Javascript must be enabled to continue!
The Exact Positioning of Oseberg 'A' Platform
View through CrossRef
ABSTRACT
This paper describes the planning and execution of the exact positioning of the 800,000 tonne Oseberg A production platform.
Oseberg A is the tenth Condeep concrete platform to have been designed, constructed and installed in the North Sea by Norwegian Contractors, and of all the Condeep structures installed to date, none have been positioned with the same degree of accuracy as this one.
As have all Condeep platforms, Oseberg A was constructed to near 100% completion inshore, in sheltered waters, on the west coast of Norway. And then finally, in June 1988, the floating structure was towed to the Oseberg field in the North Sea where the platform was positioned and installed on site in 109 metres of water.
Whereas previous positioning of such giant structures had been carried out through the utilization of free running tugs in combination with dowels, a new method of positioning had to be developed for the Oseberg A allowing for much more precision. Compared with the generous installation tolerances of the past, that had always been met with ample margins, the absolute requirements in regard to the exact positioning of Oseberg A on the field represented quite a marine engineering and operation challenge. This paper describes how that challenge was met, and how the platform was successfully positioned less than 0.1 meter (4 inches) from theoretical centre.
INTRODUCTION
A major milestone in the development of the Oseberg field in the North Sea was reached in June 1988 with the tow-out and installation of the Oseberg A platform.
The platform was installed in a water depth of 109 meters. Oseberg A is the tenth Condeep platform designed, constructed and installed by Norwegian Contractors.
On previous occasions, free running tugs have been used to position platforms. To obtain sufficient control during the final stage of positioning, dowels i.e. large piles underneath the platform, are brought into contact with the seabed to provide the resistance necessary to control the motion of the platform. The combination of tugs and dowels provide both station keeping ability and the means to accurately position and orientate the platform. The method has been proven in practice to meet generous installation tolerances with ample safety margins.
The installation of the 800,000 tonne Oseberg A platform close to the Oseberg B jacket and preinstalled subsea piplines called for very careful positioning and presented Norwegian Contractors with a new challenge. It was essential to ensure that no damage was done to the jacket or the prelaid pipelines. At the same time a high degree of accuracy of position and orientation was required as the two platforms were to be connected by a prefabricated bridge. The method of using free running tugs and dowels was therefore improved upon. For better control during this latest positioning, four of the nine tugs were anchored. For safe maneuvering of the platform towards target winches were used onboard the anchored tugs.
Title: The Exact Positioning of Oseberg 'A' Platform
Description:
ABSTRACT
This paper describes the planning and execution of the exact positioning of the 800,000 tonne Oseberg A production platform.
Oseberg A is the tenth Condeep concrete platform to have been designed, constructed and installed in the North Sea by Norwegian Contractors, and of all the Condeep structures installed to date, none have been positioned with the same degree of accuracy as this one.
As have all Condeep platforms, Oseberg A was constructed to near 100% completion inshore, in sheltered waters, on the west coast of Norway.
And then finally, in June 1988, the floating structure was towed to the Oseberg field in the North Sea where the platform was positioned and installed on site in 109 metres of water.
Whereas previous positioning of such giant structures had been carried out through the utilization of free running tugs in combination with dowels, a new method of positioning had to be developed for the Oseberg A allowing for much more precision.
Compared with the generous installation tolerances of the past, that had always been met with ample margins, the absolute requirements in regard to the exact positioning of Oseberg A on the field represented quite a marine engineering and operation challenge.
This paper describes how that challenge was met, and how the platform was successfully positioned less than 0.
1 meter (4 inches) from theoretical centre.
INTRODUCTION
A major milestone in the development of the Oseberg field in the North Sea was reached in June 1988 with the tow-out and installation of the Oseberg A platform.
The platform was installed in a water depth of 109 meters.
Oseberg A is the tenth Condeep platform designed, constructed and installed by Norwegian Contractors.
On previous occasions, free running tugs have been used to position platforms.
To obtain sufficient control during the final stage of positioning, dowels i.
e.
large piles underneath the platform, are brought into contact with the seabed to provide the resistance necessary to control the motion of the platform.
The combination of tugs and dowels provide both station keeping ability and the means to accurately position and orientate the platform.
The method has been proven in practice to meet generous installation tolerances with ample safety margins.
The installation of the 800,000 tonne Oseberg A platform close to the Oseberg B jacket and preinstalled subsea piplines called for very careful positioning and presented Norwegian Contractors with a new challenge.
It was essential to ensure that no damage was done to the jacket or the prelaid pipelines.
At the same time a high degree of accuracy of position and orientation was required as the two platforms were to be connected by a prefabricated bridge.
The method of using free running tugs and dowels was therefore improved upon.
For better control during this latest positioning, four of the nine tugs were anchored.
For safe maneuvering of the platform towards target winches were used onboard the anchored tugs.
Related Results
A Study on Brand Positioning in Dairy Product at Villupuram, Tamil Nadu
A Study on Brand Positioning in Dairy Product at Villupuram, Tamil Nadu
Brand positioning is a core concept in marketing. Despite the importance of the concept however, there is limited research in the field of positioning clarifying to what extent var...
Mobile Positioning Techniques and Systems: A Comprehensive Review
Mobile Positioning Techniques and Systems: A Comprehensive Review
The recent developments in mobile positioning technologies and the increasing demands of ubiquitous computing have significantly contributed to sophisticated positioning applicatio...
Research on Real-time and High-precision Positioning Method of Ground
Target through UAV Stereo Vision and Spatial Information Fusion
Research on Real-time and High-precision Positioning Method of Ground
Target through UAV Stereo Vision and Spatial Information Fusion
Background:
Positioning accuracy is the most important index of the reconnaissance
positioning system. Positioning accuracy involves many factors, such as the position, attitude an...
Research on Railway Train Space Position Correction Algorithm Based on
GNSS Correction Model
Research on Railway Train Space Position Correction Algorithm Based on
GNSS Correction Model
<p>The traditional railway train positioning methods mainly include three methods: speed sensor based, ground point responder response, and track circuit section occupancy de...
Positioning error estimation of honking detection systems based on YOLOX
Positioning error estimation of honking detection systems based on YOLOX
Traditionally, honking capture system calibration has primarily involved indoor experiments in muffler rooms. Additionally, the manual measurement method for estimating positioning...
An Ultra-Short Baseline Underwater Positioning System with Kalman Filtering
An Ultra-Short Baseline Underwater Positioning System with Kalman Filtering
The ultra-short baseline underwater positioning is one of the most widely applied methods in underwater positioning and navigation due to its simplicity, efficiency, low cost, and ...
Experimental Research of Triple Inertial Navigation System Shearer Positioning
Experimental Research of Triple Inertial Navigation System Shearer Positioning
In order to improve the positioning accuracy of shearers, the overground experimental device based on the positioning model of TINS (Triple Inertial Navigation System) was built. T...
Shallow Gas In The Oseberg, Brage And Troll Fields North Sea, 60°30' N
Shallow Gas In The Oseberg, Brage And Troll Fields North Sea, 60°30' N
Abstract
An integrated approach using geological, seismic, geotechnical and well log data have been used to investigate the presence of shallow gas in the Oseberg...

