Javascript must be enabled to continue!
Dalia Development-The FPSO Story and Package Challenges
View through CrossRef
Abstract
This paper will review the hull design together with topsides process modules and functions. It will also focus on the schedule challenges during construction in Korea, the steel crisis and the yards workloads. The global supply chain and management of the contractors and main subcontractors will also be addressed.
Designed and built by Dalia Mar Profundo (DMP), a consortium of Technip / Saipem / Stolt in the TSS joint venture together with Samsung Heavy Industries (SHI) and Daewoo Shipbuilding & Marine Engineering (DSME) in Korea, the FPSO is 300 metres long and 60 metres wide capable of 2 millions barrels oil storage at an average production capacity of 240,000 barrels per day. It has a "total liquid" handling capacity of 405,000 barrels per day and a gas compressing capacity of 8 million sm3 per day. A special seawater treatment for sulphate removal module is incorporated. SHI undertook the task of building the 55,000 tonnes double skinned hull and "about half" of the topside modules. DSME completed the remaining modules and undertook the installation and integration of all the topsides modules before sail away. TSS had the responsibility for onshore pre and final commissioning.
The FPSO is moored with a 12 point chain spread linked to 17 metre high, 106 tonnes suction anchors and attached to the vessel by 120 mm diameter, sheated cables 1,800 metres long, with 100 metre chain segments at either end. Weight control was very effective maintaining the weight within the original targets.
Dalia Field Overview
For more details refer to Dalia paper OTC 18538.
Refer to Figure 1 for the general field layout with the FPSO and its mooring lines, above the subsea production facilities.
Figure 1 - Dalia Development Layout (available in full paper)
General Introduction to the FPSO
The 300 metre by 60 metre new build FPSO, weighs over 85,000 tonnes dry and with a surface area of more than four football pitches, was designed and built by the DMP consortium. With storage for up to eight days at the average plateau production of 240,000 barrels per day, the twin train process system has two stages for oil separation. Each train is designed for 55% of the total capacity, to give better reliability of the separation system. After dehydration and desalting, also undertaken in two phases, the oil is cooled down to 50°C before storage.
Produced water is treated and re-injected into the reservoir for pressure maintenance. Seawater is treated to complement the total injection capacity of 405,000 barrels of water per day. Produced gas is used as fuel and the balance is re-injected in the reservoir until export to the future Angola LNG plant. Three 24 MW Gas turbines generate the power on the FPSO. These gas turbines are dual fuel and run on high quality diesel at start-up and during periods when gas is not available. Anchored in the Dalia field in September 2006 by the 12 mooring lines spread, the FPSO is built to remain in place for the design life of 20 years.
Title: Dalia Development-The FPSO Story and Package Challenges
Description:
Abstract
This paper will review the hull design together with topsides process modules and functions.
It will also focus on the schedule challenges during construction in Korea, the steel crisis and the yards workloads.
The global supply chain and management of the contractors and main subcontractors will also be addressed.
Designed and built by Dalia Mar Profundo (DMP), a consortium of Technip / Saipem / Stolt in the TSS joint venture together with Samsung Heavy Industries (SHI) and Daewoo Shipbuilding & Marine Engineering (DSME) in Korea, the FPSO is 300 metres long and 60 metres wide capable of 2 millions barrels oil storage at an average production capacity of 240,000 barrels per day.
It has a "total liquid" handling capacity of 405,000 barrels per day and a gas compressing capacity of 8 million sm3 per day.
A special seawater treatment for sulphate removal module is incorporated.
SHI undertook the task of building the 55,000 tonnes double skinned hull and "about half" of the topside modules.
DSME completed the remaining modules and undertook the installation and integration of all the topsides modules before sail away.
TSS had the responsibility for onshore pre and final commissioning.
The FPSO is moored with a 12 point chain spread linked to 17 metre high, 106 tonnes suction anchors and attached to the vessel by 120 mm diameter, sheated cables 1,800 metres long, with 100 metre chain segments at either end.
Weight control was very effective maintaining the weight within the original targets.
Dalia Field Overview
For more details refer to Dalia paper OTC 18538.
Refer to Figure 1 for the general field layout with the FPSO and its mooring lines, above the subsea production facilities.
Figure 1 - Dalia Development Layout (available in full paper)
General Introduction to the FPSO
The 300 metre by 60 metre new build FPSO, weighs over 85,000 tonnes dry and with a surface area of more than four football pitches, was designed and built by the DMP consortium.
With storage for up to eight days at the average plateau production of 240,000 barrels per day, the twin train process system has two stages for oil separation.
Each train is designed for 55% of the total capacity, to give better reliability of the separation system.
After dehydration and desalting, also undertaken in two phases, the oil is cooled down to 50°C before storage.
Produced water is treated and re-injected into the reservoir for pressure maintenance.
Seawater is treated to complement the total injection capacity of 405,000 barrels of water per day.
Produced gas is used as fuel and the balance is re-injected in the reservoir until export to the future Angola LNG plant.
Three 24 MW Gas turbines generate the power on the FPSO.
These gas turbines are dual fuel and run on high quality diesel at start-up and during periods when gas is not available.
Anchored in the Dalia field in September 2006 by the 12 mooring lines spread, the FPSO is built to remain in place for the design life of 20 years.
Related Results
FPSO's Today: What is the Optimum Concept?
FPSO's Today: What is the Optimum Concept?
ABSTRACT
FPSO technology over the past years has rapidly evolved from tanker based units with classical mooring systems to purpose-shaped new built vessels equipp...
The Sanha LPG FPSO
The Sanha LPG FPSO
Abstract
The FPSO industry will soon have the first LPG FPSO in operation. The SANHA LPG FPSO is the first gas related FPSO. With the installation of the LPG FPSO...
ROSA: New Challenges in West Africa Deepwater Developments
ROSA: New Challenges in West Africa Deepwater Developments
Abstract
Discovered in 1998, the Rosa field is located offshore Angola in the prolific Block 17, at a distance of 16 kilometers from the spread-moored Girassol FP...
FPSO Integrity; Structural Monitoring of Glas Dowr
FPSO Integrity; Structural Monitoring of Glas Dowr
Abstract
The objective of the Joint Industry project 'FPSO Integrity' is to provide insight in the fatigue loading of FPSO's and the accuracy and validity of comp...
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Abstract
In a North Sea storm during February 2011 the Gryphon Alpha FPSO broke four of her 10 mooring lines and moved partially off station, causing damage to su...
Design and Conversion of FPSO Mystras
Design and Conversion of FPSO Mystras
Abstract
A recently completed FPSO conversion project shows some novel features in FPSO design. An existing trading tanker was selected for conversion into a 48,0...
Deepwater FPSO for Aquila Field Development in the Adriatic
Deepwater FPSO for Aquila Field Development in the Adriatic
Abstract
The FPSO recently installed in 850 m water depth for the challenging Aquila Field incorporates a number of intresting features. Although the field was di...
Dalia Field - System Design and Flow Assurance for Dalia Operations
Dalia Field - System Design and Flow Assurance for Dalia Operations
Abstract
Evaluating flow assurance risks for the development of Dalia was a key task during system design to safeguard the production over the 20 years design lif...

