Integrity Management Process of Tension Leg Platforms
View through CrossRef
Abstract
As the Gulf of Mexico (GOM) fleet of Tension Leg Platforms (TLPs) ages, the need for more explicit Integrity Management (IM) and life extension guidance, particularly for the tendons, has grown. Recent industry efforts have developed Structural Integrity Management (SIM) guidance for fixed and floating systems, but tendon-specific guidance is less detailed. The Bureau of Safety and Environmental Enforcement commissioned the study described in this paper to develop this guidance including providing greater definition of IM and life extension processes for tendon systems, and describing an approach for demonstrating the reliability of tendon systems subjected to fatigue degradation.
Four primary objectives are addressed: 1) tendon IM, 2) tendon life extension, 3) tendon fatigue, and 4) tendon component post-service testing. These topics were addressed through the input of subject matter experts, interfacing with TLP operators, and developing analytical tools. The study looked at current industry practice for the design and management of tendon systems; how current SIM approaches can be applied to the unique features of TLP tendons; what are the critical features of tendons to be addressed as part of a life extension program; tendon fatigue factors of safety; how reliability approaches can be used to better define risks related to operating beyond the original service life; and how forensic testing of recovered tendon components can be used to gain a better understanding of tendon performance expectations.
Title: Integrity Management Process of Tension Leg Platforms
Description:
Abstract
As the Gulf of Mexico (GOM) fleet of Tension Leg Platforms (TLPs) ages, the need for more explicit Integrity Management (IM) and life extension guidance, particularly for the tendons, has grown.
Recent industry efforts have developed Structural Integrity Management (SIM) guidance for fixed and floating systems, but tendon-specific guidance is less detailed.
The Bureau of Safety and Environmental Enforcement commissioned the study described in this paper to develop this guidance including providing greater definition of IM and life extension processes for tendon systems, and describing an approach for demonstrating the reliability of tendon systems subjected to fatigue degradation.
Four primary objectives are addressed: 1) tendon IM, 2) tendon life extension, 3) tendon fatigue, and 4) tendon component post-service testing.
These topics were addressed through the input of subject matter experts, interfacing with TLP operators, and developing analytical tools.
The study looked at current industry practice for the design and management of tendon systems; how current SIM approaches can be applied to the unique features of TLP tendons; what are the critical features of tendons to be addressed as part of a life extension program; tendon fatigue factors of safety; how reliability approaches can be used to better define risks related to operating beyond the original service life; and how forensic testing of recovered tendon components can be used to gain a better understanding of tendon performance expectations.
Related Results
Muscle Metabolism during Exercise in Hemiparetic Patients
Muscle Metabolism during Exercise in Hemiparetic Patients
1. A group of eight male patients with moderate hemiparesis was studied at rest and during 40 min of exercise on four occasions. Both two-leg and one-leg exercise were performed an...
Ultrasonic Inspection of the Tension Leg Platform Tension Leg Components
Ultrasonic Inspection of the Tension Leg Platform Tension Leg Components
Abstract
An ultrasonic inspection system is being developed to locate and size defects in the tension legs of the Hutton Field Tension Leg Platform (TLP), which w...
Developing guidelines for research institutions
Developing guidelines for research institutions
As introduced in Chapter 1, in this thesis, I developed guidelines to research institutions on how to foster research integrity. I did this by exploring how research institutions c...
The Experimental and Theoretical Study of a Tension Leg Platform in Deep Water
The Experimental and Theoretical Study of a Tension Leg Platform in Deep Water
ABSTRACT
The offshore industry is going into deep water exceeding 3,000 ft.
The tension leg platform Js available for exploratory drilling, supp...
Design and Manufacture of Couplings for the Hutton TLP Mooring System
Design and Manufacture of Couplings for the Hutton TLP Mooring System
ABSTRACT
The components of the Hutton TLP tension legs are assembled using integral rotary shouldered couplings. This taper threaded coupling was purposed designe...
The Wave Induced Motions of a Tension Leg Platform in Deep Water
The Wave Induced Motions of a Tension Leg Platform in Deep Water
Abstract
This paper deals with the behaviour of a four column semi-submersible type Tension Leg Platform in 450 m water depth under the influence of regular and i...
Actualització consistent de bases de dades deductives
Actualització consistent de bases de dades deductives
En aquesta tesi, proposem un nou mètode per a l'actualització consistent de bases de dades deductives. Donada una petició d'actualització, aquest mètode tradueix de forma automàtic...
Hutton TLP Mooring System
Hutton TLP Mooring System
ABSTRACT
The tension leg platform (TLP) which is being developed for the Hutton Field in the North Sea is the first application of this new platform concept which...