Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Roncador Field: Transport of P-36 and Installation of the Mooring System

View through CrossRef
Abstract This paper describes the transport and installation phases of the semi-submersible PETROBRAS 36, since the unit's depart from Davie shipyard in Canada, where the conversion had been undertaken, up to the hook-up of the mooring system in Roncador Field. The selection of dry transportation of P-36 from Canada to Brazil, using the heavy lift carrier Mighty Servant 1 from Dockwise, was driven by a combination of technical and strategic issues. A set of technical studies was performed to make this 32,700-ton heavy transport feasible, taking into account the risk factors involved in the operation. P-36 mooring system comprises 16 lines in taut leg configuration, using polyester ropes and Vertically Loaded Anchors (VLAs). The water depth at the anchor locations ranges from 1200 to 1520m. The installation of a mooring system of this size in such depths represented an enormous challenge. The irregular soil characteristics in Roncador where two subsea canyons converge near to the platform location presented an additional complication factor. Background Petrobras-36 Production Unit. The Spirit of Columbus semisubmersible platform was originally built as a drilling and production unit, able to process up to 100,000 bpd. Twelve mooring legs composed its original mooring system that was designed for a maximum water depth of 500m. The construction of the unit was concluded in 1994 but, up to 1996, when it was contracted by Petrobras and renamed to Petrobras-36, it had never operated. In order to operate in Roncador Field, located in Campos Basin, the Spirit of Columbus undertook an extensive upgrade, performed at Davie shipyard in Canada. The upgrade included the installation of new process facilities for 180,000 bpd of oil and 7,200,000 m3/d of gas and 24,000 m3/d water injection capacity and facilities for risers' support. Structural modifications to support new equipment and to comply with stability and buoyancy requirements were also executed. Paper OTC 12136 (Ref.3) gives an overview of Roncador development program and a detailed description of the platform upgrade is given in paper OTC 12140 (Ref. 4). Mooring System Upgrade. The water depth increase (from 500 to 1360m), the huge number of flexible risers supported by the Unit and the strong currents in Roncador resulted in the need to upgrade the Unit's mooring system to 16 legs. Following Petrobras specifications, the system was designed in a taut leg configuration, using polyester ropes 1800m long with a Minimum Break Load (MBL) of 1,000 tons. Project Design Mooring Ropes. The 1,800m polyester legs were divided in 3 segments in order to turn easier the operations with the ropes inside the Anchor Handling Vessels. The segments were supplied in different lengths, to enable the abandonment of the lines in buoys, after the pre-setting (see below). The ropes were designed including a surplus of 25% on top of the necessary Safety Factors to comply with eventual resistance losses during the Unit's lifetime. The amount of polyester to be purchased was enormous. So, Petrobras decided to split the purchase among three different suppliers.
Title: Roncador Field: Transport of P-36 and Installation of the Mooring System
Description:
Abstract This paper describes the transport and installation phases of the semi-submersible PETROBRAS 36, since the unit's depart from Davie shipyard in Canada, where the conversion had been undertaken, up to the hook-up of the mooring system in Roncador Field.
The selection of dry transportation of P-36 from Canada to Brazil, using the heavy lift carrier Mighty Servant 1 from Dockwise, was driven by a combination of technical and strategic issues.
A set of technical studies was performed to make this 32,700-ton heavy transport feasible, taking into account the risk factors involved in the operation.
P-36 mooring system comprises 16 lines in taut leg configuration, using polyester ropes and Vertically Loaded Anchors (VLAs).
The water depth at the anchor locations ranges from 1200 to 1520m.
The installation of a mooring system of this size in such depths represented an enormous challenge.
The irregular soil characteristics in Roncador where two subsea canyons converge near to the platform location presented an additional complication factor.
Background Petrobras-36 Production Unit.
The Spirit of Columbus semisubmersible platform was originally built as a drilling and production unit, able to process up to 100,000 bpd.
Twelve mooring legs composed its original mooring system that was designed for a maximum water depth of 500m.
The construction of the unit was concluded in 1994 but, up to 1996, when it was contracted by Petrobras and renamed to Petrobras-36, it had never operated.
In order to operate in Roncador Field, located in Campos Basin, the Spirit of Columbus undertook an extensive upgrade, performed at Davie shipyard in Canada.
The upgrade included the installation of new process facilities for 180,000 bpd of oil and 7,200,000 m3/d of gas and 24,000 m3/d water injection capacity and facilities for risers' support.
Structural modifications to support new equipment and to comply with stability and buoyancy requirements were also executed.
Paper OTC 12136 (Ref.
3) gives an overview of Roncador development program and a detailed description of the platform upgrade is given in paper OTC 12140 (Ref.
4).
Mooring System Upgrade.
The water depth increase (from 500 to 1360m), the huge number of flexible risers supported by the Unit and the strong currents in Roncador resulted in the need to upgrade the Unit's mooring system to 16 legs.
Following Petrobras specifications, the system was designed in a taut leg configuration, using polyester ropes 1800m long with a Minimum Break Load (MBL) of 1,000 tons.
Project Design Mooring Ropes.
The 1,800m polyester legs were divided in 3 segments in order to turn easier the operations with the ropes inside the Anchor Handling Vessels.
The segments were supplied in different lengths, to enable the abandonment of the lines in buoys, after the pre-setting (see below).
The ropes were designed including a surplus of 25% on top of the necessary Safety Factors to comply with eventual resistance losses during the Unit's lifetime.
The amount of polyester to be purchased was enormous.
So, Petrobras decided to split the purchase among three different suppliers.

Related Results

Evaluation of Advanced Fibers for Deepwater Synthetic Fiber Mooring Systems
Evaluation of Advanced Fibers for Deepwater Synthetic Fiber Mooring Systems
Abstract Mooring systems utilizing polyester ropes have facilitated exploration and production of deepwater fields and represent a step-change in mooring system d...
Mooring Safety Assessment Using Reliability Techniques
Mooring Safety Assessment Using Reliability Techniques
ABSTRACT The paper deals with the reliability of offshore mooring systems. Reliability techniques have been applied to assess mooring systems designed by the quas...
Dynamic Response of a SPAR-Type Floating Wind Turbine Foundation with Taut Mooring System
Dynamic Response of a SPAR-Type Floating Wind Turbine Foundation with Taut Mooring System
Compared with the traditional catenary or semi-taut mooring lines, the taut mooring system is more advantageous in many aspects, such as reduction of mooring line loads, erosion an...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
Neptune Project: Spar Hull, Mooring and Topsides Installation
Neptune Project: Spar Hull, Mooring and Topsides Installation
Abstract This paper describes the installation of the Neptune Spar at Viosca Knoll Block 826, approximately 90 miles south of Mobile, Alabama in the Gulf of Mexic...
Reliability of Mooring Systems: Application to Polyester Moorings
Reliability of Mooring Systems: Application to Polyester Moorings
Abstract The trend to deep water oilfields has accelerated the development of mooring systems. Future moorings requirements represent a considerable step out on c...
North Sea Mooring Systems: How Reliable Are They?
North Sea Mooring Systems: How Reliable Are They?
In recent years a number of high profile mooring failures have emphasised the high risk nature of this element of a floating structure. Semi-submersible Mobile Offshore Drilling Un...
Finite Element Analysis of Composite Mooring Tensioner Springs in Wave Energy Converters
Finite Element Analysis of Composite Mooring Tensioner Springs in Wave Energy Converters
Abstract Floating structures are widely used in the offshore oil and gas industry, in deep-sea wind farms, and ocean wave energy converters, where fixed-bottom desig...

Back to Top