Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

REŠENJE ZA UNAPREĐENJE SISTEMA ZEMLJOSPOJNOG PREKIDAČA

View through CrossRef
In the area of the former "Elektrovojvodina", in transformer station 110/20 kV, the ground switch circuit break system was installed as a forced solution until the old low-oil circuit breakers, which have far exceeded their service life, are replaced. This system "extinguished" any transient earth fault by short-term grounding of the phase affected by the fault, without the need to disconnect the feeder on which the fault occurred. After the replacement of worn-out switches with new ones, this system continued to work because extremely high success rate in resolving transient faults, and absence of interruptions at the low voltage level. The main problem of this system that we have faced during exploitation is the jamming of the pole in the first version of the ground switch or the loss of vacuum in circuit breaker chamber, in the newer version of the ground switch. When these events occur, the entire electrical supply system to which the ground switch is connected fails. Detection of its failure is extremely complex. Namely, the ground switch, apparently, works correctly: he is still trying to solve the ground fault he himself caused. This problem was solved by connecting the ground switch system to the MV bus via a feeder cell that was used only for that purpose. That cell was fully equipped with a switch, disconnectors, current measuring transformers and a protective device. The main disadvantage of this solution is, beside the questionable economic justification, taking the place of a one feeder. In this paper, we present the solution implemented in TS 110/20 kV Apatin. Namely, we used the existing automation device and the existing cell of the ground switch, in which we added a fourth pole in serial with three poles, between the poles and the ground. This pole is permanently switched on and remotely controlled, and which, in the event of a fault, is set to disconnect the poles and grounding, blocks the automation and sends an alarm to the dispatch center that the ground switch is faulty. In this way, we prevented the outage of the power supply of large amount of consumers, reduced the failure diagnostics time to zero and increased the reliability of the power supply of all consumers supplied from the given transformer area.
Srpski nacionalni komitet Međunarodnog saveta za velike električne mreže CIGRE Srbija
Title: REŠENJE ZA UNAPREĐENJE SISTEMA ZEMLJOSPOJNOG PREKIDAČA
Description:
In the area of the former "Elektrovojvodina", in transformer station 110/20 kV, the ground switch circuit break system was installed as a forced solution until the old low-oil circuit breakers, which have far exceeded their service life, are replaced.
This system "extinguished" any transient earth fault by short-term grounding of the phase affected by the fault, without the need to disconnect the feeder on which the fault occurred.
After the replacement of worn-out switches with new ones, this system continued to work because extremely high success rate in resolving transient faults, and absence of interruptions at the low voltage level.
The main problem of this system that we have faced during exploitation is the jamming of the pole in the first version of the ground switch or the loss of vacuum in circuit breaker chamber, in the newer version of the ground switch.
When these events occur, the entire electrical supply system to which the ground switch is connected fails.
Detection of its failure is extremely complex.
Namely, the ground switch, apparently, works correctly: he is still trying to solve the ground fault he himself caused.
This problem was solved by connecting the ground switch system to the MV bus via a feeder cell that was used only for that purpose.
That cell was fully equipped with a switch, disconnectors, current measuring transformers and a protective device.
The main disadvantage of this solution is, beside the questionable economic justification, taking the place of a one feeder.
In this paper, we present the solution implemented in TS 110/20 kV Apatin.
Namely, we used the existing automation device and the existing cell of the ground switch, in which we added a fourth pole in serial with three poles, between the poles and the ground.
This pole is permanently switched on and remotely controlled, and which, in the event of a fault, is set to disconnect the poles and grounding, blocks the automation and sends an alarm to the dispatch center that the ground switch is faulty.
In this way, we prevented the outage of the power supply of large amount of consumers, reduced the failure diagnostics time to zero and increased the reliability of the power supply of all consumers supplied from the given transformer area.

Related Results

Kriza demokratije – simptomi i lekovi
Kriza demokratije – simptomi i lekovi
Svet potresaju brojne krize, od ekonomskih, finansijskih, preko ekoloških, zdravstvenih, do bezbednosnih. One su samo nagoveštaji jedne mnogo kompleksnije krize – krize liberalnog ...
Design and construction of a snapshot full-Stokes polarimetric camera : seeing through fog
Design and construction of a snapshot full-Stokes polarimetric camera : seeing through fog
(English) Polarization is one of the properties of light and it is often put aside. Human beings receive light beams and process only the intensity and wavelength information. Our ...
Comunicaciones móviles
Comunicaciones móviles
El presente trabajo se encuadra dentro de la bibliografía básica de las comunicaciones móviles, con un tratamiento de la temática que se extiende hasta los futuros sistemas de terc...
SISTEMA FOTOVOLTAICO ISOLADO DE CONFIGURAÇÃO MISTA PARA FAMÍLIAS RIBEIRINHAS
SISTEMA FOTOVOLTAICO ISOLADO DE CONFIGURAÇÃO MISTA PARA FAMÍLIAS RIBEIRINHAS
Um sistema fotovoltaico pode apresentar diferentes configurações dependendo do tipo de demanda que se deseja atender. Este trabalho apresenta um sistema de configuração mista que c...
Efeito de Estratégia de Suplementação com Concentrado no Desempenho de Cabras Mestiças Saanen, em Dois Sistemas de Produção
Efeito de Estratégia de Suplementação com Concentrado no Desempenho de Cabras Mestiças Saanen, em Dois Sistemas de Produção
O experimento foi conduzido com os objetivos de avaliar o desempenho de cabras leiteiras mestiças Saanen, submetidas a duas estratégias de suplementação com concentrado (ESC): 30% ...
Interações humano, animal e ambiente
Interações humano, animal e ambiente
Este trabalho foi elaborado para investigar viabilidade de pontos positivos e negativos do Sistema de Integração-Lavoura-Pecuária e Floresta que envolve a produção de grãos, fibras...
ANÁLISE DO SISTEMA VIÁRIO DO BAIRRO CENTRO DA CIDADE DE SÃO JOÃO DO RIO DO PEIXE/PB
ANÁLISE DO SISTEMA VIÁRIO DO BAIRRO CENTRO DA CIDADE DE SÃO JOÃO DO RIO DO PEIXE/PB
A malha urbana não é formada apenas pelas áreas edificadas e áreas livres que se relacionam entre si, mas pelo conjunto de infraestrutura urbana que compõem um espaço urbano o qual...
Comportamiento estructural frente a sismo en sistemas concreto armado y estructuras metálicas en pabellón de la I.E. Daniel Merino Ruiz-2020
Comportamiento estructural frente a sismo en sistemas concreto armado y estructuras metálicas en pabellón de la I.E. Daniel Merino Ruiz-2020
La presente tesis titulada “Comportamiento Estructural frente a sismo en sistemas concreto armado y estructuras metálicas en pabellón de la I.E. Daniel Merino Ruiz-2020” ha tenido ...

Back to Top