San Francisco HEP Headrace Tunnel – TBM Success under the Presence of Pressurized Water in Faulty Deep Rock

View through CrossRef
AbstractThe San Francisco Hydroelectric Project in Ecuador is utilizing hydropower from the Rio Pastaza in a 230 MW plant. 8.4 km of the 11.2 km long HRT have been excavated by a double shield (DS) TBM. After 4,950 m TBM excavation in metamorphic rock series of the Cordillera Real, the TBM was trapped by a block failure of the rock under high water ingress and the TBM shield was demolished. A rescue programme was undertaken immediately on the TBM in order to stabilize the region of the event, to get control about the water ingress, to make free and to repair the TBM and to continue excavation under controlled conditions. Concurrently an alternative rescue programme was investigated and started in order not to waste time if the rescue of the TBM should fail or if further events should occur. The TBM stoppage lasted for about five month and the rescue programme enabled the repair of the TBM and a controlled restart of the TBM without any accident. After the restart the TBM again reached a sufficient daily progress of more than 20 m/d and the tunnel could be finalized with success.
Title: San Francisco HEP Headrace Tunnel – TBM Success under the Presence of Pressurized Water in Faulty Deep Rock
Description:
AbstractThe San Francisco Hydroelectric Project in Ecuador is utilizing hydropower from the Rio Pastaza in a 230 MW plant.
8.
4 km of the 11.
2 km long HRT have been excavated by a double shield (DS) TBM.
After 4,950 m TBM excavation in metamorphic rock series of the Cordillera Real, the TBM was trapped by a block failure of the rock under high water ingress and the TBM shield was demolished.
A rescue programme was undertaken immediately on the TBM in order to stabilize the region of the event, to get control about the water ingress, to make free and to repair the TBM and to continue excavation under controlled conditions.
Concurrently an alternative rescue programme was investigated and started in order not to waste time if the rescue of the TBM should fail or if further events should occur.
The TBM stoppage lasted for about five month and the rescue programme enabled the repair of the TBM and a controlled restart of the TBM without any accident.
After the restart the TBM again reached a sufficient daily progress of more than 20 m/d and the tunnel could be finalized with success.

Related Results

BIM-based Quantitative Assessment Method of Tunnel Collapse Risk in TBM Construction
BIM-based Quantitative Assessment Method of Tunnel Collapse Risk in TBM Construction
Abstract Tunnel risk assessment plays an important role in tunnel design, construction and tunnel safety risk control. TBM method is more and more widely used becaus...
Geotechnical Engineering
Geotechnical Engineering
Geotechnical analysis below the surface of hydropower plant is one way to determine the stability of the opening holes in determining the supporting system. A discussion about supp...
Construction time of secondary lining of ultra-small spacing parallel overlapping tunnel
Construction time of secondary lining of ultra-small spacing parallel overlapping tunnel
Abstract Due to the unique spatial structure, stress transfer mechanism, and construction disturbance characteristics of ultra-small spacing parallel overlapping tu...
PENGADAAN BAHAN KOLEKSI PADA TAMAN BACA SOKA SALATIGA
PENGADAAN BAHAN KOLEKSI PADA TAMAN BACA SOKA SALATIGA
ABSTRACT Library institutions are also known as educational tourist attractions. In this context, libraries provide information and knowledge sources for the community. Taman Baca...
Assessment of clinician’s knowledge and attitude toward health extension program in Ethiopia: An exploratory factor analysis
Assessment of clinician’s knowledge and attitude toward health extension program in Ethiopia: An exploratory factor analysis
Health extension workers (HEWs) are the primary implementers of the health extension program (HEP) – a government-led community-based health-care program, but clinicians ...
Managing Squeezing Rock Mass with TBM Data Analysis: Rail Link Rishikesh – Karnaprayag (India)
Managing Squeezing Rock Mass with TBM Data Analysis: Rail Link Rishikesh – Karnaprayag (India)
The 125.2 km rail link Rishikesh–Karnaprayag in the Lesser Himalayas of India represents a benchmark in mechanized tunnelling through complex geology. This paper focuses on Tunnel ...
Identifying Rock Loads on TBM Shields During Standstills (Non-Advance-Periods)
Identifying Rock Loads on TBM Shields During Standstills (Non-Advance-Periods)
AbstractTunnel boring machine (TBM) operational data is mostly analysed with respect to data that was recorded during the advance of the TBM. Focusing on data that was recorded dur...

Back to Top