Javascript must be enabled to continue!
The Troll Olje Platform
View through CrossRef
ABSTRACT
The Detail Engineering of the Troll Olje Platform commenced in May 1992 with the objective of developing an optimum platform solution both economically and technically within a time constraint of 44 months measured up to and including start of oil and gas production offshore. The challenges as given by the Troll Olje Field Characteristics are a large water depth in combination with difficult soil conditions, oil reserves contained in thin layers and a shallow formation covering a wide a real extent and finally the time limit for first oil determined by reduced recovery in the event that gas production from Troll Phase 1 is started first. The objectives have been challenged by seeking new approaches within the project execution principles and a platform concept based on a catenary anchored self contained concrete semi-submersible with modularised topsides including maximized onshore/atshore work resulting in a completed platform prior to tow out.
INTRODUCTION
This paper gives a presentation of the Troll Olje Platform concept, project execution strategy and activity sequence as a solution to the challenges governed by the field characteristics and inherent time constraint due to Troll Phase 1 start-up schedule. Included is a brief review of the design considerations followed by a description of the main platform elements, i.e. the topside facilities, concrete substructure and the mooring system. A special design feature is the topsides structural concept which is emphasized and discussed separately. Finally fabrication, installation and platform completion prior to first oil are presented.
The development concept for Troll Olje is based on a single floating self-contained production and quarters (PO) platform as a field centre with associated subsea system. The substructure is a concrete semi submersible. The Floating Production Unit (FPU) will be connected to four subsea clusters with a capacity of 26 production wells from the Troll West Oil Province (TWOP). Stabilized oil and dehydrated gas is trans- ported through pipelines to shore with the gas routed via the Troll Phase 1 platform. Continuous gas injection and artificial gas lift are provided for. The Floating Production Unit is shown in figure 1.
The project schedule from start detail engineering to production start-up is 44 months.
Although the development project includes production from the TWOP the FPU will be designed also to cater for future tie-in of up to five clusters having a capacity of up to 32 oil producing wells from the Troll West Gas Province (TWGP).
PLATFORM PROJECT EXECUTION
Execution Principles
The development phase of the Troll Olje Platform Project refers to the phase of the work execution which concludes with the facilities being ready to commence production of oil and gas offshore. The project shall be executed in accordance with the basic philosophy of engaging contractors to carry out the following main activities;Detail Engineering DesignEquipment and Material ProcurementFabrication, Construction, Mechanical Completion and CommissioningAtshore Installation, Hook-up and CommissioningOffshore Installation, Hook-up and Commissioning
The exception, however, being the commissioning execution which will be undertaken by the Operator with assistance from a hook-up contractor working in an integrated team.
Title: The Troll Olje Platform
Description:
ABSTRACT
The Detail Engineering of the Troll Olje Platform commenced in May 1992 with the objective of developing an optimum platform solution both economically and technically within a time constraint of 44 months measured up to and including start of oil and gas production offshore.
The challenges as given by the Troll Olje Field Characteristics are a large water depth in combination with difficult soil conditions, oil reserves contained in thin layers and a shallow formation covering a wide a real extent and finally the time limit for first oil determined by reduced recovery in the event that gas production from Troll Phase 1 is started first.
The objectives have been challenged by seeking new approaches within the project execution principles and a platform concept based on a catenary anchored self contained concrete semi-submersible with modularised topsides including maximized onshore/atshore work resulting in a completed platform prior to tow out.
INTRODUCTION
This paper gives a presentation of the Troll Olje Platform concept, project execution strategy and activity sequence as a solution to the challenges governed by the field characteristics and inherent time constraint due to Troll Phase 1 start-up schedule.
Included is a brief review of the design considerations followed by a description of the main platform elements, i.
e.
the topside facilities, concrete substructure and the mooring system.
A special design feature is the topsides structural concept which is emphasized and discussed separately.
Finally fabrication, installation and platform completion prior to first oil are presented.
The development concept for Troll Olje is based on a single floating self-contained production and quarters (PO) platform as a field centre with associated subsea system.
The substructure is a concrete semi submersible.
The Floating Production Unit (FPU) will be connected to four subsea clusters with a capacity of 26 production wells from the Troll West Oil Province (TWOP).
Stabilized oil and dehydrated gas is trans- ported through pipelines to shore with the gas routed via the Troll Phase 1 platform.
Continuous gas injection and artificial gas lift are provided for.
The Floating Production Unit is shown in figure 1.
The project schedule from start detail engineering to production start-up is 44 months.
Although the development project includes production from the TWOP the FPU will be designed also to cater for future tie-in of up to five clusters having a capacity of up to 32 oil producing wells from the Troll West Gas Province (TWGP).
PLATFORM PROJECT EXECUTION
Execution Principles
The development phase of the Troll Olje Platform Project refers to the phase of the work execution which concludes with the facilities being ready to commence production of oil and gas offshore.
The project shall be executed in accordance with the basic philosophy of engaging contractors to carry out the following main activities;Detail Engineering DesignEquipment and Material ProcurementFabrication, Construction, Mechanical Completion and CommissioningAtshore Installation, Hook-up and CommissioningOffshore Installation, Hook-up and Commissioning
The exception, however, being the commissioning execution which will be undertaken by the Operator with assistance from a hook-up contractor working in an integrated team.
Related Results
Handling The Oil Zone On Troll
Handling The Oil Zone On Troll
Abstract
The Troll field is a giant gas field but below the gas cap 4 billion barrels of oil are located in an oil layer varying from 4–27m and covering an area o...
Troll Oil Development Concept
Troll Oil Development Concept
ABSTRACT
Underneath the large gas accumulation of the Troll field lies a considerable volume of oil. However, its development requires an innovative approach beca...
Subsea Separation and Reinjection of Produced Water
Subsea Separation and Reinjection of Produced Water
Abstract
Some of the most significant recent development in subsea design has been within subsea processing, in particular the removal of produced water from the ...
Carl Troll
Carl Troll
Carl Troll published numerous articles in various fields of geography. The present article is focused on some remarkable publications that have essentially contributed to progress ...
Completion Technology On Troll-Innovation And Simplicity
Completion Technology On Troll-Innovation And Simplicity
Abstract
The Troll Oil subsea development involves innovative completion technology such as sand control screens with inflow control devices, hydraulically contro...
For Whom the Bell Trolls: Shifting Troll Behaviour in the Twitter Brexit Debate
For Whom the Bell Trolls: Shifting Troll Behaviour in the Twitter Brexit Debate
AbstractIn 2017 Twitter released a list of 2,752 accounts believed to be connected to state‐sponsored Russian operative manipulation of the 2016 American Election. We investigate t...
Deepwater Platform Design
Deepwater Platform Design
ABSTRACT
Results of preliminary platform design studies enable engineers"to identify and appraise major variables affecting deepwater platform capabilities. Trans...
The Removal of the Maureen Steel Gravity Platform
The Removal of the Maureen Steel Gravity Platform
Abstract
The Maureen drilling, production and oil storage platform is located in 95.6m of water in block 16/29 of the U.K. Continental Shelf, and consists of a la...

