Javascript must be enabled to continue!
Self-Installed Deck On Offshore Platform
View through CrossRef
ABSTRACT
This paper attempts to describe the development of "self-installed" decks on offshore platforms.
When North Sea operations first started platform installation was performed by means of conventional derrick barges i however, faced with harsh sea conditions, they did not prove very cost effective and installation was often delayed.
Thus, operators were driven to seek new concepts. Among them, TOTAL CFP, operator on the Frigg pipeline, chose to erect big cranes on bare platforms in order to complete installation. This concept soon proved to be a reliable one as it became far easier to take advantage of narrow windows of good weather than it would have been possible with derrick barges. Moreover, safety was increased.
After a few modifications, this installation scheme can be applied to a wide range of fixed platforms both in rough and calm seas.
In this paper, our intention is to explain why we chose this concept and to give the main results gained from our experience on the field.
INTRODUCTION
Within the scope of the Frigg operations, TOTAL, as operator on the pipeline developed several completely new techniques which involved the installation of lifting devices with a load capacity of 300 t to 800 t on platforms.
Once developed by TOTAL and BUZZICHELLI, these techniques enabled offshore lifting operations to be carried out rapidly in weather conditions which were unsuitable for conventional lifting devices.
APPROACH TO THE NEW CONCEPT
North Sea beginnings
When operations first started in the North Sea, production platforms were equipped by means of conventional derrick barges.
The latter can work in up to half a foot heave but roll is critical, the limitation being between 0.5 and 1° depending on the size of the load. In the North Sea, these thresholds are often over-reached resulting in long waiting for calmer weather and sometimes in postponements of operations for up to 8 months, should they not have been completed before the winter season.
Moreover, safety is sometimes affected. Indeed, once a package has been lifted a cargo barge becomes very lively, which lead to a very tricky situation, as it is impossible to drop the package down either on the platform or back on the cargo barge. Should by any chance, the load then start swinging laterally, it is almost impossible to control.
Big modules and huge barges : some improvement but many disadvantages.
In an attempt to improve North Sea operations huge derrick barges appeared. They could handle large and heavy packages (up to 2 000 tons) in slightly worse sea conditions.
It was agreed that the bigger the modules, the fewer lifts required to install them. This was in fact quite true, but several disadvantages should be pointed out.
Title: Self-Installed Deck On Offshore Platform
Description:
ABSTRACT
This paper attempts to describe the development of "self-installed" decks on offshore platforms.
When North Sea operations first started platform installation was performed by means of conventional derrick barges i however, faced with harsh sea conditions, they did not prove very cost effective and installation was often delayed.
Thus, operators were driven to seek new concepts.
Among them, TOTAL CFP, operator on the Frigg pipeline, chose to erect big cranes on bare platforms in order to complete installation.
This concept soon proved to be a reliable one as it became far easier to take advantage of narrow windows of good weather than it would have been possible with derrick barges.
Moreover, safety was increased.
After a few modifications, this installation scheme can be applied to a wide range of fixed platforms both in rough and calm seas.
In this paper, our intention is to explain why we chose this concept and to give the main results gained from our experience on the field.
INTRODUCTION
Within the scope of the Frigg operations, TOTAL, as operator on the pipeline developed several completely new techniques which involved the installation of lifting devices with a load capacity of 300 t to 800 t on platforms.
Once developed by TOTAL and BUZZICHELLI, these techniques enabled offshore lifting operations to be carried out rapidly in weather conditions which were unsuitable for conventional lifting devices.
APPROACH TO THE NEW CONCEPT
North Sea beginnings
When operations first started in the North Sea, production platforms were equipped by means of conventional derrick barges.
The latter can work in up to half a foot heave but roll is critical, the limitation being between 0.
5 and 1° depending on the size of the load.
In the North Sea, these thresholds are often over-reached resulting in long waiting for calmer weather and sometimes in postponements of operations for up to 8 months, should they not have been completed before the winter season.
Moreover, safety is sometimes affected.
Indeed, once a package has been lifted a cargo barge becomes very lively, which lead to a very tricky situation, as it is impossible to drop the package down either on the platform or back on the cargo barge.
Should by any chance, the load then start swinging laterally, it is almost impossible to control.
Big modules and huge barges : some improvement but many disadvantages.
In an attempt to improve North Sea operations huge derrick barges appeared.
They could handle large and heavy packages (up to 2 000 tons) in slightly worse sea conditions.
It was agreed that the bigger the modules, the fewer lifts required to install them.
This was in fact quite true, but several disadvantages should be pointed out.
Related Results
Snorre TLP Topside Design
Snorre TLP Topside Design
ABSTRACT
This paper gives a brief description of the topside facilities and integrated deck structure for the Snorre TLP which will operate on Block 34/7 in the N...
Smart?Leg Computations Validated During the Ekpe Gas Compression Project Float-over Deck Installation
Smart?Leg Computations Validated During the Ekpe Gas Compression Project Float-over Deck Installation
Abstract
The Smart?Leg system developed by ETPM ensures the shockless float-over installation of heavy fully-commissioned integrated decks on offshore jacket stru...
Structural Aspects Of Snorre Mating
Structural Aspects Of Snorre Mating
ABSTRACT
The deck and the hull of the Snorre TLP were successfully connected South of Stord on the Norwegian westcoast in September 1991. The 28.000 tonnes deck w...
Alternative Offshore Foundation Installation Methods
Alternative Offshore Foundation Installation Methods
Abstract
According to the European Wind Energy Association (EWEA) in the first six months of 2012, Europe installed and fully grid connected 132 offshore wind tur...
Modified Offshore Drilling Operation - Serban Well (Nunukan Block)
Modified Offshore Drilling Operation - Serban Well (Nunukan Block)
Abstract
Serban is an offshore drilling project located in Nunukan Block, Indonesia, approximately 3 km northwest of Bunyu Island, an offshore area with very shal...
First Jack-Up Production Platform In North Sea
First Jack-Up Production Platform In North Sea
ABSTRACT
This paper describes the platform design engineering aspects of Amoco's jack-up gas production platform which was installed in August, 1972. It is the fi...
Mobile Bay Project Float-On Deck Installations
Mobile Bay Project Float-On Deck Installations
ABSTRACT
A float-on deck mating procedure was successfully used instead of a conventional derrick barge lift for installation of the integrated topsides on three ...
Prospects for Offshore Petroleum Resources
Prospects for Offshore Petroleum Resources
EXTENDED ABSTRACT
Extending the geographic scope of offshore exploration has traditionally been perceived as the frontier for offshore petroleum development. Corr...

