Design, Fabrication And Installation Of The Ninian Field Southern Platform
View through CrossRef
ABSTRACT
Chevron's Ninian Field Southern Platform is noteworthy for its rapid planning, design and fabrication, and its extremely successful installation, all of which justified the conceptual philosophy adopted early in the design stage. From the outset, the aim was to build on past experience and provide simplicity and refinement within the limits of available technology, consistent with a summer 1977 installation of a platform capable of supporting the heaviest deck load yet proposed for a piled steel structure. These goals, together with severe functional and environmental criteria, resulted in a number of interesting features.
This paper describes the process leading to the selection of a self-floating steel tower, and outlines the manner in which considerations of fabrication, transportation and installation influenced the configuration of structure and piles.
The structural design of tower and piles is described, as is the upending control system. The finite element method of analysis to verify the design of the unusual 9.2M leg nodes, is outlined and the novel cathodic protection system described.
Special study results are outlined including a summary of full scale tests to confirm the adequacy of the pile-to-sleeve grouted connection, and a computer approach to the dynamics of on-bottom stability. Installation procedure studies are listed.
Finally, the fabrication and installation record is appraised in relation to the original design concept.
SELECTION OF PLATFORM TYPE, FACTORS INFLUENCING CONFIGURATION
Introduction
It was believed that the ultimate success of the proposed program would rely as much on designing for fabrication and installation requirements as it would on structural analysis and design. In the overall development cost, the effect of saving structural steel weight by virtue of exhaustive analytical work, is insignificant; on the other hand, time spent on designing for fabrication and installation can result in very significant cost savings indeed.
Description of Tower
The Ninian Southern platform is a 4-1eg, piled, steel tower structure supporting modularized production and drilling facilities, as shown on Fig. 1. It is a self-floating unit with an integral ballasting system designed for remote controlled operation.
The deck comprises 2 levels of modules 65m by 68m in plan dimension providing three main levels, with a nominal production capacity of 150,000 B.O.P.D. Maximum anticipated deck load is 26,000 tonnes, including two drill rigs. Slots are provided for 42 conductors.
Typical dimensions are 75m by 75m center to center of the legs at the mudline tapering to 55m by 55m at the top of the module support skid-beams; overall height from mudline to skid-beams is 168.5 metres.
The tower is supported by 32 skirt piles, 1825mm O.D. by 63mm wall thickness, arranged in clusters of 8 at each leg in a 12,2m diameter circular pattern. Storage is provided in the upper parts of the 9.2m diameter flotation legs for 20,000 bbls of diesel fuel and 10,000 bbls of drilling water.
Title: Design, Fabrication And Installation Of The Ninian Field Southern Platform
Description:
ABSTRACT
Chevron's Ninian Field Southern Platform is noteworthy for its rapid planning, design and fabrication, and its extremely successful installation, all of which justified the conceptual philosophy adopted early in the design stage.
From the outset, the aim was to build on past experience and provide simplicity and refinement within the limits of available technology, consistent with a summer 1977 installation of a platform capable of supporting the heaviest deck load yet proposed for a piled steel structure.
These goals, together with severe functional and environmental criteria, resulted in a number of interesting features.
This paper describes the process leading to the selection of a self-floating steel tower, and outlines the manner in which considerations of fabrication, transportation and installation influenced the configuration of structure and piles.
The structural design of tower and piles is described, as is the upending control system.
The finite element method of analysis to verify the design of the unusual 9.
2M leg nodes, is outlined and the novel cathodic protection system described.
Special study results are outlined including a summary of full scale tests to confirm the adequacy of the pile-to-sleeve grouted connection, and a computer approach to the dynamics of on-bottom stability.
Installation procedure studies are listed.
Finally, the fabrication and installation record is appraised in relation to the original design concept.
SELECTION OF PLATFORM TYPE, FACTORS INFLUENCING CONFIGURATION
Introduction
It was believed that the ultimate success of the proposed program would rely as much on designing for fabrication and installation requirements as it would on structural analysis and design.
In the overall development cost, the effect of saving structural steel weight by virtue of exhaustive analytical work, is insignificant; on the other hand, time spent on designing for fabrication and installation can result in very significant cost savings indeed.
Description of Tower
The Ninian Southern platform is a 4-1eg, piled, steel tower structure supporting modularized production and drilling facilities, as shown on Fig.
1.
It is a self-floating unit with an integral ballasting system designed for remote controlled operation.
The deck comprises 2 levels of modules 65m by 68m in plan dimension providing three main levels, with a nominal production capacity of 150,000 B.
O.
P.
D.
Maximum anticipated deck load is 26,000 tonnes, including two drill rigs.
Slots are provided for 42 conductors.
Typical dimensions are 75m by 75m center to center of the legs at the mudline tapering to 55m by 55m at the top of the module support skid-beams; overall height from mudline to skid-beams is 168.
5 metres.
The tower is supported by 32 skirt piles, 1825mm O.
D.
by 63mm wall thickness, arranged in clusters of 8 at each leg in a 12,2m diameter circular pattern.
Storage is provided in the upper parts of the 9.
2m diameter flotation legs for 20,000 bbls of diesel fuel and 10,000 bbls of drilling water.
Related Results
Ninian Third Party Project: A Unique North Sea Challenge
Ninian Third Party Project: A Unique North Sea Challenge
ABSTRACT
The Ninian Field, operated by Chevron on behalf of the Ninian Field Group, is a mature North Sea producer. Rationalisation of the topside facilities and ...
Upending Control System for the Ninian Field Southern Platform
Upending Control System for the Ninian Field Southern Platform
ABSTRACT
This paper describes the latest "state-of-the-art" equipment developed for controlled flooding and upending of very large offshore oil drilling platforms...
Deepwater Platform Design
Deepwater Platform Design
ABSTRACT
Results of preliminary platform design studies enable engineers"to identify and appraise major variables affecting deepwater platform capabilities. Trans...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract
During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
SS: MODU Anchor: Improved Predictions of MODU Fluke Anchors Increases the Confidence in Mooring System Design
SS: MODU Anchor: Improved Predictions of MODU Fluke Anchors Increases the Confidence in Mooring System Design
Abstract
An overview of the current Norwegian and international requirements for design and installation of fluke anchors is given. Important design and installat...
The Construction Of The Ninian Central Platform For The British North Sea
The Construction Of The Ninian Central Platform For The British North Sea
ABSTRACT
At tow out from the construction base on the West coast of Scotland with 600,000 tonnes displacement, the Ninian Central Platform became the biggest floa...
T&I Engineering of Monopiles: Key Considerations – Bid to Execution
T&I Engineering of Monopiles: Key Considerations – Bid to Execution
Abstract
Monopiles remain the simplest and most widely adopted foundation solution for offshore wind farms. However, unlike onshore developments, offshore monopil...