Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Analysis Of Dynamic Transient Response (Ringing) In A Gravity-Base Structure

View through CrossRef
ABSTRACT Troll Gravity Base Structure (GBS)will be located in about 300m water depth and Will be the tallest GBS when installed in 1995. The natural periods of the structure in surge and sway are of the order of 5-5Yi seconds. Model tests carried out showed that greater responses than expected from "classic" design practice were likely under steep wave conditions. Recent model tests on other structures have also shown that loads on large diameter surface piercing cylinders in steep wave conditions are considerably larger than those expected from classic design practice. In irregular waves, this has contributed to a dynamic transient response, a phenomenon commonly referred to as "ringing". The challenge was to explain the physics behind these additional loads and quantify these to such a degree that structural reinforcement carried out on the Troll GBS for this specific reason during construction could be justified. This paper describes the work that was performed to verify the integrity of the Troll GBS in the in-place conditions focusing upon the resolution of the above challenge. INTRODUCTION Gravity base structures have been successfully deployed in the production and storage of offshore hydrocarbons since 1973. Since then, the design of GBS's has undergone a steady evolution which has resulted in considerable optimization of the strength of these structures. This optimization has gone hand in hand with increases in production water depths. Figure 1 shows the first and the most recent(Troll)(Available in full paper) Condeep GBS's with their basic particulars illustrating the significant advances which have been made on all fronts of GBS technology. Design optimization and increasing water depths have contributed to the lengthening of the natural periods of these structures which started off rather stiff with natural periods less than 2 seconds, increasing to 5½ seconds for the Troll design. In early 1992, model tests on two other concrete structures, Heidrun TLP and Draugen Monotower, had indicated that the loads experienced during the model tests under 100-year storm conditions were in excess of those which would be expected from calculations. Thus, preparations were put in place to consider whether similar increase in loads might be expected on the Troll GBS, The issue was being carefully studied by Norske Shell's EPC contractor, NorwegianContractors, via their consultant, SINTEF. In view of the uncertainty surrounding the evaluation of these additional loads, Norske Shell appointed Noble Denton to verify the work via independent analyses. Norske Shell is the Development Operator and Statoil will subsequently take over as Production Operator of the Troll Phase I gas production. Other partners are Norsk Hydro, Saga Petroleum, Elf Aquitaine, Norsk Conoco and Total Marine. This paper describes the work performed by Noble Denton to verify the calculations carried out on behalf of Norske Shell's EPC contractor. The work was performed in two key stages: Initially, efforts were focused upon developing a hydrodynamic loading model which would capture the characteristics of the dynamic transient response (ringing) which was causing the additional loads. The developed loading model was verified against model test results.
Title: Analysis Of Dynamic Transient Response (Ringing) In A Gravity-Base Structure
Description:
ABSTRACT Troll Gravity Base Structure (GBS)will be located in about 300m water depth and Will be the tallest GBS when installed in 1995.
The natural periods of the structure in surge and sway are of the order of 5-5Yi seconds.
Model tests carried out showed that greater responses than expected from "classic" design practice were likely under steep wave conditions.
Recent model tests on other structures have also shown that loads on large diameter surface piercing cylinders in steep wave conditions are considerably larger than those expected from classic design practice.
In irregular waves, this has contributed to a dynamic transient response, a phenomenon commonly referred to as "ringing".
The challenge was to explain the physics behind these additional loads and quantify these to such a degree that structural reinforcement carried out on the Troll GBS for this specific reason during construction could be justified.
This paper describes the work that was performed to verify the integrity of the Troll GBS in the in-place conditions focusing upon the resolution of the above challenge.
INTRODUCTION Gravity base structures have been successfully deployed in the production and storage of offshore hydrocarbons since 1973.
Since then, the design of GBS's has undergone a steady evolution which has resulted in considerable optimization of the strength of these structures.
This optimization has gone hand in hand with increases in production water depths.
Figure 1 shows the first and the most recent(Troll)(Available in full paper) Condeep GBS's with their basic particulars illustrating the significant advances which have been made on all fronts of GBS technology.
Design optimization and increasing water depths have contributed to the lengthening of the natural periods of these structures which started off rather stiff with natural periods less than 2 seconds, increasing to 5½ seconds for the Troll design.
In early 1992, model tests on two other concrete structures, Heidrun TLP and Draugen Monotower, had indicated that the loads experienced during the model tests under 100-year storm conditions were in excess of those which would be expected from calculations.
Thus, preparations were put in place to consider whether similar increase in loads might be expected on the Troll GBS, The issue was being carefully studied by Norske Shell's EPC contractor, NorwegianContractors, via their consultant, SINTEF.
In view of the uncertainty surrounding the evaluation of these additional loads, Norske Shell appointed Noble Denton to verify the work via independent analyses.
Norske Shell is the Development Operator and Statoil will subsequently take over as Production Operator of the Troll Phase I gas production.
Other partners are Norsk Hydro, Saga Petroleum, Elf Aquitaine, Norsk Conoco and Total Marine.
This paper describes the work performed by Noble Denton to verify the calculations carried out on behalf of Norske Shell's EPC contractor.
The work was performed in two key stages: Initially, efforts were focused upon developing a hydrodynamic loading model which would capture the characteristics of the dynamic transient response (ringing) which was causing the additional loads.
The developed loading model was verified against model test results.

Related Results

Gravity data reduction, Bouguer anomaly, and gravity disturbance
Gravity data reduction, Bouguer anomaly, and gravity disturbance
Each point on the earth has a gravity and gravity potential value. Surfaces formed by connecting points with equal gravity potential values are called equipotential surfaces or lev...
Influence of saturation level on the acoustic emission characteristics of gas hydrate-bearing coal
Influence of saturation level on the acoustic emission characteristics of gas hydrate-bearing coal
AbstractTo study the effects of gas hydrates on the prevention and control of coal and gas protrusions, this paper reports the results of acoustic emission experiments on coal bodi...
Unlocking the Secrets of Bird Conservation through Ringing: A Review
Unlocking the Secrets of Bird Conservation through Ringing: A Review
Bird ringing, a widely employed technique for marking and studying birds, plays a crucial role in bird conservation. As the human population increases and natural habitats are thre...
Nonlinear Drift of the Spring Gravimeter Caused by Air Pressure from the Kunming GS15 Gravimeters
Nonlinear Drift of the Spring Gravimeter Caused by Air Pressure from the Kunming GS15 Gravimeters
Abstract In order to monitor and correct the meteorological factors of the spring gravity meter, the characteristics of the time varying gravity changes caused by m...
Bell ringing during the epidemic: Traditions and their modern transformation
Bell ringing during the epidemic: Traditions and their modern transformation
The article examines the functions of bell ringing in medieval and early modern Europe and describes how the use of bells changed during epidemics. Catholic prayers for bell blessi...
Using spherical scaling functions in scalar and vector airborne gravimetry
Using spherical scaling functions in scalar and vector airborne gravimetry
<p>Airborne gravimetry is capable to provide Earth’s gravity data of high accuracy and spatial resolution for any area of interest, in particular for ha...
The Absolute Gravity Reference Network of Italy
The Absolute Gravity Reference Network of Italy
The project for realizing the reference network for absolute gravity in the Italian area is presented. This fundamental infrastructure is the general frame for all the scientific a...
7 th International Symposium on Enabling Technologies for Life Sciences (ETP)
7 th International Symposium on Enabling Technologies for Life Sciences (ETP)
The seventh in the series of ETP Symposia (see Rapid Communications in Mass Spectrometry 2012, 26 , ...

Back to Top