Javascript must be enabled to continue!
Monitoring Offshore Lift Dynamics
View through CrossRef
ABSTRACT
This paper illustrates the significance of lift dynamic aspects observed during two major offshore heavy lift operations performed in 1991. Extensive offshore measurements provided further knowledge related to the dynamic behaviour of heavy lift systems offshore. The contribution of lift dynamics to the overall response in the medium frequency range was found to be of similar magnitude as the response in the wave frequency range. Initial correlation studies with computer models show that this aspect was underestimated by the analyses.
INTRODUCTION
The large semi submersible crane vessels (SSCVS), currently active on the heavy lift market, have been specifically designed and equipped to perform very heavy lift operations at sea, even in rather severe environmental conditions. The lift records of the SSCVS show clearly the trend of increasing lift weight versus time [1,2]. This fact is not surprising as the market takes full advantage of the available lifting capacity. Simultaneously with the lift weight, the dimensions of the lifted structures have also increased significantly, resulting in minimal clearances between the load and the crane vessel.
For loads which are relatively light when compared with the displacement of the crane vessel, the wave induced motion behaviour of the SSCV is almost independent of the motion behaviour of the load suspended from the cranes, Furthermore, the relative motions of the load with respect to the crane vessel, thus also the clearance may be controlled to some extent by means of control lines operated from tug winches. For relatively heavy loads, however, the wave induced motion behaviour of the SSCV can be strongly affected by the motion behaviour of the load, and vice versa [23]. The dynamic motion behaviour of both the crane vessel and the load, as well as of a cargo barge in case it is involved in the lifting operations, are in fact coupled. The crane vessel, the load and the cargo barge together form one integrated dynamic system.
Considering the phenomenon described above, it becomes evident that lift dynamics play an important role in the feasibility and workability of a lift operation involving a relatively heavy load, Workability restrictions related to motions of the crane vessel and the load are therefore dependent upon the effects of lift dynamics. Furthermore, the clearance between load and crane vessel or the tension variation in the hoisting wires or the slings, can become limiting factors of a lift operation also due to the phenomenon lift dynamics. Maintaining the minimal clearance between crane vessel and lifted load throughout the lift operation has become of vital importance with respect to the overall safety.
In 1985, The Netherlands, Shell Imitational Petroleum Maatschappij (SJ.PM), The Hague, and the Maritime Research Institute Netherlands (MARIN), Wageningen, commenced research work with respect to lift dynamics, which was focused on the development of a lift simulation computer program (LIFSIM) able to calculate the dynamic motion behaviour of crane vessel, load and cargo barge during the lift operation [4,5,6]. Extensive model tests in MARIN?s sea keeping basins were carried out, additionally sponsored by Heerema Engineering Service BV, Leiden, for verification and validation of the LIFSDVI program.
Title: Monitoring Offshore Lift Dynamics
Description:
ABSTRACT
This paper illustrates the significance of lift dynamic aspects observed during two major offshore heavy lift operations performed in 1991.
Extensive offshore measurements provided further knowledge related to the dynamic behaviour of heavy lift systems offshore.
The contribution of lift dynamics to the overall response in the medium frequency range was found to be of similar magnitude as the response in the wave frequency range.
Initial correlation studies with computer models show that this aspect was underestimated by the analyses.
INTRODUCTION
The large semi submersible crane vessels (SSCVS), currently active on the heavy lift market, have been specifically designed and equipped to perform very heavy lift operations at sea, even in rather severe environmental conditions.
The lift records of the SSCVS show clearly the trend of increasing lift weight versus time [1,2].
This fact is not surprising as the market takes full advantage of the available lifting capacity.
Simultaneously with the lift weight, the dimensions of the lifted structures have also increased significantly, resulting in minimal clearances between the load and the crane vessel.
For loads which are relatively light when compared with the displacement of the crane vessel, the wave induced motion behaviour of the SSCV is almost independent of the motion behaviour of the load suspended from the cranes, Furthermore, the relative motions of the load with respect to the crane vessel, thus also the clearance may be controlled to some extent by means of control lines operated from tug winches.
For relatively heavy loads, however, the wave induced motion behaviour of the SSCV can be strongly affected by the motion behaviour of the load, and vice versa [23].
The dynamic motion behaviour of both the crane vessel and the load, as well as of a cargo barge in case it is involved in the lifting operations, are in fact coupled.
The crane vessel, the load and the cargo barge together form one integrated dynamic system.
Considering the phenomenon described above, it becomes evident that lift dynamics play an important role in the feasibility and workability of a lift operation involving a relatively heavy load, Workability restrictions related to motions of the crane vessel and the load are therefore dependent upon the effects of lift dynamics.
Furthermore, the clearance between load and crane vessel or the tension variation in the hoisting wires or the slings, can become limiting factors of a lift operation also due to the phenomenon lift dynamics.
Maintaining the minimal clearance between crane vessel and lifted load throughout the lift operation has become of vital importance with respect to the overall safety.
In 1985, The Netherlands, Shell Imitational Petroleum Maatschappij (SJ.
PM), The Hague, and the Maritime Research Institute Netherlands (MARIN), Wageningen, commenced research work with respect to lift dynamics, which was focused on the development of a lift simulation computer program (LIFSIM) able to calculate the dynamic motion behaviour of crane vessel, load and cargo barge during the lift operation [4,5,6].
Extensive model tests in MARIN?s sea keeping basins were carried out, additionally sponsored by Heerema Engineering Service BV, Leiden, for verification and validation of the LIFSDVI program.
Related Results
Fundamental study on rope vibration suppression by middle transfer floor using risk information
Fundamental study on rope vibration suppression by middle transfer floor using risk information
Lifts are essential for means of vertical transportation. Recently, the lifts installed in the high-rise buildings are long travel, thus the lift ropes are becoming longer. The nat...
Gas Lift - Past & Future
Gas Lift - Past & Future
Abstract
This paper will describe the evolution of gas lift systems over the past few decades, making parallels with other artificial lift technologies (ESP, SRP, an...
Pig Lift: A New Artificial Lift Method
Pig Lift: A New Artificial Lift Method
Abstract
Artificial lift of oil wells is a fairly broad subject. There are many different methods available but in a few cases none of them turns out to be a fit ...
Investigation of multiple lift-tube air-lift pumps: Experimental evaluation and predictive modelling
Investigation of multiple lift-tube air-lift pumps: Experimental evaluation and predictive modelling
Due to limited pumping capability the commercial use of the single lift-tube air-lift pump has been confined to very little applications. To overcome the limited pumping capability...
Artificial Lift Selection Strategy to Maximize Unconventional Oil and Gas Assets Value
Artificial Lift Selection Strategy to Maximize Unconventional Oil and Gas Assets Value
Abstract
The challenges of producing and lifting unconventional oil and gas economically is no doubt the most daunting phase of unconventional oil and gas developmen...
The Future of Plunger Lift Control Using Artificial Intelligence
The Future of Plunger Lift Control Using Artificial Intelligence
Abstract
Plunger lift is a form of artificial lift popular due to its low installation and operating costs. Historically plunger lift was reserved for low producing ...
Alternative Offshore Foundation Installation Methods
Alternative Offshore Foundation Installation Methods
Abstract
According to the European Wind Energy Association (EWEA) in the first six months of 2012, Europe installed and fully grid connected 132 offshore wind tur...
High Pressure Gas-Lift: Is Industry Missing a Potentially Huge Application to Horizontal Wells?
High Pressure Gas-Lift: Is Industry Missing a Potentially Huge Application to Horizontal Wells?
AbstractTraditional gas-lift technology blossomed between 1929 and 1945, with about 25000 patents being issued during this time (Wikipedia 2017). Minimal innovation other than impr...

