Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

The Lessons From 8 Years' Operation Ot A First-Generation North Sea Platform And Planning To Its End-Ot-Field Lite

View through CrossRef
ABSTRACT Thistle design was started in 1974 in the days of oil shortages and rising prices. When installed, it was in the deepest water and the most northerly of the Brent area developments. Production drilling commenced from the platform early in 1978. With eight years operating experience, there are two clear lessons; firstly that a facility cannot be operated in the Northern North Sea without further investment for a twenty-five year life, and secondly, that a plan is required to ensure a cost effective engineering programme through the field's declining production years. The paper considers the major capital outlays incurred since installation. It then presents how this and other experience has been developed in a "Life-of-Field" study aimed at reducing future engineering, maintenance and diving costs. INTRODUCTION Britoil currently operates two North Sea fields (four platforms) and one 'onshore terminal. A further field (Clyde) is scheduled to start production in 1987. The Thistle field was discovered in July 1973. The field, Iodated in the East Shetland Basin, was then the most northerly and in the deepest water of any North Sea field. Thistle design was undertaken in parallel with other early Northern North Sea platforms, ahead of any other installations. Thistle 'A' is therefore very much a "first generation" northern North Sea platform. Although it did not use any obviously new technology, it did involve untried extensions of technology in many areas. The field was developed by a single fixed steel platform with facilities for:-–60 wells–2 drill rigs and drilling services–4 separator trains (rated at 68,000 bpd per train)–2 subsea crude oil storage tanks (35,000 bbls per tank)–crude export by tanker (via a SALM buoy) 5 water injection pumps (rated at 50,000 bpd per pump)–3 produced water treatment flotation cells (rated at 80,000 bpd each)–gas compression (for condensate recovery and gas disposal at 3,500 psig)–2 gas turbines (rated at 26 MW per set)–accommodation for 180 men–3 future oil risers–1 future gas riser–8 future flowline riser bundles (for subsea wells tie-in) Figure 1 shows Thistle's geographical location and its connections to pipeline systems. Figure 2 is a diagramatic view of the platform facilities, highlighting additional facilities. Like many other platforms in the North Sea, Thistle has now reached a stage where production is in decline. However, the facilities are not only required to remain in service for a further 15 years or more, but must also accommodate profiles somewhat different from the orginal design parameters. Recognizing that these early North Sea platforms are almost certainly required to remain in service for twenty years or more, it was decided to review past history and, in anticipation of future requirements, attempt to construct a programme which would lead to a more cost-effective engineering, maintenance and diving programme for the remaining life of the field.
Title: The Lessons From 8 Years' Operation Ot A First-Generation North Sea Platform And Planning To Its End-Ot-Field Lite
Description:
ABSTRACT Thistle design was started in 1974 in the days of oil shortages and rising prices.
When installed, it was in the deepest water and the most northerly of the Brent area developments.
Production drilling commenced from the platform early in 1978.
With eight years operating experience, there are two clear lessons; firstly that a facility cannot be operated in the Northern North Sea without further investment for a twenty-five year life, and secondly, that a plan is required to ensure a cost effective engineering programme through the field's declining production years.
The paper considers the major capital outlays incurred since installation.
It then presents how this and other experience has been developed in a "Life-of-Field" study aimed at reducing future engineering, maintenance and diving costs.
INTRODUCTION Britoil currently operates two North Sea fields (four platforms) and one 'onshore terminal.
A further field (Clyde) is scheduled to start production in 1987.
The Thistle field was discovered in July 1973.
The field, Iodated in the East Shetland Basin, was then the most northerly and in the deepest water of any North Sea field.
Thistle design was undertaken in parallel with other early Northern North Sea platforms, ahead of any other installations.
Thistle 'A' is therefore very much a "first generation" northern North Sea platform.
Although it did not use any obviously new technology, it did involve untried extensions of technology in many areas.
The field was developed by a single fixed steel platform with facilities for:-–60 wells–2 drill rigs and drilling services–4 separator trains (rated at 68,000 bpd per train)–2 subsea crude oil storage tanks (35,000 bbls per tank)–crude export by tanker (via a SALM buoy) 5 water injection pumps (rated at 50,000 bpd per pump)–3 produced water treatment flotation cells (rated at 80,000 bpd each)–gas compression (for condensate recovery and gas disposal at 3,500 psig)–2 gas turbines (rated at 26 MW per set)–accommodation for 180 men–3 future oil risers–1 future gas riser–8 future flowline riser bundles (for subsea wells tie-in) Figure 1 shows Thistle's geographical location and its connections to pipeline systems.
Figure 2 is a diagramatic view of the platform facilities, highlighting additional facilities.
Like many other platforms in the North Sea, Thistle has now reached a stage where production is in decline.
However, the facilities are not only required to remain in service for a further 15 years or more, but must also accommodate profiles somewhat different from the orginal design parameters.
Recognizing that these early North Sea platforms are almost certainly required to remain in service for twenty years or more, it was decided to review past history and, in anticipation of future requirements, attempt to construct a programme which would lead to a more cost-effective engineering, maintenance and diving programme for the remaining life of the field.

Related Results

Analisis SWOT Mobile Dictionary Pleco dan Hanping Lite
Analisis SWOT Mobile Dictionary Pleco dan Hanping Lite
Penelitian berjudul “Analisis SWOT Mobile Dictionary Pleco dan Hanping Lite” dirancang sebagai pedoman pengguna untuk menentukan Mobile Dictionary yang sesuai dengan kebutuhan ...
The Collector Journal for Swedish Literature Science Research
The Collector Journal for Swedish Literature Science Research
Johan Svedjedal, Rymden och tvåkronan. Karin Boyes För lite och den författarsociala debatten. (Space and the Two-Crown Coin: Karin Boye’s För lite and the debate on authors’ socia...
Vega-Lite: A Grammar of Interactive Graphics
Vega-Lite: A Grammar of Interactive Graphics
We present Vega-Lite, a high-level grammar that enables rapid specification of interactive data visualizations. Vega-Lite combines a traditional grammar of graphics, providing visu...
Seasonal Arctic sea ice predictability and prediction
Seasonal Arctic sea ice predictability and prediction
Arctic sea ice plays a central role in the Earth’s climate. Changes in the sea ice on seasonal-to-interannual timescales impact ecosystems, populations and a growing number of stak...
Development Of The Beryl A Field
Development Of The Beryl A Field
Abstract Development drilling from the Beryl 'A' Platform has been in progress for over two years. A total of twelve wells nave been completed with two more neari...
Sea Level Rise
Sea Level Rise
Sea level is the height of the sea surface expressed either in a geocentric reference frame (absolute sea level) or with respect to the moving Earth’s crust (relative sea level). A...
Fire Protection on the Beryl A Platform
Fire Protection on the Beryl A Platform
This paper describes the fire protection systems of a large offshore platform in the North Sea. The Beryl A platform had several unique risk platform in the North Sea. The Beryl A ...

Back to Top