Javascript must be enabled to continue!
Self-Installed Deck On Offshore Platform
View through CrossRef
ABSTRACT
This paper attempts to describe the development of "self-installed" decks on offshore platforms.
When North Sea operations first started platform installation was performed by means of conventional derrick barges i however, faced with harsh sea conditions, they did not prove very cost effective and installation was often delayed.
Thus, operators were driven to seek new concepts. Among them, TOTAL CFP, operator on the Frigg pipeline, chose to erect big cranes on bare platforms in order to complete installation. This concept soon proved to be a reliable one as it became far easier to take advantage of narrow windows of good weather than it would have been possible with derrick barges. Moreover, safety was increased.
After a few modifications, this installation scheme can be applied to a wide range of fixed platforms both in rough and calm seas.
In this paper, our intention is to explain why we chose this concept and to give the main results gained from our experience on the field.
INTRODUCTION
Within the scope of the Frigg operations, TOTAL, as operator on the pipeline developed several completely new techniques which involved the installation of lifting devices with a load capacity of 300 t to 800 t on platforms.
Once developed by TOTAL and BUZZICHELLI, these techniques enabled offshore lifting operations to be carried out rapidly in weather conditions which were unsuitable for conventional lifting devices.
APPROACH TO THE NEW CONCEPT
North Sea beginnings
When operations first started in the North Sea, production platforms were equipped by means of conventional derrick barges.
The latter can work in up to half a foot heave but roll is critical, the limitation being between 0.5 and 1° depending on the size of the load. In the North Sea, these thresholds are often over-reached resulting in long waiting for calmer weather and sometimes in postponements of operations for up to 8 months, should they not have been completed before the winter season.
Moreover, safety is sometimes affected. Indeed, once a package has been lifted a cargo barge becomes very lively, which lead to a very tricky situation, as it is impossible to drop the package down either on the platform or back on the cargo barge. Should by any chance, the load then start swinging laterally, it is almost impossible to control.
Big modules and huge barges : some improvement but many disadvantages.
In an attempt to improve North Sea operations huge derrick barges appeared. They could handle large and heavy packages (up to 2 000 tons) in slightly worse sea conditions.
It was agreed that the bigger the modules, the fewer lifts required to install them. This was in fact quite true, but several disadvantages should be pointed out.
Title: Self-Installed Deck On Offshore Platform
Description:
ABSTRACT
This paper attempts to describe the development of "self-installed" decks on offshore platforms.
When North Sea operations first started platform installation was performed by means of conventional derrick barges i however, faced with harsh sea conditions, they did not prove very cost effective and installation was often delayed.
Thus, operators were driven to seek new concepts.
Among them, TOTAL CFP, operator on the Frigg pipeline, chose to erect big cranes on bare platforms in order to complete installation.
This concept soon proved to be a reliable one as it became far easier to take advantage of narrow windows of good weather than it would have been possible with derrick barges.
Moreover, safety was increased.
After a few modifications, this installation scheme can be applied to a wide range of fixed platforms both in rough and calm seas.
In this paper, our intention is to explain why we chose this concept and to give the main results gained from our experience on the field.
INTRODUCTION
Within the scope of the Frigg operations, TOTAL, as operator on the pipeline developed several completely new techniques which involved the installation of lifting devices with a load capacity of 300 t to 800 t on platforms.
Once developed by TOTAL and BUZZICHELLI, these techniques enabled offshore lifting operations to be carried out rapidly in weather conditions which were unsuitable for conventional lifting devices.
APPROACH TO THE NEW CONCEPT
North Sea beginnings
When operations first started in the North Sea, production platforms were equipped by means of conventional derrick barges.
The latter can work in up to half a foot heave but roll is critical, the limitation being between 0.
5 and 1° depending on the size of the load.
In the North Sea, these thresholds are often over-reached resulting in long waiting for calmer weather and sometimes in postponements of operations for up to 8 months, should they not have been completed before the winter season.
Moreover, safety is sometimes affected.
Indeed, once a package has been lifted a cargo barge becomes very lively, which lead to a very tricky situation, as it is impossible to drop the package down either on the platform or back on the cargo barge.
Should by any chance, the load then start swinging laterally, it is almost impossible to control.
Big modules and huge barges : some improvement but many disadvantages.
In an attempt to improve North Sea operations huge derrick barges appeared.
They could handle large and heavy packages (up to 2 000 tons) in slightly worse sea conditions.
It was agreed that the bigger the modules, the fewer lifts required to install them.
This was in fact quite true, but several disadvantages should be pointed out.
Related Results
Alternative Offshore Foundation Installation Methods
Alternative Offshore Foundation Installation Methods
Abstract
According to the European Wind Energy Association (EWEA) in the first six months of 2012, Europe installed and fully grid connected 132 offshore wind tur...
First Jack-Up Production Platform In North Sea
First Jack-Up Production Platform In North Sea
ABSTRACT
This paper describes the platform design engineering aspects of Amoco's jack-up gas production platform which was installed in August, 1972. It is the fi...
Platform Emmy Strengthening And Requalification
Platform Emmy Strengthening And Requalification
ABSTRACT
Older platforms that may require assessment and/or strengthening to continue operation are of primary interest and concern to operators, designers and re...
Deepwater Platform Design
Deepwater Platform Design
ABSTRACT
Results of preliminary platform design studies enable engineers"to identify and appraise major variables affecting deepwater platform capabilities. Trans...
The Jacking System and Simulator for Mating the Hutton TLP
The Jacking System and Simulator for Mating the Hutton TLP
ABSTRACT
The Hutton TLP Deck/ Hull mating and weldout operation required the use of a sophisticated and unique hydraulic jacking system. The system was designed t...
Anteo : the Float-over giant
Anteo : the Float-over giant
Abstract
Anteo is a "giant" hydraulic system providing one of the most reliable and cost-effective solution to the market demand of Integrated Deck installation b...
SWATH Technology for Subsea System Intervention
SWATH Technology for Subsea System Intervention
Abstract
Small water-plane area twin hull (SWATH) technology is being used for seagoing vessels in the marine construction industry to provide a stable working de...
00.06: Advances and development needs in the structural design of steel box girders for major bridges
00.06: Advances and development needs in the structural design of steel box girders for major bridges
ABSTRACTMajor cable‐supported bridges with a span exceeding 600m would not normally be feasible without a steel box girder to carry the traffic load. These box girders generally co...

