Gemini Host Facility Upgrade
View through CrossRef
Abstract
Effectively utilizing existing Gulf of Mexico shelf infrastructure will allow predictable fast tracking of new deepwater subsea developments. In the case of the Gemini subsea development, this meant upgrading an over twenty-year-old oil handling host platform to accommodate up to 240 MM ft3/day of gas and 4,320 bbl/day of liquids. The Viosca Knoll 900 "A" host platform was modified to include approximately 18,000 ft2 of additional deck space with an operating weight of more than 1,700 tons. The upgrade was executed in a simultaneous operations mode with limited amount of host platform production downtime. Topside facility challenges are highlighted including equipment added, equipment placement issues, installation methods and interfaces between new and existing producing equipment.
While many fixed water production and drilling platforms are aging and nearing abandonment, deepwater subsea completions are becoming more common place in the Gulf of Mexico. Properly evaluating this aging infrastructure can lead to profitable deepwater developments with short cycle time, few startup problems and high production availability.
Introduction
In August 1997, front end engineering and design was initiated for the Gemini subsea development. An integrated joint Texaco (60% working interest) and Chevron (40% working interest) project team was established. The development consisted of drilling and producing Allison gas reserves subsea with a tie back to a shallow water host facility. The following October, the jointly owned Chevron (75%) / Texaco (25%) Viosca Knoll 900 "A" platform was selected as host platform. Front end loading for topsides commenced late October 1997, with board approval by both companies granted in January 1998.
The Gemini project team was charged with drilling and completing wells in 3,393 ft water depth and producing back to the host facility located in 340-ft water depth via two 27 mile flowlines. First production was targeted for July 1, 1999.
Topside facilities were soon identified as critical path. Topside scope of work included providing gas processing facilities to accommodate new production and interfacing with existing host platform liquids handling equipment. To allow for future expansion, Gemini topside facilities were designed for 240 MM ft3/day of gas and 4,320 bbl/day of liquids. The Gemini upgrade added 18,000 ft2 of new deck area to the existing 28,000 ft2, a 64% increase. First production was brought online one month ahead of schedule on June 2, 1999.
Topside Challenges
The topside project team was faced with several challenges:Upgrading host platform to accommodate over 1,700 tons (operating weight) of new structure and equipmentIntegrating new and old production and safety systemsFast track project executionIntegrating Texaco and Chevron operations philosophies. Texaco was charged with managing project execution, while Chevron would operate the host platform
Host Platform Description
Viosca Knoll 900 "A", an eight-pile 24-slot drilling and production platform, was installed by Gulf Oil Company in 1976 and is located approximately 90 miles southeast of New Orleans, Louisiana in 340 ft of water.
Title: Gemini Host Facility Upgrade
Description:
Abstract
Effectively utilizing existing Gulf of Mexico shelf infrastructure will allow predictable fast tracking of new deepwater subsea developments.
In the case of the Gemini subsea development, this meant upgrading an over twenty-year-old oil handling host platform to accommodate up to 240 MM ft3/day of gas and 4,320 bbl/day of liquids.
The Viosca Knoll 900 "A" host platform was modified to include approximately 18,000 ft2 of additional deck space with an operating weight of more than 1,700 tons.
The upgrade was executed in a simultaneous operations mode with limited amount of host platform production downtime.
Topside facility challenges are highlighted including equipment added, equipment placement issues, installation methods and interfaces between new and existing producing equipment.
While many fixed water production and drilling platforms are aging and nearing abandonment, deepwater subsea completions are becoming more common place in the Gulf of Mexico.
Properly evaluating this aging infrastructure can lead to profitable deepwater developments with short cycle time, few startup problems and high production availability.
Introduction
In August 1997, front end engineering and design was initiated for the Gemini subsea development.
An integrated joint Texaco (60% working interest) and Chevron (40% working interest) project team was established.
The development consisted of drilling and producing Allison gas reserves subsea with a tie back to a shallow water host facility.
The following October, the jointly owned Chevron (75%) / Texaco (25%) Viosca Knoll 900 "A" platform was selected as host platform.
Front end loading for topsides commenced late October 1997, with board approval by both companies granted in January 1998.
The Gemini project team was charged with drilling and completing wells in 3,393 ft water depth and producing back to the host facility located in 340-ft water depth via two 27 mile flowlines.
First production was targeted for July 1, 1999.
Topside facilities were soon identified as critical path.
Topside scope of work included providing gas processing facilities to accommodate new production and interfacing with existing host platform liquids handling equipment.
To allow for future expansion, Gemini topside facilities were designed for 240 MM ft3/day of gas and 4,320 bbl/day of liquids.
The Gemini upgrade added 18,000 ft2 of new deck area to the existing 28,000 ft2, a 64% increase.
First production was brought online one month ahead of schedule on June 2, 1999.
Topside Challenges
The topside project team was faced with several challenges:Upgrading host platform to accommodate over 1,700 tons (operating weight) of new structure and equipmentIntegrating new and old production and safety systemsFast track project executionIntegrating Texaco and Chevron operations philosophies.
Texaco was charged with managing project execution, while Chevron would operate the host platform
Host Platform Description
Viosca Knoll 900 "A", an eight-pile 24-slot drilling and production platform, was installed by Gulf Oil Company in 1976 and is located approximately 90 miles southeast of New Orleans, Louisiana in 340 ft of water.
Related Results
Exploring Large Language Models Integration in the Histopathologic Diagnosis of Skin Diseases: A Comparative Study
Exploring Large Language Models Integration in the Histopathologic Diagnosis of Skin Diseases: A Comparative Study
Abstract
Introduction
The exact manner in which large language models (LLMs) will be integrated into pathology is not yet fully comprehended. This study examines the accuracy, bene...
Assessment of Chat-GPT, Gemini, and Perplexity in Principle of Research Publication: A Comparative Study
Assessment of Chat-GPT, Gemini, and Perplexity in Principle of Research Publication: A Comparative Study
Abstract
Introduction
Many researchers utilize artificial intelligence (AI) to aid their research endeavors. This study seeks to assess and contrast the performance of three sophis...
Conduction system versus biventricular pacing upgrade in patients with pacing-induced cardiomyopathy
Conduction system versus biventricular pacing upgrade in patients with pacing-induced cardiomyopathy
Abstract
Background
The feasibility and outcome of conduction system pacing (CSP) upgrade as an alternative modality to the trad...
Fractal Description of Pore Structures of Low Permeability Oil Reservoirs and its Relationship with Gemini Surfactant Flooding
Fractal Description of Pore Structures of Low Permeability Oil Reservoirs and its Relationship with Gemini Surfactant Flooding
Abstract
Gemini surfactant flooding is a promising technique to enhance oil recovery from medium-high permeability oil reservoirs. The screening of the gemini surfac...
Performance of
AI
‐Chatbots to Common Temporomandibular Joint Disorders (
TMDs
) Patient Queries: Accuracy, Completeness, Reliability and Readability
Performance of
AI
‐Chatbots to Common Temporomandibular Joint Disorders (
TMDs
) Patient Queries: Accuracy, Completeness, Reliability and Readability
ABSTRACT
TMDs are a common group of conditions affecting the temporomandibular joint (TMJ) often resulting from factors like injury, stress or teeth grinding. Thi...
Upgrade pacemaker to CRT: predictors and the importance of LVEF
Upgrade pacemaker to CRT: predictors and the importance of LVEF
Abstract
Funding Acknowledgements
Type of funding sources: None.
Introduction
...
Viscoelastic Evaluation of Gemini Surfactant Gel for Hydraulic Fracturing
Viscoelastic Evaluation of Gemini Surfactant Gel for Hydraulic Fracturing
Abstract
The viscoelastic surfactant (VES) fluids have been used in stimulation of low permeability oil and gas reservoir due to their low formation damage. The phys...
Google Gemini as a Learning Assistant: Exploring Student Perceptions
Google Gemini as a Learning Assistant: Exploring Student Perceptions
The emergence of Generative Artificial Intelligence (GAI) has had a significant impact on learning. One of the AI technologies that is currently developing is Google Google Gemin...