Javascript must be enabled to continue!
Shoreline Storage Tunnel Shafts and Near Surface Structures Support of Excavation
View through CrossRef
The Shoreline Storage Tunnel (SST) Project in Cleveland, Ohio is part of EPA-mandated Project Clean Lake, Northeast Ohio Regional Sewer District’s program designed to reduce pollution in Lake Erie by 4 billion gallons per year over the next 25 years. The $3-billion program includes construction of large ‑diameter storage/conveyance tunnels, shafts at key combined sewer overflow (CSO) pick-up points, underground pump stations, improvements to wastewater treatment plant capacity and treatment, and expansion of green infrastructure. When completed, SST will comprise over 2.5 miles of 23-ft-diameter tunnel installed 87 to 135 ft below ground. The storage tunnel will manage higher flow volumes and keep stormwater out of the combined sewer system to reduce overflow occurrences.
As part of the project, three deep shafts (SST-1, SST-2, and SST-3) were constructed to provide access to the tunnel, launch and retrieve the tunnel boring machine, and provide ventilation. Several additional structures will serve as diversion structures, drop manholes, gate structures or gate control structures. A short connection tunnel will connect the SST to the Dugway Storage Tunnel, which was completed earlier in the Project Clean Lake program.
The shaft support of excavation system was designed using diaphragm wall methods. This innovative solution provided watertight, continuous shafts keyed into rock that significantly reduces risks as compared to traditional secant piles combined with a rib and liner plate system. Unreinforced concrete diaphragm walls were constructed using mechanical clamshells for shafts SST-2 and SST-3, and clamshell equipment and a hydromill were used for SST-1. All the SST shafts were lined with reinforced cast-in-place concrete and include baffle drop structures. Outside of the SST-1 and SST-3 shafts, several ground improvement blocks were installed using overlapping cement bentonite panels. These ground improvement zones were created to provide increased strength and water cutoff in the soil at locations where the TBM broke into and out of the shafts.
A gate structure attached to both the SST-2 and SST-3 diaphragm wall shafts was supported by a soldier pile reinforced cement bentonite wall. The design of the gate structure SOE was handled collaboratively with the owner and their engineer, McMillen Jacobs Associates. The team worked together to resolve challenges surrounding tying in the originally designed bracing scheme to the new SOE method and methods for exposing and supporting a 100-year-old existing brick sewer, as well as excavating through an abandoned brick sewer.
This case study will present the design for the shafts and gate structures, the diaphragm wall construction methods, the unique challenges overcome for each shaft, and the benefits of the final solution to the overall project.
Deep Foundations Institute
Title: Shoreline Storage Tunnel Shafts and Near Surface Structures Support of Excavation
Description:
The Shoreline Storage Tunnel (SST) Project in Cleveland, Ohio is part of EPA-mandated Project Clean Lake, Northeast Ohio Regional Sewer District’s program designed to reduce pollution in Lake Erie by 4 billion gallons per year over the next 25 years.
The $3-billion program includes construction of large ‑diameter storage/conveyance tunnels, shafts at key combined sewer overflow (CSO) pick-up points, underground pump stations, improvements to wastewater treatment plant capacity and treatment, and expansion of green infrastructure.
When completed, SST will comprise over 2.
5 miles of 23-ft-diameter tunnel installed 87 to 135 ft below ground.
The storage tunnel will manage higher flow volumes and keep stormwater out of the combined sewer system to reduce overflow occurrences.
As part of the project, three deep shafts (SST-1, SST-2, and SST-3) were constructed to provide access to the tunnel, launch and retrieve the tunnel boring machine, and provide ventilation.
Several additional structures will serve as diversion structures, drop manholes, gate structures or gate control structures.
A short connection tunnel will connect the SST to the Dugway Storage Tunnel, which was completed earlier in the Project Clean Lake program.
The shaft support of excavation system was designed using diaphragm wall methods.
This innovative solution provided watertight, continuous shafts keyed into rock that significantly reduces risks as compared to traditional secant piles combined with a rib and liner plate system.
Unreinforced concrete diaphragm walls were constructed using mechanical clamshells for shafts SST-2 and SST-3, and clamshell equipment and a hydromill were used for SST-1.
All the SST shafts were lined with reinforced cast-in-place concrete and include baffle drop structures.
Outside of the SST-1 and SST-3 shafts, several ground improvement blocks were installed using overlapping cement bentonite panels.
These ground improvement zones were created to provide increased strength and water cutoff in the soil at locations where the TBM broke into and out of the shafts.
A gate structure attached to both the SST-2 and SST-3 diaphragm wall shafts was supported by a soldier pile reinforced cement bentonite wall.
The design of the gate structure SOE was handled collaboratively with the owner and their engineer, McMillen Jacobs Associates.
The team worked together to resolve challenges surrounding tying in the originally designed bracing scheme to the new SOE method and methods for exposing and supporting a 100-year-old existing brick sewer, as well as excavating through an abandoned brick sewer.
This case study will present the design for the shafts and gate structures, the diaphragm wall construction methods, the unique challenges overcome for each shaft, and the benefits of the final solution to the overall project.
Related Results
619. Pharmacokinetic-Pharmacodynamic (PK-PD) Target Attainment Analyses to Support Epetraborole Dose Selection for the Treatment of Patients with Mycobacterium avium Complex (MAC) Lung Disease
619. Pharmacokinetic-Pharmacodynamic (PK-PD) Target Attainment Analyses to Support Epetraborole Dose Selection for the Treatment of Patients with Mycobacterium avium Complex (MAC) Lung Disease
Abstract
Background
Epetraborole (EBO) is an orally available, bacterial leucyl transfer RNA synthetase inhibitor that concentra...
LB2306. Population Pharmacokinetic (PPK), Pharmacokinetic/Pharmacodynamic attainment (PTA), and Clinical Pharmacokinetic/Pharmacodynamic (PK/PD) Analyses for Sulbactam-Durlobactam (SUL-DUR) to Support Dose Selection for the Treatment of Acinetobacter baum
LB2306. Population Pharmacokinetic (PPK), Pharmacokinetic/Pharmacodynamic attainment (PTA), and Clinical Pharmacokinetic/Pharmacodynamic (PK/PD) Analyses for Sulbactam-Durlobactam (SUL-DUR) to Support Dose Selection for the Treatment of Acinetobacter baum
Abstract
Background
SUL-DUR is a β-lactam/β-lactamase inhibitor combination in development for the treatment of ABC infections, ...
593. Population Pharmacokinetic Model Development for Epetraborole and Mycobacterium avium Complex (MAC) Lung Disease Patients Using Data from Phase 1 and 2 Studies
593. Population Pharmacokinetic Model Development for Epetraborole and Mycobacterium avium Complex (MAC) Lung Disease Patients Using Data from Phase 1 and 2 Studies
Abstract
Background
Epetraborole (EBO), an orally available bacterial leucyl transfer RNA synthetase inhibitor with potent activ...
592. Impact of Elevated MIC Values on Echinocandin Pharmacokinetic-Pharmacodynamic (PK-PD) Candida glabrata Target Attainment (TA)
592. Impact of Elevated MIC Values on Echinocandin Pharmacokinetic-Pharmacodynamic (PK-PD) Candida glabrata Target Attainment (TA)
Abstract
Background
Given the increasing prevalence of non-albicans Candida species, including C. glabrata and C. auris, which h...
Construction time of secondary lining of ultra-small spacing parallel overlapping tunnel
Construction time of secondary lining of ultra-small spacing parallel overlapping tunnel
Abstract
Due to the unique spatial structure, stress transfer mechanism, and construction disturbance characteristics of ultra-small spacing parallel overlapping tu...
Effects of Excavation Loading Conditions on Ground Deformation and Stress Evolution in Plane-Strain Tunnel Simulations
Effects of Excavation Loading Conditions on Ground Deformation and Stress Evolution in Plane-Strain Tunnel Simulations
The construction of tunnels in urban areas typically affects a large number of buildings and infrastructure. The interaction between ground deformations induced by tunnel excavatio...
Potable Water Sources, Household Hygiene, and Sanitation Practices in Ikpoba Okha LGA, Edo State: Implications for Public Health and Sustainable Water Management
Omoregie, Andrew Edosa.1 Omoregie Abieyuwa Peace2 Okoro, Enyinnaya Okoro.3
1 College of Medi
Potable Water Sources, Household Hygiene, and Sanitation Practices in Ikpoba Okha LGA, Edo State: Implications for Public Health and Sustainable Water Management
Omoregie, Andrew Edosa.1 Omoregie Abieyuwa Peace2 Okoro, Enyinnaya Okoro.3
1 College of Medi
BACKGROUND
Access to potable drinking water and sufficient sanitation continues to be an urgent global concern, particularly in developing regions where con...
Spatiotemporal Analysis of Shoreline Changes in Mobile Bay, U.S.A
Spatiotemporal Analysis of Shoreline Changes in Mobile Bay, U.S.A
Abstract
Shoreline changes affect coastal communities by altering ecosystems and storm buffers. With the growth of coastal populations, the societal impact of shore...

