Javascript must be enabled to continue!
Hutton TLP Installation
View through CrossRef
ABSTRACT
Installation of the Hutton TLP required precise simultaneous control of several complex systems. This paper describes the equipment and operations involved in the deployment and connection of the sixteen tension legs, and the documentation used for control. The equipment trials and personnel training programmes undertaken to ensure the first-time success of this unique operation are presented. The paper concludes with an appraisal of the installation process and the significance of the principles employed to the development of deep water TLPs.
INTRODUCTION
Installation of the Hutton Tension Leg Platform, a new concept in oilfield development(l), was carried out in under four days. The process of installation involved translation of the free floating vessel into a vertically restrained platform. This operation was unprecedented in its reliance on multiple systems, novel equipment and specially trained personnel. It entailed the assembly and deployment of sixteen tension legs, their connection to four pre-installed foundations, and the application of 13,000 tonnes of tension.
These unique operations required the deve1opment of detail ed procedures to control the installation systems and activities. The use of equipment unproven in service and personnel inexperienced in the special operations necessitated intensive trials and training programmes to ensure a safe and efficient installation.
The installation of the TLP, 90 miles north-east of the Shetland islands and in a water depth of 148 metres, was completed on 15th July and first oil produced on 6th August, 1984.
PRINCIPLES OF INSTALLATION
The TLP is a compliant structure where the vertical motions of heave, pitch and roll are suppressed by leg tension. The tension is induced by an excess of buoyancy over platform weight. This concept can be represented by the equation of static equilibrium:(Equation available in full paper)
The static 'pre-tension' must be sufficient to maintain the legs in tension for all operating conditions and extreme environmental events. Approximate values are:(Equation available in full paper)
This condition is achieved by restraining the platform approximately 10 metres deeper in the water than its free floating draft. Significant changes in operating loads, riser tensions and platform centre of gravity can be accommodated by the transfer of ballast.
Installation requirements were a major factor influencing the design of the mooring system, thus engineering for installation proceeded in parallel with mooring system design. An early decision in the design process was the method of 'stabbing' the legs into the foundation mooring sleeves. Unaided stabbing was considered the most reliable, efficient and easily engineered method, provided the platform position could be maintained within acceptable tolerances. The design environmenta1 conditions were established as a wind speed of 10 m/s and a sea state typically of 2m significant wave height and 7s period. Analyses and model tests demonstrated acceptable leg motions and established a vessel positioning tolerance requirement of 1.5m during stabbing.
Title: Hutton TLP Installation
Description:
ABSTRACT
Installation of the Hutton TLP required precise simultaneous control of several complex systems.
This paper describes the equipment and operations involved in the deployment and connection of the sixteen tension legs, and the documentation used for control.
The equipment trials and personnel training programmes undertaken to ensure the first-time success of this unique operation are presented.
The paper concludes with an appraisal of the installation process and the significance of the principles employed to the development of deep water TLPs.
INTRODUCTION
Installation of the Hutton Tension Leg Platform, a new concept in oilfield development(l), was carried out in under four days.
The process of installation involved translation of the free floating vessel into a vertically restrained platform.
This operation was unprecedented in its reliance on multiple systems, novel equipment and specially trained personnel.
It entailed the assembly and deployment of sixteen tension legs, their connection to four pre-installed foundations, and the application of 13,000 tonnes of tension.
These unique operations required the deve1opment of detail ed procedures to control the installation systems and activities.
The use of equipment unproven in service and personnel inexperienced in the special operations necessitated intensive trials and training programmes to ensure a safe and efficient installation.
The installation of the TLP, 90 miles north-east of the Shetland islands and in a water depth of 148 metres, was completed on 15th July and first oil produced on 6th August, 1984.
PRINCIPLES OF INSTALLATION
The TLP is a compliant structure where the vertical motions of heave, pitch and roll are suppressed by leg tension.
The tension is induced by an excess of buoyancy over platform weight.
This concept can be represented by the equation of static equilibrium:(Equation available in full paper)
The static 'pre-tension' must be sufficient to maintain the legs in tension for all operating conditions and extreme environmental events.
Approximate values are:(Equation available in full paper)
This condition is achieved by restraining the platform approximately 10 metres deeper in the water than its free floating draft.
Significant changes in operating loads, riser tensions and platform centre of gravity can be accommodated by the transfer of ballast.
Installation requirements were a major factor influencing the design of the mooring system, thus engineering for installation proceeded in parallel with mooring system design.
An early decision in the design process was the method of 'stabbing' the legs into the foundation mooring sleeves.
Unaided stabbing was considered the most reliable, efficient and easily engineered method, provided the platform position could be maintained within acceptable tolerances.
The design environmenta1 conditions were established as a wind speed of 10 m/s and a sea state typically of 2m significant wave height and 7s period.
Analyses and model tests demonstrated acceptable leg motions and established a vessel positioning tolerance requirement of 1.
5m during stabbing.
Related Results
Challenges of TLP Installation Offshore Brazil
Challenges of TLP Installation Offshore Brazil
Abstract
Installation of a Tension Leg Platform comprises distinct phases, all of which can provide special challenges when considering locating a TLP in a fronti...
Auger TLP Well System Challenges and Innovations
Auger TLP Well System Challenges and Innovations
ABSTRACT
The Auger TLP well system has successfully employed novel features to satisfy challenging design requirements of drilling, completing, and producing near...
New Directions in TLP Technology
New Directions in TLP Technology
Abstract
Of the many deepwater platform concepts that were developed as deepwater platform technology matured, the TLP has been the most frequently selected for d...
CryoSeek identification of glycofibrils with diverse compositions and structural assemblies
CryoSeek identification of glycofibrils with diverse compositions and structural assemblies
Abstract
Last year, we reported CryoSeek, a research strategy that employs cryo-electron microscopy (cryo-EM) to discover novel bio-entities from any accessible source,...
Hutton TLP Mooring System
Hutton TLP Mooring System
ABSTRACT
The tension leg platform (TLP) which is being developed for the Hutton Field in the North Sea is the first application of this new platform concept which...
Research and Development of a Three-Piece Tendon for a TLP
Research and Development of a Three-Piece Tendon for a TLP
Abstract
Research and development of TLP tendon is described. Forged tendons are in actual use but their cost increases rapidly as the diameter becomes greater.
...
An Integrated Motion and Structural Analysis for Tension Leg Platforms
An Integrated Motion and Structural Analysis for Tension Leg Platforms
Abstract
The tension leg platform (TLP) concept has become increasingly popular as oil reservoirs, once considered too deep to recover, now contain the financial ...
SOLUSI ANALITIK RESPON GERAKAN SURGE OCEAN THERMAL ENERGY CONVERSION BERBENTUK TENSIONED LEG PLATFORM (OTEC-TLP
SOLUSI ANALITIK RESPON GERAKAN SURGE OCEAN THERMAL ENERGY CONVERSION BERBENTUK TENSIONED LEG PLATFORM (OTEC-TLP
Peningkatan kebutuhan energi dunia relatif mengalami peningkatan yang cukup signifikan dari tahun ke tahun. Kebutuhan akan Energi Baru Terbarukan (EBT) juga meningkat seiring denga...


