Success criteria-based impacts of risk factors on education building projects in southwestern Nigeria
View through CrossRef
Purpose
Despite the huge capital outlay in tertiary education building projects (TEBP), these projects undoubtedly failed in meeting the set objectives of cost, time and quality, among others. Therefore, rather than the impacts of risks on the overall project performance, which is common in the construction management literature, the purpose of this study is to assess the impacts of risk factors on the criteria for measuring the success of public TEBP.
Design/methodology/approach
The paper adopted a quantitative research method where the data collection was via a questionnaire survey. The researcher administered 452 questionnaires to the client representatives, consultants and contractors involved in building projects across five public tertiary education institutions in Ondo State, Nigeria. Of 452 questionnaires, 279 were retrieved and suitable for the analysis, translating to a 61.73% response rate. The reliability analysis of the research instrument showed 0.965 and 0.807, via Cronbach’s alpha test, indicating high reliability of the instrument used for data collection.
Findings
The study found different risk factors affecting the criteria for measuring the success of TEBP. For instance, the environmental risk factor significantly impacted completion to cost, while financial and political risk factors significantly impacted completion to time. In addition, while environmental, legal and management risks significantly impacted end-user satisfaction, safety performance was significantly impacted by logistic, legal, design, construction, political and management risks. Besides, the logistic, legal, design, construction, financial, political and management risk factors impacted profit. However, despite profit being one of the criteria for measuring the success of building projects, it recorded the highest risk impacts amounting to 41% variance.
Research limitations/implications
The findings are limited to the public tertiary education building projects procured via competitive tendering; therefore, the results might differ when considering other procurement methods.
Practical implications
The practical implication is that rather than focusing on all risk factors, the project stakeholders could give adequate attention to the significant risk factors impacting each of the parameters for measuring the success of education building projects.
Originality/value
The study revealed specific risk factors impacting the criteria for measuring the success of TEBP, which extend beyond the use of the overall project performance approach.
Title: Success criteria-based impacts of risk factors on education building projects in southwestern Nigeria
Description:
Purpose
Despite the huge capital outlay in tertiary education building projects (TEBP), these projects undoubtedly failed in meeting the set objectives of cost, time and quality, among others.
Therefore, rather than the impacts of risks on the overall project performance, which is common in the construction management literature, the purpose of this study is to assess the impacts of risk factors on the criteria for measuring the success of public TEBP.
Design/methodology/approach
The paper adopted a quantitative research method where the data collection was via a questionnaire survey.
The researcher administered 452 questionnaires to the client representatives, consultants and contractors involved in building projects across five public tertiary education institutions in Ondo State, Nigeria.
Of 452 questionnaires, 279 were retrieved and suitable for the analysis, translating to a 61.
73% response rate.
The reliability analysis of the research instrument showed 0.
965 and 0.
807, via Cronbach’s alpha test, indicating high reliability of the instrument used for data collection.
Findings
The study found different risk factors affecting the criteria for measuring the success of TEBP.
For instance, the environmental risk factor significantly impacted completion to cost, while financial and political risk factors significantly impacted completion to time.
In addition, while environmental, legal and management risks significantly impacted end-user satisfaction, safety performance was significantly impacted by logistic, legal, design, construction, political and management risks.
Besides, the logistic, legal, design, construction, financial, political and management risk factors impacted profit.
However, despite profit being one of the criteria for measuring the success of building projects, it recorded the highest risk impacts amounting to 41% variance.
Research limitations/implications
The findings are limited to the public tertiary education building projects procured via competitive tendering; therefore, the results might differ when considering other procurement methods.
Practical implications
The practical implication is that rather than focusing on all risk factors, the project stakeholders could give adequate attention to the significant risk factors impacting each of the parameters for measuring the success of education building projects.
Originality/value
The study revealed specific risk factors impacting the criteria for measuring the success of TEBP, which extend beyond the use of the overall project performance approach.
Related Results
Evaluating the Science to Inform the Physical Activity Guidelines for Americans Midcourse Report
Evaluating the Science to Inform the Physical Activity Guidelines for Americans Midcourse Report
Abstract
The Physical Activity Guidelines for Americans (Guidelines) advises older adults to be as active as possible. Yet, despite the well documented benefits of physical a...
Der skal ikke lades sten på sten tilbage
Der skal ikke lades sten på sten tilbage
The Building by the Barbar TempleClose by the large temple at Barbar 1) lies a little tell, which was investigated in the spring of 1956. The tell was shown to cover a building of ...
Volume 10, Index
Volume 10, Index
<p><strong>Vol 10, No 1 (2015)</strong></p><p><strong> </strong></p><p><a href="http://www.world-education-center.org/index...
Technological and Economic Perspective to the Modular Refinery Alternative
Technological and Economic Perspective to the Modular Refinery Alternative
Many countries have employed effective refinery planning for profitability and efficient utilization. In an attempt to stimulate similar achievements in Nigeria, the modular refine...
PUBLIC HEALTH EXPENDITURE AND MATERNAL MORTALITY IN NIGERIA
PUBLIC HEALTH EXPENDITURE AND MATERNAL MORTALITY IN NIGERIA
This study examined the effect of public health expenditure on maternal mortality in Nigeria from 2002 to 2021. To achieve this objective, the study utilized data on maternal death...
Effects of Organisational Values on Employee Performance: A Study of Selected Multinational Corporations in Lagos State, Nigeria
Effects of Organisational Values on Employee Performance: A Study of Selected Multinational Corporations in Lagos State, Nigeria
The main aim of this study was to examine the effects of organisational values on employee performance: a study of selected multinational corporations in Lagos state in Nigeria. A ...
Unveiling Construction Quality Factors: Insights from Asian Economy's Building Projects
Unveiling Construction Quality Factors: Insights from Asian Economy's Building Projects
Economic growth of any country depends on the construction projects and industry in the region. Therefore, the construction industry in Pakistan is directly related to quality and ...
Are Cervical Ribs Indicators of Childhood Cancer? A Narrative Review
Are Cervical Ribs Indicators of Childhood Cancer? A Narrative Review
Abstract
A cervical rib (CR), also known as a supernumerary or extra rib, is an additional rib that forms above the first rib, resulting from the overgrowth of the transverse proce...