective was to develop equipment and procedures and to, verify that they could be used safely at 300 m for a pipeline repair by hyperbaric welding.
Welding procedures had to be refined from previous knowledge and qualified, followed by welder team qualification.
Parallel manned and unmanned development programmes were to be launched to test equipment items, validate saturation procedures and evaluate short and long term effects of repetitive welding and diving tasks.
Human factor aspects were to be observed during these routine deep work activities.
In addition, a diving support vessel was to be prepared and a new welding spread constructed for use at 300 m.
s.
w.
and beyond.
The programme was scheduled for completion With in 15 months (by August 1983) with a demonstration dive in a Norwegian Fjord and performance of a full scale hyperbaric welding tie-in.
The methods described in this paper, not only confirm that manned hyperbaric welding is a routine pipeline repair and pipeline connection method at 300 m.
s.
w.
, but also indicate that similar techniques could be extended to even greater depths.
DEFINITION OF PARAMETERS AND PREVIOUS WORK Welding Two different welding process methods were required to be defined, one for qualifying welding procedures for each of five different pipes and for a minimum of twelve welder qualifications, and the second method as a back-up system.

Related Results

Development of Fully Automated and Integrated ("Instamatic") Welding Systems for Marine Applications
Development of Fully Automated and Integrated ("Instamatic") Welding Systems for Marine Applications
ABSTRACT A two-year research program was conducted at M.I.T. to develop fully automated and integrated welding systems. These systems package many actions involve...
A.D.S. Wet Welding
A.D.S. Wet Welding
Abstract The purpose of this paper is to discuss wet welding using fully anthropomorphic atmospheric diving suits and offer proof that wet welding operations are ...
Robotic welding system for adaptive process control in gas metal arc welding
Robotic welding system for adaptive process control in gas metal arc welding
AbstractChanging process conditions such as distortion, varying seam preparation or gap width during welding is a major challenge in automated gas metal arc welding (GMAW). While h...
Laser Welding of Steels
Laser Welding of Steels
ABSTRACT Fundamentals of high-power laser welding are reviewed and unique features relative to other welding processes are noted. A brief description is given of ...
Welding robot system applied in sub-sea pipeline-installation
Welding robot system applied in sub-sea pipeline-installation
Purpose – The aim of this study was to develop a new generation of automatic systems based on cutting-edge design and practical welding physics to minimize downtime...
Effect of GTAW on the Mechanical Properties of Mild Steel
Effect of GTAW on the Mechanical Properties of Mild Steel
Tungsten metal arc welding (GTAW) is a highly popular welding technique in manufacturing. The welding factors such as welding current, voltage, speed, and gas flow ra...
Online Extraction of Pose Information of 3D Zigzag-Line Welding Seams for Welding Seam Tracking
Online Extraction of Pose Information of 3D Zigzag-Line Welding Seams for Welding Seam Tracking
Three-dimensional (3D) zigzag-line welding seams are found extensively in the manufacturing of marine engineering equipment, heavy lifting equipment, and logistics transportation e...
Municipal solid waste composting with amendments reduces heavy metals hazard, ecological risks and greenhouse gases emission
Municipal solid waste composting with amendments reduces heavy metals hazard, ecological risks and greenhouse gases emission
Abstract Open dumping and landfilling of municipal solid waste (MSW) in India cause environmental hazards and greenhouse gases (GHGs) emissions. Therefore, studies require ...

Back to Top