Sakhalin II Project Overview

View through CrossRef
Abstract The Sakhalin Project overview discusses the origin of Sakhalin Energy, its participants, organization, supervision by Russian Federation--as guided by the production sharing agreement--and the decision-making process. The paper then delineates the major accomplishments to date on Vityaz Production Complex, with the most significant milestone being the installation of the Molikpaq Platform in September 1998. With the delivery of a new-build FSO to the Piltun Astokhskoye Field in June 1999, Phase I of Sakhalin II development will near completion, with first oil to be offloaded in summer 1999. The balance of the paper discusses lessons learned, and provides an introduction to the remaining Sakhalin II papers. As the first international company to secure a production sharing agreement from the Russian Federation, Sakhalin Energy is fully committed to its shareholders and to the people of Russia in the delivery of maximum efficiency and safety in the development, production and marketing of Sakhalin area hydrocarbons. This unyielding commitment has challenged the full project team to "think out of the box" in creating the most economic and safe approach to project viability. Inherent in this approach is the project philosophy of maximizing revenue while minimizing cost. Simplicity, standardization and austerity in facilities design represent guiding principles. Russian content is a key consideration to ensure in-country growth. Sakhalin Energy is executing a world-class project to develop two fields that have combined proven reserves of approximately 1 billion barrels of liquids and 14 trillion cubic feet of gas. This global effort incorporates the expertise of highly trained Russian employees and contractors, plus the international oil industry's best resources for upstream oil and gas development. Introduction Years of effort by the Russian Federation, the Sakhalin Oblast administration and the Sakhalin II project partners has resulted in the industry's first production platform being successfully installed offshore Sakhalin Island. The newly refitted Molikpaq drilling/production facility-the keystone of the Vityaz Production Complex-was installed at the Piltun-Astokhskoye Field in 30 meters of water, 16 kilometers offshore Sakhalin Island's northeast shore in the Sea of Okhotsk on Sept. 1, 1998. Other components of the Vityaz Production Complex include the facilities required for tanker offloading during the six months of the ice-free season. Production start-up is slated for July 1999, with flow rates expected to reach 90,000 barrels/day of oil and 70 million standard cubic feet/day of gas by the start of second producing season producing season. The project is managed by Sakhalin Energy Investment Company Ltd.--a four-company consortium including Marathon Sakhalin Ltd., Mitsui Sakhalin Holdings B.V., Shell Sakhalin Holdings B.V. and Diamond Gas Sakhalin B.V., a Mitsubishi subsidiary. The Sakhalin II project will provide the first production under a production sharing agreement in the Russian Federation. The Molikpaq--a gravity-based structure originally designed for Beaufort Sea exploratory drilling--was acquired in 1997 from Gulf Canada. It is the first platform of its kind, designed for an environment of high ice loads combined with significant seismic activity and intense wind and wave loads. The lack of infrastructure for oil and gas development at this remote location presented a challenge for the Sakhalin II team in defining a design scheme for an early production system. Molikpaq provides all of the required facilities for this remote development, including accommodations, the ability to drill and produce up to 32 wells, an oil export system and appropriate gas utiliz
Title: Sakhalin II Project Overview
Description:
Abstract The Sakhalin Project overview discusses the origin of Sakhalin Energy, its participants, organization, supervision by Russian Federation--as guided by the production sharing agreement--and the decision-making process.
The paper then delineates the major accomplishments to date on Vityaz Production Complex, with the most significant milestone being the installation of the Molikpaq Platform in September 1998.
With the delivery of a new-build FSO to the Piltun Astokhskoye Field in June 1999, Phase I of Sakhalin II development will near completion, with first oil to be offloaded in summer 1999.
The balance of the paper discusses lessons learned, and provides an introduction to the remaining Sakhalin II papers.
As the first international company to secure a production sharing agreement from the Russian Federation, Sakhalin Energy is fully committed to its shareholders and to the people of Russia in the delivery of maximum efficiency and safety in the development, production and marketing of Sakhalin area hydrocarbons.
This unyielding commitment has challenged the full project team to "think out of the box" in creating the most economic and safe approach to project viability.
Inherent in this approach is the project philosophy of maximizing revenue while minimizing cost.
Simplicity, standardization and austerity in facilities design represent guiding principles.
Russian content is a key consideration to ensure in-country growth.
Sakhalin Energy is executing a world-class project to develop two fields that have combined proven reserves of approximately 1 billion barrels of liquids and 14 trillion cubic feet of gas.
This global effort incorporates the expertise of highly trained Russian employees and contractors, plus the international oil industry's best resources for upstream oil and gas development.
Introduction Years of effort by the Russian Federation, the Sakhalin Oblast administration and the Sakhalin II project partners has resulted in the industry's first production platform being successfully installed offshore Sakhalin Island.
The newly refitted Molikpaq drilling/production facility-the keystone of the Vityaz Production Complex-was installed at the Piltun-Astokhskoye Field in 30 meters of water, 16 kilometers offshore Sakhalin Island's northeast shore in the Sea of Okhotsk on Sept.
1, 1998.
Other components of the Vityaz Production Complex include the facilities required for tanker offloading during the six months of the ice-free season.
Production start-up is slated for July 1999, with flow rates expected to reach 90,000 barrels/day of oil and 70 million standard cubic feet/day of gas by the start of second producing season producing season.
The project is managed by Sakhalin Energy Investment Company Ltd.
--a four-company consortium including Marathon Sakhalin Ltd.
, Mitsui Sakhalin Holdings B.
V.
, Shell Sakhalin Holdings B.
V.
and Diamond Gas Sakhalin B.
V.
, a Mitsubishi subsidiary.
The Sakhalin II project will provide the first production under a production sharing agreement in the Russian Federation.
The Molikpaq--a gravity-based structure originally designed for Beaufort Sea exploratory drilling--was acquired in 1997 from Gulf Canada.
It is the first platform of its kind, designed for an environment of high ice loads combined with significant seismic activity and intense wind and wave loads.
The lack of infrastructure for oil and gas development at this remote location presented a challenge for the Sakhalin II team in defining a design scheme for an early production system.
Molikpaq provides all of the required facilities for this remote development, including accommodations, the ability to drill and produce up to 32 wells, an oil export system and appropriate gas utiliz.

Related Results

SAKHALIN
SAKHALIN
The review of seismicity for Sakhalin in 2013 based on the data of four seismic stationary stations and 10 temporary digital seismic stations "DAT", working in the south of Sakhali...
ONOR EARTHQUAKE on August 14, 2016, Mw=5.8 (Sakhalin Island)
ONOR EARTHQUAKE on August 14, 2016, Mw=5.8 (Sakhalin Island)
On August 14, 2016 at 11h15m UTS there was a strong earthquake with Mw=5.8 in the central part of the Sakhalin Island, which felt in nearby settlements with an intensity of up to I...
SAKHALIN
SAKHALIN
A review of the Sakhalin seismicity in 2014 based on the data of regional network is given. The network included four stationary and ten temporary digital seismic stations. This ne...
Unknown pages of cardiovascular surgery history in Sakhalin Region (Surgeon Alfred Egorov)
Unknown pages of cardiovascular surgery history in Sakhalin Region (Surgeon Alfred Egorov)
The article is dedicated to the history of cardiac surgery in the Sakhalin Region, which over a 20-year period of its development has achieved much success and is now mastering ope...
Assessment of Community Internet Intensity (CII) in Sakhalin Island
Assessment of Community Internet Intensity (CII) in Sakhalin Island
<p>Sakhalin Island is a region with high rate of seismic activity. Tens of felt earthquakes occur within the studied area every year. Rapid macroseismic observation t...
THE EVALUATION OF NEHEMIAH'S PROJECT MANAGEMENT APPROACH IN RELATION TO (PROJECT MANAGEMENTS INSTITUTE) PMI STANDARDS
THE EVALUATION OF NEHEMIAH'S PROJECT MANAGEMENT APPROACH IN RELATION TO (PROJECT MANAGEMENTS INSTITUTE) PMI STANDARDS
This research examines the project management strategies utilized by Nehemiah in the reconstruction of Jerusalem's walls, as described in the biblical text, and assesses their comp...
PROJECT MANAGEMENT SYSTEM AT AN ENTERPRISE: THE FOUNDATIONS OF EFFECTIVE FORMATION
PROJECT MANAGEMENT SYSTEM AT AN ENTERPRISE: THE FOUNDATIONS OF EFFECTIVE FORMATION
The article examines the principles of effective formation of a project management system at an enterprise. In the modern environment, project management standards and management i...
Improvement of the project control system : a case study of an interior decoration company
Improvement of the project control system : a case study of an interior decoration company
This thesis aimed to reduce the delay and unnecessarily accelerated or crashed activities of the project by improving the project control system of an interior decoration company. ...