Javascript must be enabled to continue!
The Jacking System and Simulator for Mating the Hutton TLP
View through CrossRef
ABSTRACT
The Hutton TLP Deck/ Hull mating and weldout operation required the use of a sophisticated and unique hydraulic jacking system. The system was designed to accommodate the relative vertical and horizontal motions and the dynamic forces between the Deck and Hull during mating. Obtaining the correct load distribution between each of the 96 jack locations during mating and weldout was a fundamental requirement on which the Deck and Hull structural designs were based and represented an operation beyond the current level of experience.
To train the Jacking System operators, a Simulator was custom-built. The simulator modeled the interaction of the ballast systems, the Deck and Hull structures, the impact dampers and the Jacking System. Procedures were developed using this facility prior to its use for hands-on training of the Jacking Teams and full mating operation rehearsals with the Ballast Supervisors.
The installation, setting-to-work and commissioning of the Jacking System is described. The paper concludes with the mating and weld out operation at the offshore site.
INTRODUCTION
The Tension Leg Platform for the Hutton Field was designed for separate fabrication of the Deck and Hull and their subsequent mating at an offshore site.
To ensure correct load distribution during the mating and permanent connection of the two structures, special equipment would be required, the most important being the Jacking System (reference 1).
The operation of the Jacking System, in concert with the impact dampers and the Hull and Barge ballast systems, would require comprehensive training and rehearsal. A Simulator was considered the most effective means of achieving this.
The major phases of the work are described in the following sequence:PHASE I - The Jacking SystemPHASE II - The SimulatorPHASE III - Engineering Review and Procedure DevelopmentPHASE IV - TrainingPHASE V - Installation, Setting-to-Work, Commissioning and Final CheckoutPHASE VI - Operation
PHASE I - THE JACKING SYSTEM
The Jacking System contract was awarded in November 81. Delivery was made 10 months later in September 82.
SPECIFICATION
Deck and Hull Structural Design
The TLP Deck is supported at four locations on each of the six Hull columns (ref. Figure 1). This configuration results in a light design, while providing a joint with adequate shear and bending moment strength.
For each joint, target were calculated, which for the full Deck weight distribution would produce the lowest stress levels overall. The TLP structural design assumed that these target loads would be achievable to within ±10% at mating and during weldout. During load transfer, the tolerances would be wider. (reference 2.)
The change of relative vertical deflection between the Deck and Hull at the jack locations during load transfer could be as much as 70 mm. The relative horizontal movements between Deck and Hull during load transfer could be as much as 102 mm.
Title: The Jacking System and Simulator for Mating the Hutton TLP
Description:
ABSTRACT
The Hutton TLP Deck/ Hull mating and weldout operation required the use of a sophisticated and unique hydraulic jacking system.
The system was designed to accommodate the relative vertical and horizontal motions and the dynamic forces between the Deck and Hull during mating.
Obtaining the correct load distribution between each of the 96 jack locations during mating and weldout was a fundamental requirement on which the Deck and Hull structural designs were based and represented an operation beyond the current level of experience.
To train the Jacking System operators, a Simulator was custom-built.
The simulator modeled the interaction of the ballast systems, the Deck and Hull structures, the impact dampers and the Jacking System.
Procedures were developed using this facility prior to its use for hands-on training of the Jacking Teams and full mating operation rehearsals with the Ballast Supervisors.
The installation, setting-to-work and commissioning of the Jacking System is described.
The paper concludes with the mating and weld out operation at the offshore site.
INTRODUCTION
The Tension Leg Platform for the Hutton Field was designed for separate fabrication of the Deck and Hull and their subsequent mating at an offshore site.
To ensure correct load distribution during the mating and permanent connection of the two structures, special equipment would be required, the most important being the Jacking System (reference 1).
The operation of the Jacking System, in concert with the impact dampers and the Hull and Barge ballast systems, would require comprehensive training and rehearsal.
A Simulator was considered the most effective means of achieving this.
The major phases of the work are described in the following sequence:PHASE I - The Jacking SystemPHASE II - The SimulatorPHASE III - Engineering Review and Procedure DevelopmentPHASE IV - TrainingPHASE V - Installation, Setting-to-Work, Commissioning and Final CheckoutPHASE VI - Operation
PHASE I - THE JACKING SYSTEM
The Jacking System contract was awarded in November 81.
Delivery was made 10 months later in September 82.
SPECIFICATION
Deck and Hull Structural Design
The TLP Deck is supported at four locations on each of the six Hull columns (ref.
Figure 1).
This configuration results in a light design, while providing a joint with adequate shear and bending moment strength.
For each joint, target were calculated, which for the full Deck weight distribution would produce the lowest stress levels overall.
The TLP structural design assumed that these target loads would be achievable to within ±10% at mating and during weldout.
During load transfer, the tolerances would be wider.
(reference 2.
)
The change of relative vertical deflection between the Deck and Hull at the jack locations during load transfer could be as much as 70 mm.
The relative horizontal movements between Deck and Hull during load transfer could be as much as 102 mm.
Related Results
Field Test and Numerical Simulation of Jacking Force of Reinforced Concrete Pipe Jacking in Long Distance Composite Formation
Field Test and Numerical Simulation of Jacking Force of Reinforced Concrete Pipe Jacking in Long Distance Composite Formation
Jacking force is one of the important parameters of pipe jacking construction. In order to analyze the mechanical properties of large-diameter reinforced concrete pipe jacking cons...
New Directions in TLP Technology
New Directions in TLP Technology
Abstract
Of the many deepwater platform concepts that were developed as deepwater platform technology matured, the TLP has been the most frequently selected for d...
Auger TLP Well System Challenges and Innovations
Auger TLP Well System Challenges and Innovations
ABSTRACT
The Auger TLP well system has successfully employed novel features to satisfy challenging design requirements of drilling, completing, and producing near...
Challenges of TLP Installation Offshore Brazil
Challenges of TLP Installation Offshore Brazil
Abstract
Installation of a Tension Leg Platform comprises distinct phases, all of which can provide special challenges when considering locating a TLP in a fronti...
CryoSeek identification of glycofibrils with diverse compositions and structural assemblies
CryoSeek identification of glycofibrils with diverse compositions and structural assemblies
Abstract
Last year, we reported CryoSeek, a research strategy that employs cryo-electron microscopy (cryo-EM) to discover novel bio-entities from any accessible source,...
Research and Development of a Three-Piece Tendon for a TLP
Research and Development of a Three-Piece Tendon for a TLP
Abstract
Research and development of TLP tendon is described. Forged tendons are in actual use but their cost increases rapidly as the diameter becomes greater.
...
An Integrated Motion and Structural Analysis for Tension Leg Platforms
An Integrated Motion and Structural Analysis for Tension Leg Platforms
Abstract
The tension leg platform (TLP) concept has become increasingly popular as oil reservoirs, once considered too deep to recover, now contain the financial ...
Hutton TLP Mooring System
Hutton TLP Mooring System
ABSTRACT
The tension leg platform (TLP) which is being developed for the Hutton Field in the North Sea is the first application of this new platform concept which...


