Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

First Jack-Up Production Platform In North Sea

View through CrossRef
ABSTRACT This paper describes the platform design engineering aspects of Amoco's jack-up gas production platform which was installed in August, 1972. It is the first jack-up production platform installed in the North Sea. The main advantage of using the jack-up platform as compared with the conventional template-type platform is that all production, storage, and living facilities can be installed, tested, and checked out in the fabrication yard prior to leaving for installation. As a result, considerable expensive offshore work is avoided, and more important, much less time is required to commission the production facilities and begin operation. INTRODUCTION The Oil Industry is constantly searching for new methods and systems to reduce the high cost of offshore installations. Particular interest is being shown in producing facilities required to be located offshore. These installations can vary in size from a single separator to a bulky, highly instrumented gas dehydration complex. The first step toward economy was the "skid mounted" unit which combined a principal unit with pumps, meters and instrumentation installed and possibly tested on a set of skids designed for lifting into place on the offshore platform. Later the deck sections were sectionalized. The equipment was installed integrally with the deck section pieces and then finally assembled and tested offshore. Still later the idea of "production packages" (more commonly referred to now as modules) came into use. For the larger facilities and deep water locations this method appears to be the most popular at the present time. To date, this arrangement appears to be planned for all deep water North Sea installations. For this type operation the equipment is installed in a series of structural steel boxes. The boxes are fabricated in the yard in the exact position they will occupy in their final location offshore to insure a final, correct inter-connection. The entire system can then be tested as a unit in the yard. Once installed offshore only a minimum amount of final testing is required. One type of permanent installation that has seen limited use is the "jack-up" barge. Some use has been made in the Gulf of Mexico, but principally for storage. One such installation for large separator units is known by the writers to be in use in the Middle East. Amoco, having used the three previous mentioned methods in the British North Sea, investigated the use of a jack-up barge, in an effort to further reduce offshore connection work and testing. The results of the investigation showed this method feasible and economical up to approximately 100 ft. water depth. The decision was made to use the "jack-up" barge concept on a gas dehydration facility to be installed in a 75 ft. water depth location in the Leman Field, British North Sea.
Title: First Jack-Up Production Platform In North Sea
Description:
ABSTRACT This paper describes the platform design engineering aspects of Amoco's jack-up gas production platform which was installed in August, 1972.
It is the first jack-up production platform installed in the North Sea.
The main advantage of using the jack-up platform as compared with the conventional template-type platform is that all production, storage, and living facilities can be installed, tested, and checked out in the fabrication yard prior to leaving for installation.
As a result, considerable expensive offshore work is avoided, and more important, much less time is required to commission the production facilities and begin operation.
INTRODUCTION The Oil Industry is constantly searching for new methods and systems to reduce the high cost of offshore installations.
Particular interest is being shown in producing facilities required to be located offshore.
These installations can vary in size from a single separator to a bulky, highly instrumented gas dehydration complex.
The first step toward economy was the "skid mounted" unit which combined a principal unit with pumps, meters and instrumentation installed and possibly tested on a set of skids designed for lifting into place on the offshore platform.
Later the deck sections were sectionalized.
The equipment was installed integrally with the deck section pieces and then finally assembled and tested offshore.
Still later the idea of "production packages" (more commonly referred to now as modules) came into use.
For the larger facilities and deep water locations this method appears to be the most popular at the present time.
To date, this arrangement appears to be planned for all deep water North Sea installations.
For this type operation the equipment is installed in a series of structural steel boxes.
The boxes are fabricated in the yard in the exact position they will occupy in their final location offshore to insure a final, correct inter-connection.
The entire system can then be tested as a unit in the yard.
Once installed offshore only a minimum amount of final testing is required.
One type of permanent installation that has seen limited use is the "jack-up" barge.
Some use has been made in the Gulf of Mexico, but principally for storage.
One such installation for large separator units is known by the writers to be in use in the Middle East.
Amoco, having used the three previous mentioned methods in the British North Sea, investigated the use of a jack-up barge, in an effort to further reduce offshore connection work and testing.
The results of the investigation showed this method feasible and economical up to approximately 100 ft.
water depth.
The decision was made to use the "jack-up" barge concept on a gas dehydration facility to be installed in a 75 ft.
water depth location in the Leman Field, British North Sea.

Related Results

Jack-up Operational Guidelines
Jack-up Operational Guidelines
ABSTRACT In the time interval between 1956 and 1977.Zapata Off-Shore Company has operated eleven jack-up rigs for a total of 127 rig-years of operating experience...
Seasonal Arctic sea ice predictability and prediction
Seasonal Arctic sea ice predictability and prediction
Arctic sea ice plays a central role in the Earth’s climate. Changes in the sea ice on seasonal-to-interannual timescales impact ecosystems, populations and a growing number of stak...
Fire Protection on the Beryl A Platform
Fire Protection on the Beryl A Platform
This paper describes the fire protection systems of a large offshore platform in the North Sea. The Beryl A platform had several unique risk platform in the North Sea. The Beryl A ...
Sea Level Rise
Sea Level Rise
Sea level is the height of the sea surface expressed either in a geocentric reference frame (absolute sea level) or with respect to the moving Earth’s crust (relative sea level). A...
The Lessons From 8 Years' Operation Ot A First-Generation North Sea Platform And Planning To Its End-Ot-Field Lite
The Lessons From 8 Years' Operation Ot A First-Generation North Sea Platform And Planning To Its End-Ot-Field Lite
ABSTRACT Thistle design was started in 1974 in the days of oil shortages and rising prices. When installed, it was in the deepest water and the most northerly of ...
Geohazards in the Yellow Sea and East China Sea
Geohazards in the Yellow Sea and East China Sea
ABSTRACT Shallow submarine geology in the Yellow and East China seas is dicta ted mostly by the proximity of the Yellow and Yangtze Rivers and by the late Quatern...
The Removal of the Maureen Steel Gravity Platform
The Removal of the Maureen Steel Gravity Platform
Abstract The Maureen drilling, production and oil storage platform is located in 95.6m of water in block 16/29 of the U.K. Continental Shelf, and consists of a la...

Back to Top