Javascript must be enabled to continue!
A Pilot Subsea Completion Installation in the Ninian Field, U.K. North Sea
View through CrossRef
ABSTRACT
A project to design, manufacture, test, install, commission and operate a single well prototype subsea completion of a suspended appraisal well on the Ninian Unit has been successfully accomplished. This was carried out over the period September 1976 through February 1980.
The main objective of the project was to evaluate prototype subsea equipment for both producing and injection wells which could be needed in the future to supplement fixed platform locations. The opportunity was taken to specify a number of designs which would have merit if a large supplemental programme was ever required.
The paper describes the now installed system of wellhead, flowlines and platform facilities. The system was tested on land by subsystems, systems from separate suppliers and finally as an integrated system. Installation of wellhead equipment from a semisubmersible and of flowlines by a layship was conducted simultaneously towards the end of 1979.
The various project phases are discussed and the results presented.
INTRODUCTION
The Ninian Unit in UK Blocks 3/3 and 3/8 as shown in Figure I contains in excess of 1 billion barrels of recoverable reserves. It is in the Northern north sea with a water depth of about 450'. The field development programme approved provided for platforms in the northern, central and southern sectors of the field as well as interconnecting field pipelines and a pipeline to shore. Platform slots allow for drilling a maximum of 109 wells.
As it was recognised that there might be a need to supplement the wells drilled from the platforms, it was decided to develop a specification and tender for subsea completion systems to quantify the state of the art, designs and costs. The equipment was to cater for new wells or reentry completion of suspended appraisal wells, either producers or injectors. Bids were received, reviewed and the capability to complete subsea to specification verified.
The final decision was made in early 1977 to contract for a single well completion to permit first hand design, manufacture, testing, installation and operating experience. As firm needs were unknown, it was decided to include requirements to cater for the most complicated case and therefore a diverless design with through flowline (TFL) maintenance capabilities was justified. To gain knowledge on systems suitable for complicated single wells, manifolds and templates, multiplexed production controls were specified. A split tree to provide additional safety during pull-ins and maintenance operations, and wellhead protection against fishing equipment and small anchors were agreed.
Consideration was given to drilling a new well but review of the suspended appraisal wells determined several were suitable for re-entry and completion. Based on its low profile, downhole configuration (9 8" casing to total depth), and distance from the Central Platform which would give a good test of TFL tools, as well as minimising interference with other field facilities, Well 3/3-5A was selected.
The project having been initiated saw the engineering group, which was originally set up only to conduct feasibility studies and other preliminary work, follow through from design to commissioning.
Title: A Pilot Subsea Completion Installation in the Ninian Field, U.K. North Sea
Description:
ABSTRACT
A project to design, manufacture, test, install, commission and operate a single well prototype subsea completion of a suspended appraisal well on the Ninian Unit has been successfully accomplished.
This was carried out over the period September 1976 through February 1980.
The main objective of the project was to evaluate prototype subsea equipment for both producing and injection wells which could be needed in the future to supplement fixed platform locations.
The opportunity was taken to specify a number of designs which would have merit if a large supplemental programme was ever required.
The paper describes the now installed system of wellhead, flowlines and platform facilities.
The system was tested on land by subsystems, systems from separate suppliers and finally as an integrated system.
Installation of wellhead equipment from a semisubmersible and of flowlines by a layship was conducted simultaneously towards the end of 1979.
The various project phases are discussed and the results presented.
INTRODUCTION
The Ninian Unit in UK Blocks 3/3 and 3/8 as shown in Figure I contains in excess of 1 billion barrels of recoverable reserves.
It is in the Northern north sea with a water depth of about 450'.
The field development programme approved provided for platforms in the northern, central and southern sectors of the field as well as interconnecting field pipelines and a pipeline to shore.
Platform slots allow for drilling a maximum of 109 wells.
As it was recognised that there might be a need to supplement the wells drilled from the platforms, it was decided to develop a specification and tender for subsea completion systems to quantify the state of the art, designs and costs.
The equipment was to cater for new wells or reentry completion of suspended appraisal wells, either producers or injectors.
Bids were received, reviewed and the capability to complete subsea to specification verified.
The final decision was made in early 1977 to contract for a single well completion to permit first hand design, manufacture, testing, installation and operating experience.
As firm needs were unknown, it was decided to include requirements to cater for the most complicated case and therefore a diverless design with through flowline (TFL) maintenance capabilities was justified.
To gain knowledge on systems suitable for complicated single wells, manifolds and templates, multiplexed production controls were specified.
A split tree to provide additional safety during pull-ins and maintenance operations, and wellhead protection against fishing equipment and small anchors were agreed.
Consideration was given to drilling a new well but review of the suspended appraisal wells determined several were suitable for re-entry and completion.
Based on its low profile, downhole configuration (9 8" casing to total depth), and distance from the Central Platform which would give a good test of TFL tools, as well as minimising interference with other field facilities, Well 3/3-5A was selected.
The project having been initiated saw the engineering group, which was originally set up only to conduct feasibility studies and other preliminary work, follow through from design to commissioning.
Related Results
Ninian Third Party Project: A Unique North Sea Challenge
Ninian Third Party Project: A Unique North Sea Challenge
ABSTRACT
The Ninian Field, operated by Chevron on behalf of the Ninian Field Group, is a mature North Sea producer. Rationalisation of the topside facilities and ...
Subsea Factory–Standardization of the Brownfield Factory
Subsea Factory–Standardization of the Brownfield Factory
Abstract
As part of the corporate technology strategy Statoil has launched a technology plan for the Subsea Factory concept. The plan describes how to combine subsea...
Ormen Lange Subsea Production System
Ormen Lange Subsea Production System
Abstract
This paper presents the concept and the technical solutions developed and applied to the Ormen Lange subsea production system. First, the key technical c...
Design, Installation, And Connection Of Subsea Lines On East Frigg Field
Design, Installation, And Connection Of Subsea Lines On East Frigg Field
ABSTRACT
This paper describes the subsea network which interconnects the three subsea templates at EAST FRIGG field, and connects this field to the FRIGG field, 1...
Subsea Separation and Reinjection of Produced Water
Subsea Separation and Reinjection of Produced Water
Abstract
Some of the most significant recent development in subsea design has been within subsea processing, in particular the removal of produced water from the ...
Subsea Facilities
Subsea Facilities
Abstract
This paper presents the system design and concept solutions selected for the Ormen Lange subsea facilities.
The field is located in a r...
Subsea Production Controls-The Trend Toward Simplification
Subsea Production Controls-The Trend Toward Simplification
Abstract
Control of subsea wellheads has evolved from the earliest diver operated wellheads to systems involving sophisticated electro-hydraulic techniques. With ...
A New Approach to Subsea Intervention
A New Approach to Subsea Intervention
ABSTRACT
In March 1987 representatives of Statoil and the Asea Brown Boveri Group could witness the completion of a successful sea test of a new subsea interventi...

