Dynamic Behavior of a Flexible Line During Installation
View through CrossRef
ABSTRACT
In order to get information about the forces on the connection between a flexible riser and a wet Christmas tree during a guide lineless lay-away operation, a full scale measurement has been performed in Campos Basin. Special transducers, based on LVDT sensors were developed for this purpose and installed on the external surface of the flexible line. Accelerometers and current meters were used for motion and current measurements, respectively.
Anumerical simulation of the initial configuration of the flexible line was carried out by using a non-linear finite element program installed on a 386 microcomputer.
The experimental and numerical results are presented in this paper and show a reasonable correlation.
INTRODUCTION
The recent discoveries of two big oil fields in Campus Basin, offshore Brazil, are outstanding in deep water exploration in a world scale. These fields, situated in waters from 200m to 1600m deep, have reservesaround 4 billion barrels of crude oil and 65 billion cubic meters of associated gas.
Based upon the analysis of several alternatives, PETROBRAS has decided to proceed with the preliminary exploitationplan of deep water oil fields, based on semi-submersible floating production units and subsea completed satellite wells using wet christmas trees and flexible lines. Flexible lines are classified in static lines and dynamic risers. Lines which lie on the bottom of the ocean are called static lines or just flowlines. Those which connect flowlines to the production platform, namedflexible risers, are primarely flowlines reinforced to withstand the stresses generated by current, wave and platform motions1.
The subsea well completion in water depths beyond 300m represents a quite critical operation. To overcome the major difficulty of an underwater couplingbetween the flexible production/control bundle (production, annulus and control lines) and the wet christmas tree, PETROBRAS recently developed the so-called lay-away operation.
The primary objective of the lay-away system is to provide a means of running either tree or production base attached to the flowlines in order to prevent the vulnerable pull-in operations. In the first option the tree is run attached to flowlines. In the second option, the production base is run with flowlines and after completing the well, the tree is lowered and locked onto the production base and flowline hub by means of two hydraulic connectors. Bothalternatives have already been successfully tested in Campos Basin
A lay-away completion is shown in Figure 1. After arriving on location, the lay vessel positions itself approximately 85m (280 ft) far away from the completion unit. Then, a cable is passed from the completion to the laying vessel and fastened on the flowline hub bridle, which is lowered by paying off the flowlines until a predetermined catenary curve is achieved. The hub is then hooked up to the moon pool and connected onto the production base cradle or tree flowline connector, depending on the option considered. Once locked in position the hydraulic and electrical connectors are tested from the lay vessel. The next step is simultaneously lowering tree or production base and flowlines until landing on wellhead.
Title: Dynamic Behavior of a Flexible Line During Installation
Description:
ABSTRACT
In order to get information about the forces on the connection between a flexible riser and a wet Christmas tree during a guide lineless lay-away operation, a full scale measurement has been performed in Campos Basin.
Special transducers, based on LVDT sensors were developed for this purpose and installed on the external surface of the flexible line.
Accelerometers and current meters were used for motion and current measurements, respectively.
Anumerical simulation of the initial configuration of the flexible line was carried out by using a non-linear finite element program installed on a 386 microcomputer.
The experimental and numerical results are presented in this paper and show a reasonable correlation.
INTRODUCTION
The recent discoveries of two big oil fields in Campus Basin, offshore Brazil, are outstanding in deep water exploration in a world scale.
These fields, situated in waters from 200m to 1600m deep, have reservesaround 4 billion barrels of crude oil and 65 billion cubic meters of associated gas.
Based upon the analysis of several alternatives, PETROBRAS has decided to proceed with the preliminary exploitationplan of deep water oil fields, based on semi-submersible floating production units and subsea completed satellite wells using wet christmas trees and flexible lines.
Flexible lines are classified in static lines and dynamic risers.
Lines which lie on the bottom of the ocean are called static lines or just flowlines.
Those which connect flowlines to the production platform, namedflexible risers, are primarely flowlines reinforced to withstand the stresses generated by current, wave and platform motions1.
The subsea well completion in water depths beyond 300m represents a quite critical operation.
To overcome the major difficulty of an underwater couplingbetween the flexible production/control bundle (production, annulus and control lines) and the wet christmas tree, PETROBRAS recently developed the so-called lay-away operation.
The primary objective of the lay-away system is to provide a means of running either tree or production base attached to the flowlines in order to prevent the vulnerable pull-in operations.
In the first option the tree is run attached to flowlines.
In the second option, the production base is run with flowlines and after completing the well, the tree is lowered and locked onto the production base and flowline hub by means of two hydraulic connectors.
Bothalternatives have already been successfully tested in Campos Basin
A lay-away completion is shown in Figure 1.
After arriving on location, the lay vessel positions itself approximately 85m (280 ft) far away from the completion unit.
Then, a cable is passed from the completion to the laying vessel and fastened on the flowline hub bridle, which is lowered by paying off the flowlines until a predetermined catenary curve is achieved.
The hub is then hooked up to the moon pool and connected onto the production base cradle or tree flowline connector, depending on the option considered.
Once locked in position the hydraulic and electrical connectors are tested from the lay vessel.
The next step is simultaneously lowering tree or production base and flowlines until landing on wellhead.
Related Results
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract
During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
Failure Detection Monitoring System Qualification Through a Full-Scale Dynamic Test
Failure Detection Monitoring System Qualification Through a Full-Scale Dynamic Test
Abstract
Flexible riser systems are widely adopted by the industry as solutions to interconnect subsea equipment and pipelines to floating production units. Their...
Independence Installation
Independence Installation
Abstract
This Session paper will review the planning, preparation, and execution of the installation of the Independence Hub facility in Mississippi Canyon Block ...
Reeled Pipe for Dynamic Riser Applications
Reeled Pipe for Dynamic Riser Applications
Abstract
A comprehensive test program has been running within the CSO organisation to establish the feasibility of using reeled pipe technology as an installation...
Challenges of TLP Installation Offshore Brazil
Challenges of TLP Installation Offshore Brazil
Abstract
Installation of a Tension Leg Platform comprises distinct phases, all of which can provide special challenges when considering locating a TLP in a fronti...
Offshore WTG Monopile Installation – Crane Vessel Preparation
Offshore WTG Monopile Installation – Crane Vessel Preparation
Abstract
Oil and Gas EPC contractors in the Middle East are gradually transitioning into the Wind farm development projects in Far East Asia and Europe. NPCC, one of...
Installation Analysis of Matterhorn Pipeline Replacement
Installation Analysis of Matterhorn Pipeline Replacement
Abstract
The paper describes the installation analysis for the Matterhorn field pipeline replacement, located in water depths between 800-ft to 1200-ft in the Gul...
Deepwater Development Using Novel Diverless Flowline Connection Technology
Deepwater Development Using Novel Diverless Flowline Connection Technology
ABSTRACT
The Statfjord Satellites, Statfjord Nerd and Statfjord Øst, are two smaller fields located in the vicinity of the Statfjord C' platform in the North Sea....