Optimization of Deepwater Template Drilling
View through CrossRef
ABSTRACT
This paper describes the methods and technologies employed during the drilling of the Jolliet Development wells. The Jolliet development wells were drilled from a subsea drilling template in water depth of 1760 feet.
INTRODUCTION
The field is currently producing from the first Tension Leg Well Platform (TLWP) in the Gulf of Mexico which was installed after completion of the drilling phase. Jolliet development drilling operations were conducted between July 1987 and May 1989 after installation of the drilling template.
The drilling performance attained on this project was outstanding when compared with other wells drilled in this type of frontier environment. This paper presents an overview of the methods and equipment used to optimize deepwater drilling from a template and therefore ultimately realize substantial savings.
Key elements of the successful Jolliet drilling program were a result of THOROUGH PRE-PLANNING through superior teamwork between operations and engineering personnel and the inclusion of state of the art. The detailed drilling rig specification, steerabledirectional drilling motors, MWD tools with downhole torque and bit weight capabilities, development of an All oil Mud System utilizing LVT base oil, implementation ofimproved hole cleaning techniques areindicative of the detailed approach taken throughout the drilling program. Personal computing capabilities played a major part in the ability to thoroughly analyze and optimize drilling. Each of these elements were continually fine tuned and adjusted through a detailed system of concurrent critique.
TEAM ORGANIZATION
The Jolliet drilling team was formed well in advance of drilling template installation. Personnel from many different departments within the company were pulled together to form the team. Company management made a committment to ensure that the expertise ofindividuals within the company was utilized to the fullest. The team was organized with a central point of focus around the DrillingSupervisor. All planning and optimization was funnelled to and from the DrillingSupervisor for implementation as illustrated in Figure 1.
PROJECT OBJECTIVES
The first step in assurance of a successful drilling program was to clearly define the MISSION of the drilling team and the program. Clear and concise objectives were defined.
Safety
From the outset safety was identified ag the team's most important priority. The safety of the drilling operation and all team members was considered first when planning and executing all operations. Protection of the environment and compliance with governmental regulations were addressed and included within the umbrella of the "Safety Objective".
Well Productivity
Maximum well productivity, as a result of minimum exposure to formation damage during drilling operations, was considered paramount. Drilling practices as well as the mud system and additives were closely scrutinized to ensure minimum formation damage.
Primary cementation
Good primary cement jobs were identified as an absolute requirement for the efficient depletion of the Jolliet reservoirs. Primary cementation techniques were fined tuned for integration with subsea wellheads. This of course resulted in a minimum requirement for remedial cement jobs both during and after drilling operations.
Title: Optimization of Deepwater Template Drilling
Description:
ABSTRACT
This paper describes the methods and technologies employed during the drilling of the Jolliet Development wells.
The Jolliet development wells were drilled from a subsea drilling template in water depth of 1760 feet.
INTRODUCTION
The field is currently producing from the first Tension Leg Well Platform (TLWP) in the Gulf of Mexico which was installed after completion of the drilling phase.
Jolliet development drilling operations were conducted between July 1987 and May 1989 after installation of the drilling template.
The drilling performance attained on this project was outstanding when compared with other wells drilled in this type of frontier environment.
This paper presents an overview of the methods and equipment used to optimize deepwater drilling from a template and therefore ultimately realize substantial savings.
Key elements of the successful Jolliet drilling program were a result of THOROUGH PRE-PLANNING through superior teamwork between operations and engineering personnel and the inclusion of state of the art.
The detailed drilling rig specification, steerabledirectional drilling motors, MWD tools with downhole torque and bit weight capabilities, development of an All oil Mud System utilizing LVT base oil, implementation ofimproved hole cleaning techniques areindicative of the detailed approach taken throughout the drilling program.
Personal computing capabilities played a major part in the ability to thoroughly analyze and optimize drilling.
Each of these elements were continually fine tuned and adjusted through a detailed system of concurrent critique.
TEAM ORGANIZATION
The Jolliet drilling team was formed well in advance of drilling template installation.
Personnel from many different departments within the company were pulled together to form the team.
Company management made a committment to ensure that the expertise ofindividuals within the company was utilized to the fullest.
The team was organized with a central point of focus around the DrillingSupervisor.
All planning and optimization was funnelled to and from the DrillingSupervisor for implementation as illustrated in Figure 1.
PROJECT OBJECTIVES
The first step in assurance of a successful drilling program was to clearly define the MISSION of the drilling team and the program.
Clear and concise objectives were defined.
Safety
From the outset safety was identified ag the team's most important priority.
The safety of the drilling operation and all team members was considered first when planning and executing all operations.
Protection of the environment and compliance with governmental regulations were addressed and included within the umbrella of the "Safety Objective".
Well Productivity
Maximum well productivity, as a result of minimum exposure to formation damage during drilling operations, was considered paramount.
Drilling practices as well as the mud system and additives were closely scrutinized to ensure minimum formation damage.
Primary cementation
Good primary cement jobs were identified as an absolute requirement for the efficient depletion of the Jolliet reservoirs.
Primary cementation techniques were fined tuned for integration with subsea wellheads.
This of course resulted in a minimum requirement for remedial cement jobs both during and after drilling operations.
Related Results
The Future of Regulations for the Deepwater GOM
The Future of Regulations for the Deepwater GOM
Abstract
Deepwater oil and gas activities in the U.S. Gulf of Mexico Outer ContinentalShelf (OCS) are regulated by the Minerals Management Service (MMS). The leve...
Experimental Investigation of Permeability and Fluid Loss Properties of Water Based Mud Under High Pressure-High Temperature Conditions
Experimental Investigation of Permeability and Fluid Loss Properties of Water Based Mud Under High Pressure-High Temperature Conditions
Drilling in deeper formations and in high pressure and high temperature (HPHT) environments is a new frontier for the oil industry. Fifty years ago, no one would have imagined dril...
New Tendon and Riser Technologies Improve TLP Competitiveness in Ultra- Deepwater
New Tendon and Riser Technologies Improve TLP Competitiveness in Ultra- Deepwater
Abstract
The extensive industry experience with design, fabrication, installation, and operation of TLPs in water depths up to 4,000 ft has demonstrated the flexi...
Planning Drilling Fluid Programs in Southeast Asia
Planning Drilling Fluid Programs in Southeast Asia
Planning the drilling fluids program is one of the most important steps in Planning the drilling fluids program is one of the most important steps in preparation for the drilling o...
Deepwater Riserless Mud Return System for Dual Gradient Tophole Drilling
Deepwater Riserless Mud Return System for Dual Gradient Tophole Drilling
Abstract
The paper presents results of a large-scale field trial conducted from a deepwater semi submersible drilling vessel offshore Sabah, Malaysia, September 2008...
Casing Drilling with Retrievable Drilling Assemblies
Casing Drilling with Retrievable Drilling Assemblies
Abstract
Retrievable Casing Drilling* tools have been used to drill more than 600,000 ft of hole in over 120 wells encompassing six casing sizes ranging from 4-1/...
Real – Time Geomechanics: Applications to Deepwater Drilling
Real – Time Geomechanics: Applications to Deepwater Drilling
Abstract
Lithologies under deepwater conditions usually show relatively reduced effective stress, due to the reduced lithostatic column. This translates into relativ...
Application of Multiphase Flow Methods to Horizontal Underbalanced Drilling
Application of Multiphase Flow Methods to Horizontal Underbalanced Drilling
Abstract
Multiphase flow can be present in all aspects of underbalanced drilling. This paper outlines the ways in which multiphase flow pressure loss calculations...