Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

The Exact Positioning of Oseberg 'A' Platform

View through CrossRef
ABSTRACT This paper describes the planning and execution of the exact positioning of the 800,000 tonne Oseberg A production platform. Oseberg A is the tenth Condeep concrete platform to have been designed, constructed and installed in the North Sea by Norwegian Contractors, and of all the Condeep structures installed to date, none have been positioned with the same degree of accuracy as this one. As have all Condeep platforms, Oseberg A was constructed to near 100% completion inshore, in sheltered waters, on the west coast of Norway. And then finally, in June 1988, the floating structure was towed to the Oseberg field in the North Sea where the platform was positioned and installed on site in 109 metres of water. Whereas previous positioning of such giant structures had been carried out through the utilization of free running tugs in combination with dowels, a new method of positioning had to be developed for the Oseberg A allowing for much more precision. Compared with the generous installation tolerances of the past, that had always been met with ample margins, the absolute requirements in regard to the exact positioning of Oseberg A on the field represented quite a marine engineering and operation challenge. This paper describes how that challenge was met, and how the platform was successfully positioned less than 0.1 meter (4 inches) from theoretical centre. INTRODUCTION A major milestone in the development of the Oseberg field in the North Sea was reached in June 1988 with the tow-out and installation of the Oseberg A platform. The platform was installed in a water depth of 109 meters. Oseberg A is the tenth Condeep platform designed, constructed and installed by Norwegian Contractors. On previous occasions, free running tugs have been used to position platforms. To obtain sufficient control during the final stage of positioning, dowels i.e. large piles underneath the platform, are brought into contact with the seabed to provide the resistance necessary to control the motion of the platform. The combination of tugs and dowels provide both station keeping ability and the means to accurately position and orientate the platform. The method has been proven in practice to meet generous installation tolerances with ample safety margins. The installation of the 800,000 tonne Oseberg A platform close to the Oseberg B jacket and preinstalled subsea piplines called for very careful positioning and presented Norwegian Contractors with a new challenge. It was essential to ensure that no damage was done to the jacket or the prelaid pipelines. At the same time a high degree of accuracy of position and orientation was required as the two platforms were to be connected by a prefabricated bridge. The method of using free running tugs and dowels was therefore improved upon. For better control during this latest positioning, four of the nine tugs were anchored. For safe maneuvering of the platform towards target winches were used onboard the anchored tugs.
Title: The Exact Positioning of Oseberg 'A' Platform
Description:
ABSTRACT This paper describes the planning and execution of the exact positioning of the 800,000 tonne Oseberg A production platform.
Oseberg A is the tenth Condeep concrete platform to have been designed, constructed and installed in the North Sea by Norwegian Contractors, and of all the Condeep structures installed to date, none have been positioned with the same degree of accuracy as this one.
As have all Condeep platforms, Oseberg A was constructed to near 100% completion inshore, in sheltered waters, on the west coast of Norway.
And then finally, in June 1988, the floating structure was towed to the Oseberg field in the North Sea where the platform was positioned and installed on site in 109 metres of water.
Whereas previous positioning of such giant structures had been carried out through the utilization of free running tugs in combination with dowels, a new method of positioning had to be developed for the Oseberg A allowing for much more precision.
Compared with the generous installation tolerances of the past, that had always been met with ample margins, the absolute requirements in regard to the exact positioning of Oseberg A on the field represented quite a marine engineering and operation challenge.
This paper describes how that challenge was met, and how the platform was successfully positioned less than 0.
1 meter (4 inches) from theoretical centre.
INTRODUCTION A major milestone in the development of the Oseberg field in the North Sea was reached in June 1988 with the tow-out and installation of the Oseberg A platform.
The platform was installed in a water depth of 109 meters.
Oseberg A is the tenth Condeep platform designed, constructed and installed by Norwegian Contractors.
On previous occasions, free running tugs have been used to position platforms.
To obtain sufficient control during the final stage of positioning, dowels i.
e.
large piles underneath the platform, are brought into contact with the seabed to provide the resistance necessary to control the motion of the platform.
The combination of tugs and dowels provide both station keeping ability and the means to accurately position and orientate the platform.
The method has been proven in practice to meet generous installation tolerances with ample safety margins.
The installation of the 800,000 tonne Oseberg A platform close to the Oseberg B jacket and preinstalled subsea piplines called for very careful positioning and presented Norwegian Contractors with a new challenge.
It was essential to ensure that no damage was done to the jacket or the prelaid pipelines.
At the same time a high degree of accuracy of position and orientation was required as the two platforms were to be connected by a prefabricated bridge.
The method of using free running tugs and dowels was therefore improved upon.
For better control during this latest positioning, four of the nine tugs were anchored.
For safe maneuvering of the platform towards target winches were used onboard the anchored tugs.

Related Results

Troll Oseberg Gas Injection (TOGI) Development
Troll Oseberg Gas Injection (TOGI) Development
ABSTRACT In 1986 the Oseberg partners decided to replace the planned water injection scheme by gas injection. Pressure maintenance by gas of the...
TOGI: Multiphase Flow From Troll to Oseberg
TOGI: Multiphase Flow From Troll to Oseberg
ABSTRACT The TOGI 20" pipeline has been designed to transport unprocessed well fluid 48.5 Km from a subsea installation to an offshore production platform. ...
Challenges in Heavy Crude Oil-Grane, an Overview
Challenges in Heavy Crude Oil-Grane, an Overview
Abstract At current production, Grane field supply the market with more than 220,000 barrels of oil per day. Innovative solutions were needed to produce the heavy...
The Oseberg Transportation System
The Oseberg Transportation System
ABSTRACT The Oseberg Transportation System includes a crude oil pipeline placed in water depths up to 357m, connecting the Oseberg Field in the North Sea with a s...
A Study on Brand Positioning in Dairy Product at Villupuram, Tamil Nadu
A Study on Brand Positioning in Dairy Product at Villupuram, Tamil Nadu
Brand positioning is a core concept in marketing. Despite the importance of the concept however, there is limited research in the field of positioning clarifying to what extent var...
Mobile Positioning Techniques and Systems: A Comprehensive Review
Mobile Positioning Techniques and Systems: A Comprehensive Review
The recent developments in mobile positioning technologies and the increasing demands of ubiquitous computing have significantly contributed to sophisticated positioning applicatio...
Research on Real-time and High-precision Positioning Method of Ground Target through UAV Stereo Vision and Spatial Information Fusion
Research on Real-time and High-precision Positioning Method of Ground Target through UAV Stereo Vision and Spatial Information Fusion
Background: Positioning accuracy is the most important index of the reconnaissance positioning system. Positioning accuracy involves many factors, such as the position, attitude an...
Research and Development of an Augmented Reality Visual Image-Guided Radiotherapy Positioning Technology
Research and Development of an Augmented Reality Visual Image-Guided Radiotherapy Positioning Technology
Abstract Objective: This study is conducted to explore the development of a noninvasive and nonradiative guided radiotherapy positioning system based on augmented reality (...

Back to Top