Sustainable Electrical Outfitting in Shipbuilding: A Chemical Tanker Case Study
View through CrossRef
The electrical outfitting process has emerged as a critical phase in contemporary ship-building, influencing both construction efficiency and the vessels' long-term performance. This study examines the impact of planning, installation, and coordination of electrical systems on productivity and sustainability at shipyards, specifically on a chemical tanker project. Project records supplied information on labor hours, material management, and task sequencing, facilitating a rigorous examination of the impact of outfitting choices on quality and timelines. Particular emphasis was placed on the prompt installation of cable supports during block assembly, the systematic arrangement of cable routing, and the im-plementation of explicit registers and connection annotations. The results indicate that proactive planning of electrical outfitting, in conjunction with lean production methodol-ogies, minimizes delays, reduces rework, and enhances overall resource efficiency. These enhancements result in concrete advantages, including reduced construction durations, decreased expenses, and improved construction reliability. The study suggests that treat-ing electrical outfitting as a planned and integrated component of ship building, rather than a final phase, yields quantifiable improvements in efficiency and advances sustain-ability objectives. This illustrates a viable approach for promoting low-carbon, re-source-efficient shipbuilding methods.
Title: Sustainable Electrical Outfitting in Shipbuilding: A Chemical Tanker Case Study
Description:
The electrical outfitting process has emerged as a critical phase in contemporary ship-building, influencing both construction efficiency and the vessels' long-term performance.
This study examines the impact of planning, installation, and coordination of electrical systems on productivity and sustainability at shipyards, specifically on a chemical tanker project.
Project records supplied information on labor hours, material management, and task sequencing, facilitating a rigorous examination of the impact of outfitting choices on quality and timelines.
Particular emphasis was placed on the prompt installation of cable supports during block assembly, the systematic arrangement of cable routing, and the im-plementation of explicit registers and connection annotations.
The results indicate that proactive planning of electrical outfitting, in conjunction with lean production methodol-ogies, minimizes delays, reduces rework, and enhances overall resource efficiency.
These enhancements result in concrete advantages, including reduced construction durations, decreased expenses, and improved construction reliability.
The study suggests that treat-ing electrical outfitting as a planned and integrated component of ship building, rather than a final phase, yields quantifiable improvements in efficiency and advances sustain-ability objectives.
This illustrates a viable approach for promoting low-carbon, re-source-efficient shipbuilding methods.
Related Results
Soviet Shipbuilding: Productivity improvement Efforts
Soviet Shipbuilding: Productivity improvement Efforts
Constant demand for new naval and commercial vessels has created special conditions for the Government-owned Soviet shipbuilding industry, which practically has not been affected b...
Hydatid Disease of The Brain Parenchyma: A Systematic Review
Hydatid Disease of The Brain Parenchyma: A Systematic Review
Abstarct
Introduction
Isolated brain hydatid disease (BHD) is an extremely rare form of echinococcosis. A prompt and timely diagnosis is a crucial step in disease management. This ...
EPD Electronic Pathogen Detection v1
EPD Electronic Pathogen Detection v1
Electronic pathogen detection (EPD) is a non - invasive, rapid, affordable, point- of- care test, for Covid 19 resulting from infection with SARS-CoV-2 virus. EPD scanning techno...
Automatic Generation of a Detailed Outfitting Planning and Determining the Effect of Multi-Skilled Mounting Teams
Automatic Generation of a Detailed Outfitting Planning and Determining the Effect of Multi-Skilled Mounting Teams
Automatic planning literature for shipbuilding has historically only addressed the hull-related production processes, such as section building and erection. However, the outfitting...
Breast Carcinoma within Fibroadenoma: A Systematic Review
Breast Carcinoma within Fibroadenoma: A Systematic Review
Abstract
Introduction
Fibroadenoma is the most common benign breast lesion; however, it carries a potential risk of malignant transformation. This systematic review provides an ove...
Ming Dynasty Shipbuilding Technology from the Chronicle of Longjiang Shipyard
Ming Dynasty Shipbuilding Technology from the Chronicle of Longjiang Shipyard
This study analyzes the shipbuilding techniques of gongjiang, the types of ships, and the materials, labor, and management systems used in their production, in order to clarify the...
A convergence between cultural heritage and shipbuilding science
A convergence between cultural heritage and shipbuilding science
In the contemporary context, the demand for wooden vessels remains prevalent in the domains of fisheries, tourism and contemporary sailing. This necessitates a convergence of tradi...
Can Knowledge Management Be Appropriate for Shipbuilding?: Based on Typology and the Seven C’s Model
Can Knowledge Management Be Appropriate for Shipbuilding?: Based on Typology and the Seven C’s Model
I use typology to find the divisions of knowledge management by literature review, then I use the seven C's model to evaluate knowledge management in shipbuilding. The research aim...