Javascript must be enabled to continue!
Balmoral: Floating Production Vessel Integrated Control System
View through CrossRef
ABSTRACT
The paper describes the Integrated Digital Control System installed on the Balmoral Floating Production Vessel (FPV). It describes the hardware and functional aspects of the system and the reasons for integration.
The main system is unique in that it incorporates both Vessel and Production subsystems, utilises common hardware and software and provides plantwide monitoring, control and reporting facilities.
The paper concludes that the system may well set the trend for future FPVs with similar control requirements.
INTRODUCTlON
The necessity for some level of system integration was indicated by the Owner's design basis requirements that the Control System should:-Provide maximum design flexibility permitting early commitment of hardware orders prior to full definition of operational requirements.Permit control of selected subsystems from anyone of three control rooms, namely the Wheelhouse, Ballast Control Room and Process & Subsea Control Room dependent on operational mode.Permit monitoring of subsystems from all control rooms.Provide facilities for planning major operations and sufficient automation of tasks to avoid operating errors, resulting in shutdown or hazardous conditions.Provide for reporting and transmission of plantwide data to snore. These criteria in space constraints microprocessor based shown in Figure 1.
The extent of integration desirable was decided by two main constraints:-The level of specialisation/capability required by each subsystemThe differing Certifying Authority requirements for control and safety related systems Due to the various constraints the subsystem were split into:Safety related and logic systemsSubsea controlsMain system
The subsea and safety interfaced with the main reporting purposes.
The main system is a distributed digital control system (DCS) with a supervisory computer superimposed. This configuration provided the degree of design flexibility and plant wide interface required. It also ensured that should software problems arise, the DCS would provide an adequate level of functionality for plant commissioning and initial operation.
Because of the coverage necessary to describe all the Balmoral systems, this paper is restricted to the DCS and Supervisory Computer system functions. Other systems are described only with regard to their interface with this system.
The main DCS and Supervisory System functions are:Ballast ManagementMooring ManagementEnergy ManagementProduction Management and System interfaces The advantage of integrating these systems is that all data is stored in a common data base and is thus available for use to any management system for computations or display.
SYSTEM ARCHITECTURE
The configuration of the Main Control System is shown in fig 2.. The system is comprised of dual Supervisory and Monitoring System (SMS) computers and a distributed Digital Control System (DCS). The DCS provides the plant interface for the SMS via intelligent data acquisition units and microprocessor control units. The operator interface with the DCS is comprised of intelligent workstations with 19 inch colour monitors and keyboards. These are independent of the SMS computer and provide back-up for the computer workstations. The computer workstations consist of 19 inch colour monitors, keyboards and video generator and are driven by the SMS computer.
Title: Balmoral: Floating Production Vessel Integrated Control System
Description:
ABSTRACT
The paper describes the Integrated Digital Control System installed on the Balmoral Floating Production Vessel (FPV).
It describes the hardware and functional aspects of the system and the reasons for integration.
The main system is unique in that it incorporates both Vessel and Production subsystems, utilises common hardware and software and provides plantwide monitoring, control and reporting facilities.
The paper concludes that the system may well set the trend for future FPVs with similar control requirements.
INTRODUCTlON
The necessity for some level of system integration was indicated by the Owner's design basis requirements that the Control System should:-Provide maximum design flexibility permitting early commitment of hardware orders prior to full definition of operational requirements.
Permit control of selected subsystems from anyone of three control rooms, namely the Wheelhouse, Ballast Control Room and Process & Subsea Control Room dependent on operational mode.
Permit monitoring of subsystems from all control rooms.
Provide facilities for planning major operations and sufficient automation of tasks to avoid operating errors, resulting in shutdown or hazardous conditions.
Provide for reporting and transmission of plantwide data to snore.
These criteria in space constraints microprocessor based shown in Figure 1.
The extent of integration desirable was decided by two main constraints:-The level of specialisation/capability required by each subsystemThe differing Certifying Authority requirements for control and safety related systems Due to the various constraints the subsystem were split into:Safety related and logic systemsSubsea controlsMain system
The subsea and safety interfaced with the main reporting purposes.
The main system is a distributed digital control system (DCS) with a supervisory computer superimposed.
This configuration provided the degree of design flexibility and plant wide interface required.
It also ensured that should software problems arise, the DCS would provide an adequate level of functionality for plant commissioning and initial operation.
Because of the coverage necessary to describe all the Balmoral systems, this paper is restricted to the DCS and Supervisory Computer system functions.
Other systems are described only with regard to their interface with this system.
The main DCS and Supervisory System functions are:Ballast ManagementMooring ManagementEnergy ManagementProduction Management and System interfaces The advantage of integrating these systems is that all data is stored in a common data base and is thus available for use to any management system for computations or display.
SYSTEM ARCHITECTURE
The configuration of the Main Control System is shown in fig 2.
The system is comprised of dual Supervisory and Monitoring System (SMS) computers and a distributed Digital Control System (DCS).
The DCS provides the plant interface for the SMS via intelligent data acquisition units and microprocessor control units.
The operator interface with the DCS is comprised of intelligent workstations with 19 inch colour monitors and keyboards.
These are independent of the SMS computer and provide back-up for the computer workstations.
The computer workstations consist of 19 inch colour monitors, keyboards and video generator and are driven by the SMS computer.
Related Results
Balmoral: Conception to Production
Balmoral: Conception to Production
ABSTRACT
Sun was faced with the challenge of commercially developing Balmoral, a small reservoir located in a water depth of 460 ft on Block 16/21a of the UK sect...
Kajian Pengembangan Sediaan Floating Sustained Release Tablet
Kajian Pengembangan Sediaan Floating Sustained Release Tablet
Abstract. Floating sustained release tablets were developed to increase the elimination half-life and bioavailability of the drug because it is able to release the active substance...
Design of Floating HPMC Matrix Tablets: Effect of Formulation Variables on Floating Properties and Drug Release
Design of Floating HPMC Matrix Tablets: Effect of Formulation Variables on Floating Properties and Drug Release
Floating matrix tablets were designed and evaluated. Theophylline was used as a model drug. The system was prepared by mixing drug, matrix-forming polymer (hydroxypropyl methylcell...
Design and Functional Requirements for the Floating Container Terminal at Valdez, Alaska
Design and Functional Requirements for the Floating Container Terminal at Valdez, Alaska
ABSTRACT
The City of Valdez, Alaska, will be pioneering in container terminal facilities when it installs the first floating dock designed for the operation of a ...
Debottlenecking of The Machar Slug Catcher
Debottlenecking of The Machar Slug Catcher
Abstract
The BP Machar slug catcher is a combined three phase separator and slug catcher located at the ETAP platform in the British sector of the North Sea. With...
Floating Production Systems
Floating Production Systems
Abstract
This paper considers some of the major problem areas which are being encountered in offshore oil and gas developments. The case is then presented for the...
Floating Production Systems
Floating Production Systems
ABSTRACT
The paper reviews the different types of floating production systems available ttt the petroleum industry and addresses why these platforms presently rep...
Nonlinear optimal control for robotic exoskeletons with electropneumatic actuators
Nonlinear optimal control for robotic exoskeletons with electropneumatic actuators
Purpose
To provide high torques needed to move a robot’s links, electric actuators are followed by a transmission system with a high transmission rate. For instance, gear ratios of...

