Lula Alto - Strategy and Execution of a Megaproject in Deep Water Santos Basin Pre-Salt
View through CrossRef
Abstract
This article presents the successful history of Lula Alto Project, one of the development modules of Lula giant field, located in Santos Basin pre-salt at southeast Brazil at a 2,120 meters water depth. The project is currently producing at its maximum oil capacity, considering operational performance, achieved only 9 months from first oil. This is the fifth module of Lula field, which modular development allowed drainage plan and subsea layout optimization.
The article will present the reservoir conceptual model, drainage plan optimization, information acquisition strategy and modular development insights; the subsea layout optimization that led to a minimum flowline length per well; twin FPSO construction strategy; project development and fast ramp-up and the challenges faced during the first year of production. It will also address integrity and maintenance management, aiming a secure and sustainable operation, and well construction highlights.
The leased FPSO Cidade de Maricá initiated production in February 2016, and the project strategy was to carbon copy FPSO Cidade de Ilhabela engineering (this FPSO is also producing in pre-salt), reducing design costs and schedule. Construction phase strategy was to build two identical FPSO's in parallel, FPSO's Cidade de Maricá and Cidade de Saquarema, with a planned 2 months schedule delivery gap. Suppliers and construction sites were the same, allowing cost reduction, construction risks mitigation and supply chain optimization. After one year of production, many challenges had to be surpassed, and all lessons learned were important for a solid ramp-up achievement and sustainable peak production.
Title: Lula Alto - Strategy and Execution of a Megaproject in Deep Water Santos Basin Pre-Salt
Description:
Abstract
This article presents the successful history of Lula Alto Project, one of the development modules of Lula giant field, located in Santos Basin pre-salt at southeast Brazil at a 2,120 meters water depth.
The project is currently producing at its maximum oil capacity, considering operational performance, achieved only 9 months from first oil.
This is the fifth module of Lula field, which modular development allowed drainage plan and subsea layout optimization.
The article will present the reservoir conceptual model, drainage plan optimization, information acquisition strategy and modular development insights; the subsea layout optimization that led to a minimum flowline length per well; twin FPSO construction strategy; project development and fast ramp-up and the challenges faced during the first year of production.
It will also address integrity and maintenance management, aiming a secure and sustainable operation, and well construction highlights.
The leased FPSO Cidade de Maricá initiated production in February 2016, and the project strategy was to carbon copy FPSO Cidade de Ilhabela engineering (this FPSO is also producing in pre-salt), reducing design costs and schedule.
Construction phase strategy was to build two identical FPSO's in parallel, FPSO's Cidade de Maricá and Cidade de Saquarema, with a planned 2 months schedule delivery gap.
Suppliers and construction sites were the same, allowing cost reduction, construction risks mitigation and supply chain optimization.
After one year of production, many challenges had to be surpassed, and all lessons learned were important for a solid ramp-up achievement and sustainable peak production.
Related Results
Luiz Inácio Lula da Silva and the Brazilian Workers’ Party (PT)
Luiz Inácio Lula da Silva and the Brazilian Workers’ Party (PT)
Luiz Inácio Lula da Silva (b. Caetés, Pernambuco, Brazil, October 27, 1945) was born in severe poverty in the Brazilian northeast. “Lula” was a nickname which he legalized as an ad...
Thermal Anomalies Around Evolving Salt Sheets
Thermal Anomalies Around Evolving Salt Sheets
ABSTRACT
The thermal conductivity of salt is about a factor three larger than that of sediments at sediment surface temperatures. The increase of sedimentary ther...
Analysis of Sticking and the Releasing Technology of the Composite Gypsum-Salt Rock in the Tarim Basin
Analysis of Sticking and the Releasing Technology of the Composite Gypsum-Salt Rock in the Tarim Basin
ABSTRACT:
The Kuqa FoId-Thrust BeIt in Tarim Basin is verified as the most challenging geological structure for ultra-deep hydrocarbon development in China onshor...
The Integrated Drilling Technology to Solve Well Construction Challenges in the Pre-Salt Reservoirs of Ultra-Deep Water
The Integrated Drilling Technology to Solve Well Construction Challenges in the Pre-Salt Reservoirs of Ultra-Deep Water
Abstract
The well construction operation in the pre-salt reservoirs of Santos basin faced great challenges such as the drill string stuck in big-thickness salt forma...
First Look-Ahead VSP Guided Salt Dome Island Exploration Well Drilling in the UAE
First Look-Ahead VSP Guided Salt Dome Island Exploration Well Drilling in the UAE
Abstract
An exploration well offshore UAE, which was the first of it's kind, was planned to be drilled from an island and within salt dome. Well planning was based o...
Comparison of Distribution Procedures in Blended Finance
Comparison of Distribution Procedures in Blended Finance
This paper is devoted to the blended (joint) finance mechanism of a megaproject consisting of several projects. One part of the megaproject budget comes from the megaproject manage...
Use of Formation Water and Associated Gases and their Simultaneous Utilization for Obtaining Microelement Concentrates Fresh Water and Drinking Water
Use of Formation Water and Associated Gases and their Simultaneous Utilization for Obtaining Microelement Concentrates Fresh Water and Drinking Water
Abstract Purpose: The invention relates to the oil industry, inorganic chemistry, in particular, to the methods of complex processing of formation water, using flare gas of oil and...
Climate change modeling for water resources management : Tana Sub-Basin, Ethiopia
Climate change modeling for water resources management : Tana Sub-Basin, Ethiopia
This study, conducted in the Tana Sub-basin, Ethiopia, aimed to model the impact of climate
change on water resources management. The Soil and Water Assessment Tool (SWAT), SPI
gen...