Javascript must be enabled to continue!
Offshore Replacement of a Damaged FPSO Fairlead
View through CrossRef
Abstract
In 2010, the operator completed the successful replacement of a damaged fairlead within the mooring system of its FPSO (Floating Production, Storage and Offloading). This is believed to be the first time that a fairlead has been changed-out in situ on any floating installation in the North Sea. This was a complex operation involving many different vessels and topsides activities. This paper details how the damaged fairlead was safely secured and replaced.
The replaced fairlead was deemed irreparable because one of the axle retaining plates and its associated bolts were missing. However, after further ROV (Remotely Operated Vehicle) inspections, it was discovered that the remaining seven fairleads were also displaying symptoms of the same failure mode i.e. axle retaining bolts were missing or found loose placing further strain on the remaining bolts.
The condition of the axle retaining bolts was deteriorating and the operator was unsure when the next catastrophic failure could occur. Therefore, ROVs were used to secure the seven failreads as effectively as possible by replacing/tightening bolts and air divers were mobilized to install pins to apply additional clamping force while allowing access to the original retaining bolts. The original bolts were replaced and segregated so that they could be analysed onshore.
An investigation was undertaken to understand the failure mode of the FPSO fairleads. It was hoped to compare the differing levels of damage to different factors such as weather, mooring line catenaries, etc… to determine which factors are significant.
It was concluded that the bolt damage was mainly the result of design issues. A combination of QA/QC (quality assurance/quality control) issues, environmental and operating conditions could explain the differing levels of fairlead damage.
The integrity of the mooring system was severely under threat throughout. Plus, replacing a fairlead is a long and costly exercise, therefore early identification of fairlead bolt issues and intervention is extremely valuable.
Title: Offshore Replacement of a Damaged FPSO Fairlead
Description:
Abstract
In 2010, the operator completed the successful replacement of a damaged fairlead within the mooring system of its FPSO (Floating Production, Storage and Offloading).
This is believed to be the first time that a fairlead has been changed-out in situ on any floating installation in the North Sea.
This was a complex operation involving many different vessels and topsides activities.
This paper details how the damaged fairlead was safely secured and replaced.
The replaced fairlead was deemed irreparable because one of the axle retaining plates and its associated bolts were missing.
However, after further ROV (Remotely Operated Vehicle) inspections, it was discovered that the remaining seven fairleads were also displaying symptoms of the same failure mode i.
e.
axle retaining bolts were missing or found loose placing further strain on the remaining bolts.
The condition of the axle retaining bolts was deteriorating and the operator was unsure when the next catastrophic failure could occur.
Therefore, ROVs were used to secure the seven failreads as effectively as possible by replacing/tightening bolts and air divers were mobilized to install pins to apply additional clamping force while allowing access to the original retaining bolts.
The original bolts were replaced and segregated so that they could be analysed onshore.
An investigation was undertaken to understand the failure mode of the FPSO fairleads.
It was hoped to compare the differing levels of damage to different factors such as weather, mooring line catenaries, etc… to determine which factors are significant.
It was concluded that the bolt damage was mainly the result of design issues.
A combination of QA/QC (quality assurance/quality control) issues, environmental and operating conditions could explain the differing levels of fairlead damage.
The integrity of the mooring system was severely under threat throughout.
Plus, replacing a fairlead is a long and costly exercise, therefore early identification of fairlead bolt issues and intervention is extremely valuable.
Related Results
Analisis Pengaruh Posisi Fairlead Terhadap Rasio Kerusakan Akibat Kelelahan Pada Struktur Tali Tambat Tipe Catenary FPSO Aoka Mizu
Analisis Pengaruh Posisi Fairlead Terhadap Rasio Kerusakan Akibat Kelelahan Pada Struktur Tali Tambat Tipe Catenary FPSO Aoka Mizu
Penelitian ini membahas pengaruh posisi fairlead terhadap rasio kerusakan akibat kelelahan atau fatigue damage ratio pada struktur catenary Floating Production Storage and Offloadi...
FPSO's Today: What is the Optimum Concept?
FPSO's Today: What is the Optimum Concept?
ABSTRACT
FPSO technology over the past years has rapidly evolved from tanker based units with classical mooring systems to purpose-shaped new built vessels equipp...
The Sanha LPG FPSO
The Sanha LPG FPSO
Abstract
The FPSO industry will soon have the first LPG FPSO in operation. The SANHA LPG FPSO is the first gas related FPSO. With the installation of the LPG FPSO...
ROSA: New Challenges in West Africa Deepwater Developments
ROSA: New Challenges in West Africa Deepwater Developments
Abstract
Discovered in 1998, the Rosa field is located offshore Angola in the prolific Block 17, at a distance of 16 kilometers from the spread-moored Girassol FP...
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Abstract
In a North Sea storm during February 2011 the Gryphon Alpha FPSO broke four of her 10 mooring lines and moved partially off station, causing damage to su...
Offshore Dry-Docking of FPSOs: A Response to Industry Needs
Offshore Dry-Docking of FPSOs: A Response to Industry Needs
ABSTRACT
The bonanza of floating production, storage and offloading units (FPSOs) that were commissioned over a decade ago have come to an age whereby offshore as...
FPSO Integrity; Structural Monitoring of Glas Dowr
FPSO Integrity; Structural Monitoring of Glas Dowr
Abstract
The objective of the Joint Industry project 'FPSO Integrity' is to provide insight in the fatigue loading of FPSO's and the accuracy and validity of comp...
Floating LNG: New Rule Note for the Classification of LNG FPSO
Floating LNG: New Rule Note for the Classification of LNG FPSO
Abstract
Offshore LNG terminals are today broadly considered by the industry to respond to the world thirst of energy in a rapid and efficient manner. In order to...

