Effective HSE-MS Implementation: A Success Story of Ikike Project 6 Million + Manhours with NO LTI
View through CrossRef
Abstract
Ikike is an undeveloped field located 20km offshore and approximately 15km north of the Amenam complex in 20m water depth. The Amenam field which has been producing since July 2003 is located approximately 60km southeast of the NLNG Plant and 95km Southeast of Port Harcourt and the water depth range from 30 to 40 meters.
The Ikike project leverages on the existing Amenam facilities to keep costs low and is designed to minimize greenhouse gas emissions. Estimated at less than 4kg CO2e/boe, they will contribute to reducing the average carbon intensity of TotalEnergies’ upstream portfolio.
Given to the inherent hazard and risk associated with Oil & Gas projects from Conceptual phase to Front End Engineering Design studies, to fabrication and constructions as well as installation and commissioning, HSE management system becomes pivotal to driving an incident free project phases.
This Paper focuses on the sound application of the Project HSE Management strategy, plan and system which comprises a set of components that includes; Project HSE Policy and HSE objectives,Identification of the risk involved in the Project activities,An organization within which the HSE responsibilities are clearly defined,Competent and trained personnel,Internal and external communication.Practises and processes formally defined in the project documentation,Evaluation and reviews of Project HSE performances,Correctives action plans and periodic management reviews,An HSE audit program
All of these were deployed during the Ikike project towards demonstrating and providing a means of anticipating and controlling the risks involved in the Project which had continuously improved the HSE performances all through the project in conformance with project improvement goals set for the Project.
Several other proactive and reactive measures were taken towards ensuring a success story of Ikike Project with a total of 6milliom man hours of No Lost Time Incident.
Title: Effective HSE-MS Implementation: A Success Story of Ikike Project 6 Million + Manhours with NO LTI
Description:
Abstract
Ikike is an undeveloped field located 20km offshore and approximately 15km north of the Amenam complex in 20m water depth.
The Amenam field which has been producing since July 2003 is located approximately 60km southeast of the NLNG Plant and 95km Southeast of Port Harcourt and the water depth range from 30 to 40 meters.
The Ikike project leverages on the existing Amenam facilities to keep costs low and is designed to minimize greenhouse gas emissions.
Estimated at less than 4kg CO2e/boe, they will contribute to reducing the average carbon intensity of TotalEnergies’ upstream portfolio.
Given to the inherent hazard and risk associated with Oil & Gas projects from Conceptual phase to Front End Engineering Design studies, to fabrication and constructions as well as installation and commissioning, HSE management system becomes pivotal to driving an incident free project phases.
This Paper focuses on the sound application of the Project HSE Management strategy, plan and system which comprises a set of components that includes; Project HSE Policy and HSE objectives,Identification of the risk involved in the Project activities,An organization within which the HSE responsibilities are clearly defined,Competent and trained personnel,Internal and external communication.
Practises and processes formally defined in the project documentation,Evaluation and reviews of Project HSE performances,Correctives action plans and periodic management reviews,An HSE audit program
All of these were deployed during the Ikike project towards demonstrating and providing a means of anticipating and controlling the risks involved in the Project which had continuously improved the HSE performances all through the project in conformance with project improvement goals set for the Project.
Several other proactive and reactive measures were taken towards ensuring a success story of Ikike Project with a total of 6milliom man hours of No Lost Time Incident.
Related Results
Quantifying HSE Culture – A Leading Indicator of HSE Performance: An Energy Industry Case Study
Quantifying HSE Culture – A Leading Indicator of HSE Performance: An Energy Industry Case Study
Abstract
This paper presents the results of an HSE Culture survey administered to employees and managers at an energy company. HSE culture can be defined as the valu...
INTEGRATING ADVANCED TECHNOLOGIES FOR ENHANCED HSE MANAGEMENT IN THE FMCG SECTOR
INTEGRATING ADVANCED TECHNOLOGIES FOR ENHANCED HSE MANAGEMENT IN THE FMCG SECTOR
The Fast-Moving Consumer Goods (FMCG) sector operates in a dynamic environment, facing numerous challenges in maintaining Health, Safety, and Environment (HSE) standards while meet...
HSE Management for China Offshore Drilling Project
HSE Management for China Offshore Drilling Project
Abstract
According to the International Drilling HSE (Health, Safety, and Environment) management standards and advanced management experience as well as hazard m...
Long-term outcome of severe herpes simplex encephalitis: a population-based observational study
Long-term outcome of severe herpes simplex encephalitis: a population-based observational study
Abstract
Introduction
Herpes simplex encephalitis (HSE) is a rare disease with a poor prognosis. No recent evaluation of hospital incidence, acute m...
Exploring Project Success Factors in Developing Countries: Focus on Morocco
Exploring Project Success Factors in Developing Countries: Focus on Morocco
Although project management (PM) literature has addressed project success, attention has not been paid to statistically testing the relationship between various critical success fa...
Video Analytics for Workplace Safety
Video Analytics for Workplace Safety
Abstract
The present paper describes how an artificial intelligence-based video analytics system was implemented to improve workplace safety in a construction site i...
Quality in HSE Management Systems
Quality in HSE Management Systems
Abstract
This paper describes Quality's role in HSE systems and provides detail information on one offshore drilling contractor's HSE system through the company's qu...
PROJECT MANAGEMENT SYSTEM AT AN ENTERPRISE: THE FOUNDATIONS OF EFFECTIVE FORMATION
PROJECT MANAGEMENT SYSTEM AT AN ENTERPRISE: THE FOUNDATIONS OF EFFECTIVE FORMATION
The article examines the principles of effective formation of a project management system at an enterprise. In the modern environment, project management standards and management i...