Application of GPS in pile foundation (PHC)
View through CrossRef
This study focuses on the problems of insufficient or excessive depth of
pile foundation embedding and excessive pile displacement in pile
foundation construction. By introducing global positioning system (GPS)
technology, the study focuses on solving practical problems in pile
foundation construction, optimizing pile foundation construction
methods, and designing an optimization plan based on verified GPS
technology in pile foundation construction. This plan includes precise
guidance for pile foundation layout using GPS technology, accurate
determination of effective pile length, and optimization of elevation
measurement using GPS technology. To verify the effectiveness of the
scheme, this study conducted empirical application in the pile
foundation construction project of Building 4 in a certain residential
area. The research results show that by combining the estimation of
effective pile length with pre drilled pile planting method, the
effective pile length can be accurately determined in most cases, and
the error is controlled within a reasonable range. Compared with total
stations, GPS technology has shown higher efficiency in determining pile
foundation points and pile top elevations, and can significantly save
costs. In addition, GPS technology can timely detect and correct
problems during pile height measurement, ensuring the stability of
construction quality.
Title: Application of GPS in pile foundation (PHC)
Description:
This study focuses on the problems of insufficient or excessive depth of
pile foundation embedding and excessive pile displacement in pile
foundation construction.
By introducing global positioning system (GPS)
technology, the study focuses on solving practical problems in pile
foundation construction, optimizing pile foundation construction
methods, and designing an optimization plan based on verified GPS
technology in pile foundation construction.
This plan includes precise
guidance for pile foundation layout using GPS technology, accurate
determination of effective pile length, and optimization of elevation
measurement using GPS technology.
To verify the effectiveness of the
scheme, this study conducted empirical application in the pile
foundation construction project of Building 4 in a certain residential
area.
The research results show that by combining the estimation of
effective pile length with pre drilled pile planting method, the
effective pile length can be accurately determined in most cases, and
the error is controlled within a reasonable range.
Compared with total
stations, GPS technology has shown higher efficiency in determining pile
foundation points and pile top elevations, and can significantly save
costs.
In addition, GPS technology can timely detect and correct
problems during pile height measurement, ensuring the stability of
construction quality.
Related Results
Analysis Of Three-Dimensional Pile Groups With Nonlinear Soil Response And Pile-Soil-Pile Interaction
Analysis Of Three-Dimensional Pile Groups With Nonlinear Soil Response And Pile-Soil-Pile Interaction
ABSTRACT
Present methods of pile group analysis are either limited to special geometric cases or do not consider pile-soil-pile interaction. An analytical procedu...
Model Test of Jacked Pile Penetration Process Considering Influence of Pile Diameter
Model Test of Jacked Pile Penetration Process Considering Influence of Pile Diameter
In order to investigate the influence of different diameters on pile end resistance, pile side resistance, pile axial force and pile force transmission law of jacked pile penetrati...
Pile–Soil Interaction and Group Pile Effect in Composite Foundation Under Different Pile Length Conditions
Pile–Soil Interaction and Group Pile Effect in Composite Foundation Under Different Pile Length Conditions
With the rapid development of urbanization and infrastructure construction, the requirements for the foundation design of high-rise buildings and large bridges are increasing. Pile...
Simplified Heat Transfer Model for Spiral‐Coil Energy Pile Groups and the Pile–Pile Thermal Interference
Simplified Heat Transfer Model for Spiral‐Coil Energy Pile Groups and the Pile–Pile Thermal Interference
ABSTRACTThe spiral heat exchanger of the energy pile groups is divided into multiple segments. Each heat exchanger segment is regarded as a three‐dimensional spiral heat source of ...
Pile Driving Measurements On The Heather Platform Installation
Pile Driving Measurements On The Heather Platform Installation
Abstract
The first leg piles of the Heather Platform were instrumented using strain transducers and accelerometers that were attached to the pile just below its t...
Comparative Analysis of the Compression and Uplift Bearing Characteristics of PHC Pipe Pile on the Same Site
Comparative Analysis of the Compression and Uplift Bearing Characteristics of PHC Pipe Pile on the Same Site
Introduction:
The analysis of single pile behavior is an important foundation for the analysis of group pile foundation and other complex pile foundations.
...
Contact between Prefabricated Pile and Pile Clamping Jaws under Pile Driving
Contact between Prefabricated Pile and Pile Clamping Jaws under Pile Driving
Pile clamping mechanism with hydraulic static pile driver has advantages of convenient for the design, improvement and use. The maximum transmission pile driving force of pile clam...
Behaviour of rock socketed pile groups
Behaviour of rock socketed pile groups
Rock socketed pile groups are extensively employed in the construction industry due to their effectiveness in maximizing space utilization while supporting substantial structural l...