Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Excellent Engineering Solution in Compressor Area to Avoid Project Delay

View through CrossRef
Abstract Green field projects always have an advantage in terms of optimization because everything can be planned with a calculated time barrier. Whereas for brown filed projects, it is a difficult task due to multiple challenges such as limited shutdown time, limited layout space, accessibility for construction, and so on. This paper demonstrates an excellent engineering solution for overcoming these challenges while replacing the existing compressor without requiring major piping/civil modifications. During a routine asset integrity assessment, it was decided to replace one of ADNOC GAS's existing compressors with a similar one that had the same footprint, nozzle sizes, and orientations. As a result, no significant engineering is required, and only minor adjustments may be required, which can be managed as residual engineering during construction. Consequently, the Purchase Order for the compressor was placed before any engineering activities based on the limited period of the shutdown window. Since the existing compressor was very old and the design data was unknown, it was difficult to determine the nozzle loads. However, based on the new compressor design data/ nozzle loads, a stress analysis with existing piping configurations is required to ensure the piping system's integrity. It was identified that the new compressor nozzle's allowable loads are much lower as per the latest design code, API 661. The existing piping configuration is imposing more loads than expected due to the need for more flexibility in piping layout configuration. Moreover, the new compressor vendor denied the request to increase the nozzle loads. Consequently, the existing piping routing has to be modified to achieve flexibility in the piping system and meet the nozzle load requirements. With the available shutdown window, there was no time to obtain additional pipe material or change civil supports. To overcome this situation, enhanced engineering with specialized stress analysis skills and advanced techniques were used to study various options for minimizing the piping/civil modifications as much as possible while meeting the nozzle loads. The best engineering techniques include utilizing the existing support locations, minimizing piping routing/support modifications, and minimizing civil and foundation modifications. By doing so, the compressor was installed without any changes to the vendor's technical requirements and with significant cost savings in implementation while adhering to the available shutdown window.
Title: Excellent Engineering Solution in Compressor Area to Avoid Project Delay
Description:
Abstract Green field projects always have an advantage in terms of optimization because everything can be planned with a calculated time barrier.
Whereas for brown filed projects, it is a difficult task due to multiple challenges such as limited shutdown time, limited layout space, accessibility for construction, and so on.
This paper demonstrates an excellent engineering solution for overcoming these challenges while replacing the existing compressor without requiring major piping/civil modifications.
During a routine asset integrity assessment, it was decided to replace one of ADNOC GAS's existing compressors with a similar one that had the same footprint, nozzle sizes, and orientations.
As a result, no significant engineering is required, and only minor adjustments may be required, which can be managed as residual engineering during construction.
Consequently, the Purchase Order for the compressor was placed before any engineering activities based on the limited period of the shutdown window.
Since the existing compressor was very old and the design data was unknown, it was difficult to determine the nozzle loads.
However, based on the new compressor design data/ nozzle loads, a stress analysis with existing piping configurations is required to ensure the piping system's integrity.
It was identified that the new compressor nozzle's allowable loads are much lower as per the latest design code, API 661.
The existing piping configuration is imposing more loads than expected due to the need for more flexibility in piping layout configuration.
Moreover, the new compressor vendor denied the request to increase the nozzle loads.
Consequently, the existing piping routing has to be modified to achieve flexibility in the piping system and meet the nozzle load requirements.
With the available shutdown window, there was no time to obtain additional pipe material or change civil supports.
To overcome this situation, enhanced engineering with specialized stress analysis skills and advanced techniques were used to study various options for minimizing the piping/civil modifications as much as possible while meeting the nozzle loads.
The best engineering techniques include utilizing the existing support locations, minimizing piping routing/support modifications, and minimizing civil and foundation modifications.
By doing so, the compressor was installed without any changes to the vendor's technical requirements and with significant cost savings in implementation while adhering to the available shutdown window.

Related Results

Root Cause Analysis of the Catastrophic Failure of a Propylene Recycle Compressor
Root Cause Analysis of the Catastrophic Failure of a Propylene Recycle Compressor
Abstract A 2-section, 6-stage propylene recycle compressor experienced a catastrophic failure that resulted in extensive damage to its internals. The compressor was ...
Compressor Piping Design Effect on Vibration Data
Compressor Piping Design Effect on Vibration Data
One of the systems for oil and gas production supports is the nitrogen compression system. Problem found that condition of the compressor has high vibration with the maximum overal...
Real-Time Torque Estimation of an Air Conditioner Compressor for the CO2 Emissions Reduction from an Engine Vehicle
Real-Time Torque Estimation of an Air Conditioner Compressor for the CO2 Emissions Reduction from an Engine Vehicle
Reducing the CO2 emissions from all new cars is essential to prevent a climate emergency. Even in the trend of accelerating the uptake of zero-emission models, the market forecasti...
Achieving the Three Dimensions of Mixed Refrigerant Compressor Efficiency
Achieving the Three Dimensions of Mixed Refrigerant Compressor Efficiency
Abstract Investors in small-scale LNG (SSLNG) face the grave challenge of achieving cost efficiency, operational efficiency, and energy efficiency in the equipment t...
Approach to Model Thermistor Based AC Compressor Cut-OFF/Cut-IN Phenomenon in 1D Simulation of Mobile Air Conditioning
Approach to Model Thermistor Based AC Compressor Cut-OFF/Cut-IN Phenomenon in 1D Simulation of Mobile Air Conditioning
<div class="section abstract"><div class="htmlview paragraph">This paper documents the approach followed to simulate the physical phenomenon of thermistor based AC comp...
Centrifugal Compressor Design Considerations
Centrifugal Compressor Design Considerations
Initial design considerations of centrifugal compressor are commonly performed with experience base, although computer technology and numerical methods had made significantly progr...
The Effects of Wet Compression on Gas Turbine Engine Operating Performance
The Effects of Wet Compression on Gas Turbine Engine Operating Performance
Water, in the liquid or vapor phase, injected at various locations into the gas turbine cycle has frequently been employed to improve engine performance. One such way to improve en...
Inlet Distortion Studies on a Centrifugal Compressor
Inlet Distortion Studies on a Centrifugal Compressor
Abstract Centrifugal compressors can be subjected to non-uniformity in inlet flows due to complicated inlet pipe geometries arising from space constraints and the wa...

Back to Top