Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Project To Upright The Alexander L. Kielland

View through CrossRef
Abstract The Alexander L Kielland is a drilling rig of Pentagone type. It was being used as an accommodation unit when it capsized in the North Sea in 1980 as a result of a structural failure. In June 1980 the owners invited tenders to upright the rig. The physical size and geometry of the rig made the prospective uprighting a novel undertaking. The method devised was based on the simple concept of rotating the rig underwater with the minimum amount of nett positive buoyancy that was consistent with safety. Adopting such a method would reduce the applied loads to acceptable levels. However, it required a detailed knowledge of the response of the rig to the applied loads, and the structural stresses involved. It was therefore decided that, in addition to the engineering systems, a computer programme should be developed to simulate the motion of the rig and that comprehensive computing capability should be deployed on site. Its purpose was to carry out the necessary analytical investigations and to work interactively with the monitoring system that had been designed for the project. Introduction The initial estimates, made immediately prior to the accident, indicated that the displacement of the rig was in excess of 17000 tonnes. The loss of D leg, its associated bracings and other structural damage was estimated to account for approximately 1400 tonnes. However the final condition of the rig in the inverted position was not known accurately. Many of the tank fittings had been damaged during the capsize and water had flooded into a number of compartments. It had also been necessary to pump air into several compartments as a preventative measure to stop the rig from sinking. The basic uprighting method involved the transfer operation between nominated tanks and hence it was imperative to ascertain the status of each tank and from that information assess the mass and structural integrity of the rig. The basic philosophy had to be developed into operating systems that would maintain control of the structure throughout the rotation. Safety of personnel and the structure were a top priority. The development of the systems and the computer software were done under line project conditions and a limited timescale. Philosophy An invitation to bid for the salvage of the rig was received in June 1980. In the document, the owners stated their intention to have the rig repaired and recommissioned as a drilling unit. They also indicated their desire to have the salvage operation completed by the end of September. This would avoid the difficulties associated with a winter towage operation to a repair yard. This implied that the contract for uprighting and preserving the rig should be completed in approximately twelve weeks. The owners also drew our attention to the fact that there was a Commission of Enquiry and Police Investigation concerned with the rig. Having given due consideration to the nature of the accident and these requirements, it was concluded that any salvage operation should satisfy the following basic criteria.
Title: Project To Upright The Alexander L. Kielland
Description:
Abstract The Alexander L Kielland is a drilling rig of Pentagone type.
It was being used as an accommodation unit when it capsized in the North Sea in 1980 as a result of a structural failure.
In June 1980 the owners invited tenders to upright the rig.
The physical size and geometry of the rig made the prospective uprighting a novel undertaking.
The method devised was based on the simple concept of rotating the rig underwater with the minimum amount of nett positive buoyancy that was consistent with safety.
Adopting such a method would reduce the applied loads to acceptable levels.
However, it required a detailed knowledge of the response of the rig to the applied loads, and the structural stresses involved.
It was therefore decided that, in addition to the engineering systems, a computer programme should be developed to simulate the motion of the rig and that comprehensive computing capability should be deployed on site.
Its purpose was to carry out the necessary analytical investigations and to work interactively with the monitoring system that had been designed for the project.
Introduction The initial estimates, made immediately prior to the accident, indicated that the displacement of the rig was in excess of 17000 tonnes.
The loss of D leg, its associated bracings and other structural damage was estimated to account for approximately 1400 tonnes.
However the final condition of the rig in the inverted position was not known accurately.
Many of the tank fittings had been damaged during the capsize and water had flooded into a number of compartments.
It had also been necessary to pump air into several compartments as a preventative measure to stop the rig from sinking.
The basic uprighting method involved the transfer operation between nominated tanks and hence it was imperative to ascertain the status of each tank and from that information assess the mass and structural integrity of the rig.
The basic philosophy had to be developed into operating systems that would maintain control of the structure throughout the rotation.
Safety of personnel and the structure were a top priority.
The development of the systems and the computer software were done under line project conditions and a limited timescale.
Philosophy An invitation to bid for the salvage of the rig was received in June 1980.
In the document, the owners stated their intention to have the rig repaired and recommissioned as a drilling unit.
They also indicated their desire to have the salvage operation completed by the end of September.
This would avoid the difficulties associated with a winter towage operation to a repair yard.
This implied that the contract for uprighting and preserving the rig should be completed in approximately twelve weeks.
The owners also drew our attention to the fact that there was a Commission of Enquiry and Police Investigation concerned with the rig.
Having given due consideration to the nature of the accident and these requirements, it was concluded that any salvage operation should satisfy the following basic criteria.

Related Results

Small Female Occupant Response in Reclined and Upright Seated Postures in Frontal Impacts
Small Female Occupant Response in Reclined and Upright Seated Postures in Frontal Impacts
Abstract The objective of this study was to compare the kinematics of the head-neck, torso, pelvis, and lower extremities and document injuries and their patterns to...
THE EVALUATION OF NEHEMIAH'S PROJECT MANAGEMENT APPROACH IN RELATION TO (PROJECT MANAGEMENTS INSTITUTE) PMI STANDARDS
THE EVALUATION OF NEHEMIAH'S PROJECT MANAGEMENT APPROACH IN RELATION TO (PROJECT MANAGEMENTS INSTITUTE) PMI STANDARDS
This research examines the project management strategies utilized by Nehemiah in the reconstruction of Jerusalem's walls, as described in the biblical text, and assesses their comp...
PROJECT MANAGEMENT SYSTEM AT AN ENTERPRISE: THE FOUNDATIONS OF EFFECTIVE FORMATION
PROJECT MANAGEMENT SYSTEM AT AN ENTERPRISE: THE FOUNDATIONS OF EFFECTIVE FORMATION
The article examines the principles of effective formation of a project management system at an enterprise. In the modern environment, project management standards and management i...
Simulating upright cervical lordosis in the supine position
Simulating upright cervical lordosis in the supine position
Cervical alignment or lordosis evolution is still attained by direct radiography in standing position because an ideal cervical curvature is essential to maintain a horizontal gaze...
LUMBO-PELVIC HIP ANGLE CHANGES DURING UPRIGHT AND FREE STYLE SITTING IN IT PROFESSIONAL WITH LOWER CROSSED SYNDROME
LUMBO-PELVIC HIP ANGLE CHANGES DURING UPRIGHT AND FREE STYLE SITTING IN IT PROFESSIONAL WITH LOWER CROSSED SYNDROME
Background: In the modern workplace, particularly within the Information Technology (IT) sector, sedentary lifestyles have become increasingly prevalent. Prolonged sitting, often i...
Improvement of the project control system : a case study of an interior decoration company
Improvement of the project control system : a case study of an interior decoration company
This thesis aimed to reduce the delay and unnecessarily accelerated or crashed activities of the project by improving the project control system of an interior decoration company. ...
Application of Mitigation Hierarchy During the Development Phase of Tilenga Project, Uganda
Application of Mitigation Hierarchy During the Development Phase of Tilenga Project, Uganda
Abstract The Tilenga project operated by TotalEnergies Exploration and Production Uganda, is an onshore oil project located in the Lake Albert Basin of Uganda. The p...
The relationship between project management process characteristics and performance outcomes
The relationship between project management process characteristics and performance outcomes
Purpose– The aim of this paper is to examine the links between project management process characteristics and project-level and firm-level performance outcomes to test the hypothes...

Back to Top