An overview of nuclear power plant siting and licensing
View through CrossRef
Abstract
Studies on nuclear power plant siting and licensing are expensive and complex undertakings requiring critical geologic input for the planning, design, and construction phases. Commercial production of nuclear power in the United States began in 1959, in an era when geologic hazards were seemingly not as critical as they are today to designers, constructors, and regulatory agencies. By the early 1970s, however, siting work required a more sophisticated appreciation of geologic hazards such as earthquake effects, subsidence, slope stability, and foundation integrity. These concerns were formalized by the U.S. Atomic Energy Commission (AEC) in 1971 in its "Seismic and Geologic Siting Criteria for Nuclear Power Plants" and in 1972 in the Standard Format.
The required Federal license to construct and operate nuclear power plants is awarded through a careful and demanding process. Construction permits are not granted until high levels of assurance are attained as to suitability of the site; the construction process must be observed and monitored. Electric utility applicants for construction permits and operating licenses organize large teams of scientific and technical personnel to compile the Preliminary Safety Analysis Report (PSAR) required for each nuclear power plant. Geologists constitute a key part of these teams, producing site-specific and regional assessments that are accurate enough to withstand scrutiny and timely enough to avoid costly delays in the programmed design-and-construct sequence.
Management techniques must be applied to coordinate data-collection efforts and timely release of findings. As soon as a complete set of findings is compiled to the specifications of the Standard Format, the PSAR is accepted for review by the Nuclear Regulatory Commission (NRC). These reports become complex documents and include the responses to subsequent review questions which are included as amendments. The Final Safety Analysis Report (FSAR) includes supplementary reports dealing with geologic findings revealed during construction.
Many of the key geologic issues identified in siting and licensing are often analogous to those problems that confront researchers in the geological sciences today, such as evaluation of remote imagery, proof of subsurface stratigraphic continuity, evaluation of potential fault activity, a thorough assessment of ground-water conditions at each site, and subsidence potential including evaluation of dissolution of foundation material.
The overriding goal of each applicant utility is the construction of a safe power plant; however, the future of the industry in the United States is dependent on its ability to maintain construction schedules while staying within allotted budgets. Lessons learned from previous sitings have pointed out that effective management and judgment, efficient communication, and coordination contribute to timely and cost-efficient license studies.
Geological Society of America
Title: An overview of nuclear power plant siting and licensing
Description:
Abstract
Studies on nuclear power plant siting and licensing are expensive and complex undertakings requiring critical geologic input for the planning, design, and construction phases.
Commercial production of nuclear power in the United States began in 1959, in an era when geologic hazards were seemingly not as critical as they are today to designers, constructors, and regulatory agencies.
By the early 1970s, however, siting work required a more sophisticated appreciation of geologic hazards such as earthquake effects, subsidence, slope stability, and foundation integrity.
These concerns were formalized by the U.
S.
Atomic Energy Commission (AEC) in 1971 in its "Seismic and Geologic Siting Criteria for Nuclear Power Plants" and in 1972 in the Standard Format.
The required Federal license to construct and operate nuclear power plants is awarded through a careful and demanding process.
Construction permits are not granted until high levels of assurance are attained as to suitability of the site; the construction process must be observed and monitored.
Electric utility applicants for construction permits and operating licenses organize large teams of scientific and technical personnel to compile the Preliminary Safety Analysis Report (PSAR) required for each nuclear power plant.
Geologists constitute a key part of these teams, producing site-specific and regional assessments that are accurate enough to withstand scrutiny and timely enough to avoid costly delays in the programmed design-and-construct sequence.
Management techniques must be applied to coordinate data-collection efforts and timely release of findings.
As soon as a complete set of findings is compiled to the specifications of the Standard Format, the PSAR is accepted for review by the Nuclear Regulatory Commission (NRC).
These reports become complex documents and include the responses to subsequent review questions which are included as amendments.
The Final Safety Analysis Report (FSAR) includes supplementary reports dealing with geologic findings revealed during construction.
Many of the key geologic issues identified in siting and licensing are often analogous to those problems that confront researchers in the geological sciences today, such as evaluation of remote imagery, proof of subsurface stratigraphic continuity, evaluation of potential fault activity, a thorough assessment of ground-water conditions at each site, and subsidence potential including evaluation of dissolution of foundation material.
The overriding goal of each applicant utility is the construction of a safe power plant; however, the future of the industry in the United States is dependent on its ability to maintain construction schedules while staying within allotted budgets.
Lessons learned from previous sitings have pointed out that effective management and judgment, efficient communication, and coordination contribute to timely and cost-efficient license studies.
Related Results
The state-federal partnership in siting of nuclear power plants
The state-federal partnership in siting of nuclear power plants
Abstract
Geology and seismology studies are becoming increasingly important in nuclear power plant siting decisions. Earthquake hazard assessment is perhaps the most...
Exploring the implementation of public involvement in local alcohol availability policy: the case of alcohol licensing decision‐making in England
Exploring the implementation of public involvement in local alcohol availability policy: the case of alcohol licensing decision‐making in England
AbstractBackground and AimsIn 2003, the UK government passed the Licensing Act for England and Wales. The Act provides a framework for regulating alcohol sale, including four licen...
Improving Public Acceptance to Nuclear Power: Policy, Practice and Experience With Public Communication
Improving Public Acceptance to Nuclear Power: Policy, Practice and Experience With Public Communication
With the development of public awareness on environmental protection, especially after the Fukushima nuclear accident, the opposition to nuclear power due to NIMBY (not in my back ...
Legal Issues on the Management of High-Level Radioactive Waste
Legal Issues on the Management of High-Level Radioactive Waste
In Korea, the level of environmental issues and safety awareness of the people has increased since the 2000s, and after the Fukushima nuclear accident, public opinion against the g...
Siting Noxious Facilities: A Test of the Facility Siting Credo
Siting Noxious Facilities: A Test of the Facility Siting Credo
Over the past decade it has become increasingly difficult to site noxious facilities, despite the fact that there is a growing need to do so. To address this problem, a set of guid...
Public Perception of Nuclear Power Risk in China and Methods to Improve Public Acceptance
Public Perception of Nuclear Power Risk in China and Methods to Improve Public Acceptance
At present, the most influencing factor on nuclear power’s development in China the public’s attitude and acceptance. This paper studies the public perception of nuclear power risk...
Public Acceptance of Spent Fuel Reprocessing Project
Public Acceptance of Spent Fuel Reprocessing Project
At present, there are hundreds of nuclear power plants in operation around the world. Anti-nuclear movements continue in many places, although the nuclear power plants have good op...
Back to the Future: Nuclear Power
Back to the Future: Nuclear Power
Nuclear power is considered by many to be an old technology locked in the past— they say the future is with solar and wind. Commercial nuclear power began in 1951 when Russia built...