Javascript must be enabled to continue!
New Build Generic Large FPSO
View through CrossRef
Abstract
The increasing demand for FPSOs and constant pressure for ever shorter delivery times has motivated SBM to design conversions and new-build hulls in a generic manner.
SBM has been designing successfully generic FPSOs using converted VLCC hulls, based on a rationalized deck layout with integrated power generation and process equipment.
Over a period of 3 years, this generic conversion design has been applied to a series of 7 FPSOs that will be briefly described in this paper.
In order to meet the increasing world-wide demand for large new-build hulls, SBM has designed a generic hull with a storage capacity of 2mmbbls or 2.4mmbbls, capable of supporting large topsides with a high level of flexibility in the process layout and using a similar philosophy to that developed for the generic hull conversions. Typical machinery and accommodation blocks are proposed permitting future modifications to be tailored to specific requirement.
This new-build hull design will permit fast track hull construction and FPSO delivery.
Introduction
FPSO designs, whether based on converted tanker or new-build hulls, are governed by a number of key technical factors:- typically the storage capacity, production capacity, export capacity, site environment and crew complement.
However, a key non-technical factor affecting the entire project organization and major technical decisions is time schedule which is a significant challenge for designers.
There is obviously a need for a fast track method for building or converting FPSOs. However, it is unreasonable to expect to simply squeeze indefinitely all project activities to achieve significantly reduced delivery times: this would result in unacceptable risks during design and construction, with commensurate risks to the performance of the unit.
Those conflicting requirements triggered an alternative approach to manage a fast track FPSO project, the so-called generic approach.
At the end of 1999 SBM and Gusto invested time in screening all aspects of tanker conversion; defining a basis of design suitable for a wide range of applications and carried out an internal engineering study in preparation for expected future FPSO conversion projects.
This investment proved to be very fruitful. The design was used in several projects including the FPSOs Falcon, Atlantic and Serpentina for ExxonMobil, FPSO Espadarte, Brasil and Marlim Sul for Petrobras and FPSO Mystras for Agip. The design is also currently proposed on many other projects.
Despite the success of generic conversions, new-build hulls may be required for FPSO projects.
This paper will first address FPSO conversion background and explain the main drivers for new build hulls.
Then, the generic hull, including the basis of design, the structure, the hull systems and the interfaces with topsides plant, will be presented.
Finally, construction phase and operational feed-back will be addressed briefly based on the experience gained as both prime contractor and leased vessel operator.
Title: New Build Generic Large FPSO
Description:
Abstract
The increasing demand for FPSOs and constant pressure for ever shorter delivery times has motivated SBM to design conversions and new-build hulls in a generic manner.
SBM has been designing successfully generic FPSOs using converted VLCC hulls, based on a rationalized deck layout with integrated power generation and process equipment.
Over a period of 3 years, this generic conversion design has been applied to a series of 7 FPSOs that will be briefly described in this paper.
In order to meet the increasing world-wide demand for large new-build hulls, SBM has designed a generic hull with a storage capacity of 2mmbbls or 2.
4mmbbls, capable of supporting large topsides with a high level of flexibility in the process layout and using a similar philosophy to that developed for the generic hull conversions.
Typical machinery and accommodation blocks are proposed permitting future modifications to be tailored to specific requirement.
This new-build hull design will permit fast track hull construction and FPSO delivery.
Introduction
FPSO designs, whether based on converted tanker or new-build hulls, are governed by a number of key technical factors:- typically the storage capacity, production capacity, export capacity, site environment and crew complement.
However, a key non-technical factor affecting the entire project organization and major technical decisions is time schedule which is a significant challenge for designers.
There is obviously a need for a fast track method for building or converting FPSOs.
However, it is unreasonable to expect to simply squeeze indefinitely all project activities to achieve significantly reduced delivery times: this would result in unacceptable risks during design and construction, with commensurate risks to the performance of the unit.
Those conflicting requirements triggered an alternative approach to manage a fast track FPSO project, the so-called generic approach.
At the end of 1999 SBM and Gusto invested time in screening all aspects of tanker conversion; defining a basis of design suitable for a wide range of applications and carried out an internal engineering study in preparation for expected future FPSO conversion projects.
This investment proved to be very fruitful.
The design was used in several projects including the FPSOs Falcon, Atlantic and Serpentina for ExxonMobil, FPSO Espadarte, Brasil and Marlim Sul for Petrobras and FPSO Mystras for Agip.
The design is also currently proposed on many other projects.
Despite the success of generic conversions, new-build hulls may be required for FPSO projects.
This paper will first address FPSO conversion background and explain the main drivers for new build hulls.
Then, the generic hull, including the basis of design, the structure, the hull systems and the interfaces with topsides plant, will be presented.
Finally, construction phase and operational feed-back will be addressed briefly based on the experience gained as both prime contractor and leased vessel operator.
Related Results
Competitive CVAR-FPSO concepts with Dry trees in ultra-deepwater; Weathervaning CVAR-FPSO for Brazil and Indonesia vs. Non-weathervaning for West Africa
Competitive CVAR-FPSO concepts with Dry trees in ultra-deepwater; Weathervaning CVAR-FPSO for Brazil and Indonesia vs. Non-weathervaning for West Africa
Abstract
A new FPSO concept termed CVAR-FPSO is under development by a JNOC headed Joint Industry Project (JIP). The concept, using Compliant Vertical Access Rise...
Increased life expectancy of heart failure patients in a rural center by a multidisciplinary program
Increased life expectancy of heart failure patients in a rural center by a multidisciplinary program
Abstract
Funding Acknowledgements
Type of funding sources: None.
INTRODUCTION Patients with heart failure (HF)...
FPSO EIS Results and Record of Decision
FPSO EIS Results and Record of Decision
Abstract
The United States Department of the Interior (DOI), Minerals Management Service (MMS) prepared an environmental impact statement (EIS)1 to evaluate poten...
FPSO's Today: What is the Optimum Concept?
FPSO's Today: What is the Optimum Concept?
ABSTRACT
FPSO technology over the past years has rapidly evolved from tanker based units with classical mooring systems to purpose-shaped new built vessels equipp...
The Challenges and Opportunities of FPSO Relocations
The Challenges and Opportunities of FPSO Relocations
Abstract
The first FPSO relocation project was completed 18 years ago (SBM's FPSO II), and since that time there has been a steady rise in the number and complexi...
The Sanha LPG FPSO
The Sanha LPG FPSO
Abstract
The FPSO industry will soon have the first LPG FPSO in operation. The SANHA LPG FPSO is the first gas related FPSO. With the installation of the LPG FPSO...
Floating Production, Storage, and Offloading Systems in the Gulf of Mexico OCS: A Regulatory Perspective
Floating Production, Storage, and Offloading Systems in the Gulf of Mexico OCS: A Regulatory Perspective
Abstract
Floating Production, Storage, and Offloading (FPSO) systems represent an untested technology in the U.S. Gulf of Mexico (GOM) Outer Continental Shelf. Th...
Deepstar Study on Predicting FPSO Responses - Model Tests VS Numerical Analysis
Deepstar Study on Predicting FPSO Responses - Model Tests VS Numerical Analysis
1. ABSTRACT
This paper presents the correlation study of FPSO model tests and numerical analyses sponsored by the DeepStar program. The numerical analysis results...

