PERANCANGAN PEMBANGKIT LISTRIK TENAGA MIKROHIDRO. STUDI KASUS DI CURUG CIGEUNTIS, KECAMATAN TEGALWARU, KABUPATEN KARAWANG, JAWA BARAT
View through CrossRef
This research aims to create a design model of microhydro powerplant, and implement that design model to particular location, which decided location in this research is Cigeuntis Waterfall. Output of this research can be utilized by microhydro power plant practitioners as a tool, and stakeholders to valuing natural resources potential in their area. Cigeuntis Waterfall is selected because it has sufficient water in raining season, and more important, in dry season. Analysis descriptive method is used in this research with qualitative approach. Technics of Engineering is type of this research, encompassing design formulation of microhydro power plant, formula validation by comparing design of microhydro power plant based on formula with existing microhydro power plant in PLN Laboratory, and designing microhydro power plant components like intake, settling basin, penstock pipe, turbine, pulley, and generator regarding water flow and net head of Cigeuntis Waterfall.
Results of this research are if microhydro power plant build at Cigeuntis Waterfall with 0.55 m3/s water flow and net head is 25 m, the size of components must be 2.97 m2 for intake, 6.6 m x 0.83 m x 2.2 m for settling basin, 48 cm for penstock diameter and 0.17 cm for its thickness, 11.81 inch for turbine diameter and 3.8 inch for its length, 2.1 inch for blade turbine space, 18 blades turbine needed, 11.81 inch for pulley diameter which connected to turbine and 5.2 inch diameter which connected to generator, and capacity of generator is 104.1 kW.
This formula created in Microsoft Excel format, and after validation with existing microhydro power plant, there is not any substantial difference as the result. Therefore, the conclusion is this design model of microhydro power plant able to be implemented.
Abstrak
Penelitian ini bertujuan untuk menghasilkan model perancangan PLTMH, dan mengimplementasikannya pada lokasi tertentu, yang pada penelitian ini ditetapkan lokasinya adalah Curug Cigeuntis. Model perancangan ini nantinya bisa digunakan oleh para perancang PLTMH sebagai observasi awal, dan juga digunakan oleh para pemangku kebijakan dalam melihat potensi sumber daya alam di daerahnya. Curug Cigeuntis dipilih menjadi lokasi pengujian sebagai contoh implementasi yang dari model perancangan yang dibuat karena ketersediaan air di sana boleh dikatakan tinggi akibat curah hujan yang besar. Penelitian ini menggunakan metode deskriptif analisis melalui pendekatan kualitatif. Jenis penelitian yang dipilih ialah rekayasa teknik dengan mencangkup pembuatan formulasi perancangan PLTMH, validasi formulasi perancangan PLTMH dengan acuan sistem PLTMH yang terpasang pada Laboratorium Tenaga Air Mini milik PLN, dan perancangan b agian PLTMH, yaitu saluran intake, bak penenang, pipa penstock, turbin, pulley, dan generator mempertimbangkan kondisi alam seperti debit air dan tinggi jatuh air pada Curug Cigeuntis. Hasil penelitian menunjukan bahwa Curug Cigeuntis dengan debit andalan sebesar 0.55 m3/s dan tinggi jatuh air sebesar 25 m, diperoleh ukuran intake 2.97 m2, ukuran bak penenang 6.6 m x 0.83 m x 2.2 m, ukuran diameter penstock 48 cm dan ketebalannya 0.17 cm, ukuran diameter turbin 11.81 inch dengan panjang 3.8 inch, jarak antara pisau 2.1 inch, dan jumlah pisau turbin sebanyak 18 buah. Ukuran pulley besarnya pada bagian diameter terhubung turbin adalah 11.81 inch dan diameter terhubung generator 5.2 inch. Kapasitas generator yang digunakan sebesar 104.1 kw. Formulasi perancangan yang dibuat menggunakan program Microsoft Excel, telah divalidasi dengan sistem PLTMH terpasang dan tidak didapati perbedaan yang substansial sehingga dapat disimpulkan perancangan PLTMH layak untuk diimplementasikan pada perancangan tertentu.
Universitas Negeri Jakarta
Title: PERANCANGAN PEMBANGKIT LISTRIK TENAGA MIKROHIDRO. STUDI KASUS DI CURUG CIGEUNTIS, KECAMATAN TEGALWARU, KABUPATEN KARAWANG, JAWA BARAT
Description:
This research aims to create a design model of microhydro powerplant, and implement that design model to particular location, which decided location in this research is Cigeuntis Waterfall.
Output of this research can be utilized by microhydro power plant practitioners as a tool, and stakeholders to valuing natural resources potential in their area.
Cigeuntis Waterfall is selected because it has sufficient water in raining season, and more important, in dry season.
Analysis descriptive method is used in this research with qualitative approach.
Technics of Engineering is type of this research, encompassing design formulation of microhydro power plant, formula validation by comparing design of microhydro power plant based on formula with existing microhydro power plant in PLN Laboratory, and designing microhydro power plant components like intake, settling basin, penstock pipe, turbine, pulley, and generator regarding water flow and net head of Cigeuntis Waterfall.
Results of this research are if microhydro power plant build at Cigeuntis Waterfall with 0.
55 m3/s water flow and net head is 25 m, the size of components must be 2.
97 m2 for intake, 6.
6 m x 0.
83 m x 2.
2 m for settling basin, 48 cm for penstock diameter and 0.
17 cm for its thickness, 11.
81 inch for turbine diameter and 3.
8 inch for its length, 2.
1 inch for blade turbine space, 18 blades turbine needed, 11.
81 inch for pulley diameter which connected to turbine and 5.
2 inch diameter which connected to generator, and capacity of generator is 104.
1 kW.
This formula created in Microsoft Excel format, and after validation with existing microhydro power plant, there is not any substantial difference as the result.
Therefore, the conclusion is this design model of microhydro power plant able to be implemented.
Abstrak
Penelitian ini bertujuan untuk menghasilkan model perancangan PLTMH, dan mengimplementasikannya pada lokasi tertentu, yang pada penelitian ini ditetapkan lokasinya adalah Curug Cigeuntis.
Model perancangan ini nantinya bisa digunakan oleh para perancang PLTMH sebagai observasi awal, dan juga digunakan oleh para pemangku kebijakan dalam melihat potensi sumber daya alam di daerahnya.
Curug Cigeuntis dipilih menjadi lokasi pengujian sebagai contoh implementasi yang dari model perancangan yang dibuat karena ketersediaan air di sana boleh dikatakan tinggi akibat curah hujan yang besar.
Penelitian ini menggunakan metode deskriptif analisis melalui pendekatan kualitatif.
Jenis penelitian yang dipilih ialah rekayasa teknik dengan mencangkup pembuatan formulasi perancangan PLTMH, validasi formulasi perancangan PLTMH dengan acuan sistem PLTMH yang terpasang pada Laboratorium Tenaga Air Mini milik PLN, dan perancangan b agian PLTMH, yaitu saluran intake, bak penenang, pipa penstock, turbin, pulley, dan generator mempertimbangkan kondisi alam seperti debit air dan tinggi jatuh air pada Curug Cigeuntis.
Hasil penelitian menunjukan bahwa Curug Cigeuntis dengan debit andalan sebesar 0.
55 m3/s dan tinggi jatuh air sebesar 25 m, diperoleh ukuran intake 2.
97 m2, ukuran bak penenang 6.
6 m x 0.
83 m x 2.
2 m, ukuran diameter penstock 48 cm dan ketebalannya 0.
17 cm, ukuran diameter turbin 11.
81 inch dengan panjang 3.
8 inch, jarak antara pisau 2.
1 inch, dan jumlah pisau turbin sebanyak 18 buah.
Ukuran pulley besarnya pada bagian diameter terhubung turbin adalah 11.
81 inch dan diameter terhubung generator 5.
2 inch.
Kapasitas generator yang digunakan sebesar 104.
1 kw.
Formulasi perancangan yang dibuat menggunakan program Microsoft Excel, telah divalidasi dengan sistem PLTMH terpasang dan tidak didapati perbedaan yang substansial sehingga dapat disimpulkan perancangan PLTMH layak untuk diimplementasikan pada perancangan tertentu.
Related Results
PROSES MANUFAKTUR PEMBANGKIT LISTRIK TENAGA MIKROHIDRO
PROSES MANUFAKTUR PEMBANGKIT LISTRIK TENAGA MIKROHIDRO
Bagaimana cara pembuatan rangka dan komponen pada mesin pembangkit listrik tenaga mikrohidro Bagaimana proses perakitan mesin pembangkit listrik tenaga mikrohidro. Bagaiman...
DAMPAK TEKNOLOGI TERHADAP PROSES BELAJAR MENGAJAR
DAMPAK TEKNOLOGI TERHADAP PROSES BELAJAR MENGAJAR
DAFTAR PUSTAKAAditama, M. H. R., & Selfiardy, S. (2022). Kehidupan Mahasiswa Kuliah Sambil Bekerja di Masa Pandemi Covid-19. Kidspedia: Jurnal Pendidikan Anak Usia Dini, 3(...
PELATIHAN PERAWATAN PEMBANGKIT LISTRIK TENAGA MIKROHIDRO UNTUK MENINGKATKAN EFISIENSI DAN FUNGSI PLTMH DI DESA PESAWARAN INDAH KECAMATAN WAY RATAI KABUPATEN PESAWARAN
PELATIHAN PERAWATAN PEMBANGKIT LISTRIK TENAGA MIKROHIDRO UNTUK MENINGKATKAN EFISIENSI DAN FUNGSI PLTMH DI DESA PESAWARAN INDAH KECAMATAN WAY RATAI KABUPATEN PESAWARAN
Di Desa Pesawaran Indah Kecamatan Way Ratai banyak menpunyai potensi aliran air sungai yang bisa dimanfaatkan sebagai Pembangkit Listrik Tenaga Mikrohidro. Terjunan air pada aliran...
Studi Kelayakan Aspek Finansial Pembangunan Pembangkit Listrik Tenaga Piko-hidro untuk Listrik Desa dengan Penggerak Mula Pompa Sentrifugal Sebagai Turbin
Studi Kelayakan Aspek Finansial Pembangunan Pembangkit Listrik Tenaga Piko-hidro untuk Listrik Desa dengan Penggerak Mula Pompa Sentrifugal Sebagai Turbin
Pompa sebagai turbin (PST) merupakan salah satu solusi yang ditawarkan oleh para peneliti agar masyarakat lebih mudah mendapatkan turbin air untuk pembangkit listrik tenaga piko-hi...
Model Hybrid Pembangkit Listrik Di Pedesaan
Model Hybrid Pembangkit Listrik Di Pedesaan
Energi listrik merupakan salah satu jenis energi yang paling banyak digunakan dalam aktivitas manusia sehari-hari. pemenuhan kebutuhan energi listrik dapat meningkatkan kesejahtera...
Perencanaan Pembangkit Listrik Tenaga Mikrohidro pada Sungai Batee Iliek Samalanga Bireuen
Perencanaan Pembangkit Listrik Tenaga Mikrohidro pada Sungai Batee Iliek Samalanga Bireuen
Pembangkit Listrik Tenaga Mikrohidro merupakan salah satu alternatif pembangkit listrik skala kecil yang dapat diterapkan di daerah pedesaan dimana tersedia aliran sungai yang memp...
Peranan Heat Recovery Steam Generator (HRSG) pada Pembangkit Listrik PLTGU
Peranan Heat Recovery Steam Generator (HRSG) pada Pembangkit Listrik PLTGU
Pembangkit listrik mengubah berbagai sumber energi non-listrik menjadi listrik menggunakan berbagai bahan bakar seperti minyak, batu bara, dan energi terbarukan. Jenis pembangkit l...
PROSES MANUFAKTUR PEMBANGKIT LISTRIK TENAGA MIKROHIDRO
PROSES MANUFAKTUR PEMBANGKIT LISTRIK TENAGA MIKROHIDRO
Pembangkit Listrik Tenaga Mikrohidro (PLTMH) merupakan sesuatu pembangkit listrik berskala kecil dengan kapasitas pembangkitan tenaga listrik 1 s/ d 150 kW yang memakai tenaga air ...