Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Contracting and Project Strategy to Reduce the Costs

View through CrossRef
INTRODUCTION The Norwegian oil industry has developed and grown to a significant size from the 1970's through the 80's, and numerous large fields were developed under a business environment with high oil prices. The technological challenges were significant, but the expectation of high volumes of produced oil and increasing oil prices, secured the necessary funding for development of these large fields. Today this situation is dramatically changed, and the low oil price alone would make it uneconomic to develop the new fields. In addition to low oil prices, we are now also facing smaller reservoirs, deeper water and more sever environmental conditions. The general competitiveness of the Norwegian Continental Shelf is challenged. Many initiatives have been launched in Norway to support the necessary improvements in business performance. The Norwegian oil and gas industry together with the authorities have through 1994 worked together in the NORSOK initiative to identify means to save 40-50% in cost and time for development of new fields. The industry has developed new technology. The authorities have been addressing the fiscal conditions and general framework for the oil companies, and several areas of improvement have been identified and to some degree implemented by the Operator. The most important improvements are probably those that are directly implemented in actual development projects, and Statoil/Kvaxner have together some joint experiences that can illustrate how such ideas successfully can be implemented. In the following we will give a brief introduction to specific achievements b-three such projects. The three projects to be introduced are: Sleipner T, Treatment platform. In the Sleipner Vest Development, S1eipner A modifications . Required modifications to the existing platform Sleipner A to import production from Sleipner Vest. Norne Development SLEIPNER VEST Project description (see illustration) – Wellhead platform, SLB – 12 km 20" pipeline – Proows platform, SLT – Bridge connection to existing Sleipner A platform SLA – Upgrading of SLA control and utility systems – Start-up 01.04.97, improved to 01.10.96 – Estimated cost, approx. 1,5 G$ Contract Strategy A traditional contract strategy was selected for the Sleipner Vest development.–Engineering on Fixed Fee + reimbursable manhours–Procurement based on competitive bidding–Fabrication lump sum with preceding engineering completed to a high degree–Installation and offshore completion–All contracts based on competitive international bidding The project was started on this basis, and the engineering work was awarded to Kwemer Engineering for the treatment platform and for overall project integrity. A separate engineering contract was awarded to NRC for the wellhead platform. An initiative was taken by the operator Statoil to reduce cost and execution time, and all parties involved agreed to contribute in such process. Statoil's revised strategy comprised the following main elements:–Reduced lead time–Share Cost savings with parties involved in the process–Focus on action and on end products–Revised Business Processes–Reorganise Project Management Organisation–Optimize further the technical concept andstandards Kværner Engineering and Statoil had been working together since 1991 on the project. Plan for Development and operation was submitted to the authorities December 1991.
Title: Contracting and Project Strategy to Reduce the Costs
Description:
INTRODUCTION The Norwegian oil industry has developed and grown to a significant size from the 1970's through the 80's, and numerous large fields were developed under a business environment with high oil prices.
The technological challenges were significant, but the expectation of high volumes of produced oil and increasing oil prices, secured the necessary funding for development of these large fields.
Today this situation is dramatically changed, and the low oil price alone would make it uneconomic to develop the new fields.
In addition to low oil prices, we are now also facing smaller reservoirs, deeper water and more sever environmental conditions.
The general competitiveness of the Norwegian Continental Shelf is challenged.
Many initiatives have been launched in Norway to support the necessary improvements in business performance.
The Norwegian oil and gas industry together with the authorities have through 1994 worked together in the NORSOK initiative to identify means to save 40-50% in cost and time for development of new fields.
The industry has developed new technology.
The authorities have been addressing the fiscal conditions and general framework for the oil companies, and several areas of improvement have been identified and to some degree implemented by the Operator.
The most important improvements are probably those that are directly implemented in actual development projects, and Statoil/Kvaxner have together some joint experiences that can illustrate how such ideas successfully can be implemented.
In the following we will give a brief introduction to specific achievements b-three such projects.
The three projects to be introduced are: Sleipner T, Treatment platform.
In the Sleipner Vest Development, S1eipner A modifications .
Required modifications to the existing platform Sleipner A to import production from Sleipner Vest.
Norne Development SLEIPNER VEST Project description (see illustration) – Wellhead platform, SLB – 12 km 20" pipeline – Proows platform, SLT – Bridge connection to existing Sleipner A platform SLA – Upgrading of SLA control and utility systems – Start-up 01.
04.
97, improved to 01.
10.
96 – Estimated cost, approx.
1,5 G$ Contract Strategy A traditional contract strategy was selected for the Sleipner Vest development.
–Engineering on Fixed Fee + reimbursable manhours–Procurement based on competitive bidding–Fabrication lump sum with preceding engineering completed to a high degree–Installation and offshore completion–All contracts based on competitive international bidding The project was started on this basis, and the engineering work was awarded to Kwemer Engineering for the treatment platform and for overall project integrity.
A separate engineering contract was awarded to NRC for the wellhead platform.
An initiative was taken by the operator Statoil to reduce cost and execution time, and all parties involved agreed to contribute in such process.
Statoil's revised strategy comprised the following main elements:–Reduced lead time–Share Cost savings with parties involved in the process–Focus on action and on end products–Revised Business Processes–Reorganise Project Management Organisation–Optimize further the technical concept andstandards Kværner Engineering and Statoil had been working together since 1991 on the project.
Plan for Development and operation was submitted to the authorities December 1991.

Related Results

Improvement of the project control system : a case study of an interior decoration company
Improvement of the project control system : a case study of an interior decoration company
This thesis aimed to reduce the delay and unnecessarily accelerated or crashed activities of the project by improving the project control system of an interior decoration company. ...
THE EVALUATION OF NEHEMIAH'S PROJECT MANAGEMENT APPROACH IN RELATION TO (PROJECT MANAGEMENTS INSTITUTE) PMI STANDARDS
THE EVALUATION OF NEHEMIAH'S PROJECT MANAGEMENT APPROACH IN RELATION TO (PROJECT MANAGEMENTS INSTITUTE) PMI STANDARDS
This research examines the project management strategies utilized by Nehemiah in the reconstruction of Jerusalem's walls, as described in the biblical text, and assesses their comp...
PROJECT MANAGEMENT SYSTEM AT AN ENTERPRISE: THE FOUNDATIONS OF EFFECTIVE FORMATION
PROJECT MANAGEMENT SYSTEM AT AN ENTERPRISE: THE FOUNDATIONS OF EFFECTIVE FORMATION
The article examines the principles of effective formation of a project management system at an enterprise. In the modern environment, project management standards and management i...
Blockchains and Transaction Costs
Blockchains and Transaction Costs
This paper examines current business applications of blockchain technology and discusses blockchain implications for transaction costs. Blockchains are a relatively new set of tech...
Economic Burden of Sickle Cell Disease among Children and Adults.
Economic Burden of Sickle Cell Disease among Children and Adults.
Abstract Background: The economic burden of sickle cell disease (SCD) has not been determined. Cost-of-care estimates improve health care planning, inform research p...
Application of Mitigation Hierarchy During the Development Phase of Tilenga Project, Uganda
Application of Mitigation Hierarchy During the Development Phase of Tilenga Project, Uganda
Abstract The Tilenga project operated by TotalEnergies Exploration and Production Uganda, is an onshore oil project located in the Lake Albert Basin of Uganda. The p...
The relationship between project management process characteristics and performance outcomes
The relationship between project management process characteristics and performance outcomes
Purpose– The aim of this paper is to examine the links between project management process characteristics and project-level and firm-level performance outcomes to test the hypothes...
Hawiyah NGL Recovery Project: Operational Considerations during Project Design
Hawiyah NGL Recovery Project: Operational Considerations during Project Design
ABSTRACT Saudi Aramco new NGL Recovery Project has been managed by an integrated team from project managements and proponent. Project management team members have...

Back to Top