Javascript must be enabled to continue!
Deepwater FPSO for Aquila Field Development in the Adriatic
View through CrossRef
Abstract
The FPSO recently installed in 850 m water depth for the challenging Aquila Field incorporates a number of intresting features. Although the field was discovered some tune ago, development has only now been made possible due to the technical advances in both subsea and turret mooring/riser systems combined with cost savings obtained in the conversion of an existing FPSO. The original turret mooring system, designed for 97 m water depth has now been transformed to operate in 850 m and includes the use of suction anchors, which we believe are the deepest yet employed. The process has been designed to cater for 9000 ppm H2S, and incorporates a crude oil stabilization column to maximise recovery. Due to the strict environmental regulations in the Mediterranean, the produced water treatment is designed to achieve less than 10 ppm Oil m water, or to offload produced water via shuttle tanker. This paper describes the Aquila FPSO and highlights how the latest technology and reuse of existing systems have provided an innovative and cost effective approach to develop the deep water Aquila field.
Introduction
The Aquila field development called for the production of two subsea completed wells in 850 m of water in the Adriatic sea, 50 km NE of Brindisi, Offshore Italy, plus provision for a third well. As there is no production or export infrastructure nearby, a stand alone FPSO system was envisaged. At the start of the project, the technical challenges to achieve this were considerable, especially in the following areas:–subsea tree design and installation,–riser armour wire material selection to withstand the high partial pressure of H2S (0.4 barg) in a potentially wet environment,–mooring and anchor system design,–mooring and riser installation requirements.
Furthermore, the field has only moderate reserves and a maximum production of 18,800 BOPD for a 5-7 years field life. This entailed strict budget restrictions for the project. By 1995, technical progress had been made and the projectcould be considered more seriously:–A deepwater subsea tree installation system called "Sistemi Alti Fondati" (SAF) had been sucessfully proven in shallow water.–Monohull FPSO's with flexible risers were being installed in 350m of water using technology which could be extrapolated to 850 m.–The existing FPSO "AGIP FIRENZE" was made available to the project.–Material tests were being carried out to qualify a suitable wire armour material for the flexible risers in sour service
By December 1995, the project was given the go-ahead. A Project management team was established and engineering started immediately on the various elements of the project. These covered subsea, turret/mooring, risers, topsides, their integration into the existing vessel and the vessel refurbishment and conversion itself. The approach taken with the specific project challenges for each of these elements are described below and general project and environmental data are given in Appendices A and B. The FPSO has now been sucessfully installed on site and at the time of writing is being prepared for first oil.
Subsea
The basic guideline for the subsea production system is to utilise the SAF concept. In addition to this, the safety of the system is the mandatory philosophy used and stressed in all selections.
Title: Deepwater FPSO for Aquila Field Development in the Adriatic
Description:
Abstract
The FPSO recently installed in 850 m water depth for the challenging Aquila Field incorporates a number of intresting features.
Although the field was discovered some tune ago, development has only now been made possible due to the technical advances in both subsea and turret mooring/riser systems combined with cost savings obtained in the conversion of an existing FPSO.
The original turret mooring system, designed for 97 m water depth has now been transformed to operate in 850 m and includes the use of suction anchors, which we believe are the deepest yet employed.
The process has been designed to cater for 9000 ppm H2S, and incorporates a crude oil stabilization column to maximise recovery.
Due to the strict environmental regulations in the Mediterranean, the produced water treatment is designed to achieve less than 10 ppm Oil m water, or to offload produced water via shuttle tanker.
This paper describes the Aquila FPSO and highlights how the latest technology and reuse of existing systems have provided an innovative and cost effective approach to develop the deep water Aquila field.
Introduction
The Aquila field development called for the production of two subsea completed wells in 850 m of water in the Adriatic sea, 50 km NE of Brindisi, Offshore Italy, plus provision for a third well.
As there is no production or export infrastructure nearby, a stand alone FPSO system was envisaged.
At the start of the project, the technical challenges to achieve this were considerable, especially in the following areas:–subsea tree design and installation,–riser armour wire material selection to withstand the high partial pressure of H2S (0.
4 barg) in a potentially wet environment,–mooring and anchor system design,–mooring and riser installation requirements.
Furthermore, the field has only moderate reserves and a maximum production of 18,800 BOPD for a 5-7 years field life.
This entailed strict budget restrictions for the project.
By 1995, technical progress had been made and the projectcould be considered more seriously:–A deepwater subsea tree installation system called "Sistemi Alti Fondati" (SAF) had been sucessfully proven in shallow water.
–Monohull FPSO's with flexible risers were being installed in 350m of water using technology which could be extrapolated to 850 m.
–The existing FPSO "AGIP FIRENZE" was made available to the project.
–Material tests were being carried out to qualify a suitable wire armour material for the flexible risers in sour service
By December 1995, the project was given the go-ahead.
A Project management team was established and engineering started immediately on the various elements of the project.
These covered subsea, turret/mooring, risers, topsides, their integration into the existing vessel and the vessel refurbishment and conversion itself.
The approach taken with the specific project challenges for each of these elements are described below and general project and environmental data are given in Appendices A and B.
The FPSO has now been sucessfully installed on site and at the time of writing is being prepared for first oil.
Subsea
The basic guideline for the subsea production system is to utilise the SAF concept.
In addition to this, the safety of the system is the mandatory philosophy used and stressed in all selections.
Related Results
FPSO's Today: What is the Optimum Concept?
FPSO's Today: What is the Optimum Concept?
ABSTRACT
FPSO technology over the past years has rapidly evolved from tanker based units with classical mooring systems to purpose-shaped new built vessels equipp...
The Sanha LPG FPSO
The Sanha LPG FPSO
Abstract
The FPSO industry will soon have the first LPG FPSO in operation. The SANHA LPG FPSO is the first gas related FPSO. With the installation of the LPG FPSO...
FPSOS for Deepwater Applications
FPSOS for Deepwater Applications
This paper addresses the design and challenges of FPSOs for deepwater applications. The building blocks of FPSOs of topsides, hull, turret, mooring and risers are reviewed and a de...
ROSA: New Challenges in West Africa Deepwater Developments
ROSA: New Challenges in West Africa Deepwater Developments
Abstract
Discovered in 1998, the Rosa field is located offshore Angola in the prolific Block 17, at a distance of 16 kilometers from the spread-moored Girassol FP...
FPSO Integrity; Structural Monitoring of Glas Dowr
FPSO Integrity; Structural Monitoring of Glas Dowr
Abstract
The objective of the Joint Industry project 'FPSO Integrity' is to provide insight in the fatigue loading of FPSO's and the accuracy and validity of comp...
Design and Conversion of FPSO Mystras
Design and Conversion of FPSO Mystras
Abstract
A recently completed FPSO conversion project shows some novel features in FPSO design. An existing trading tanker was selected for conversion into a 48,0...
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Abstract
In a North Sea storm during February 2011 the Gryphon Alpha FPSO broke four of her 10 mooring lines and moved partially off station, causing damage to su...
Golfinho Project-Well Construction
Golfinho Project-Well Construction
Abstract
The Golfinho Field is located in the Southeastern coast of Brazil, at water depths between 1,300 and 1,640m and is the first offshore deepwater developme...

