ABSTRACT
The paper analyzes the limiting conditions of crane vessel operations with special emphasis on large semisubmersibles. As reference structures a barge with 500 t crane capacity, a ship with 1,800 t capacity and a semisubmersible with two revolving 6,000 t cranes, are investigated. Model tests in irregular seas and specific wave groups demonstrate the significance of coupled resonance motions of vessel and suspended load for crane operations with semisubmersibles. 'With barges and ships resonance is of minor in1.portance due to high damping.
The mass of the suspended load and the sling length are decisive parameters for the motion characteristics of crane vessels. The transfer function of the vertical load motion, which is selected as limiting quantity, has been determined experimentally for each of the three vessels. Depending on this parameter and the maximum allowable load motion the limiting wave heights for crane vessel operations are compiled.
INTRODUCTION
Offshore oil production in deeper and more hostile locations of the North Sea will require an investment of $15 to $20 for each barrel of future oil output. Consequently, the crude oil price collapse in 1986 - taking the value of a barrel of Brent oil down to $10 - stopped most industrial developments. The challenge, however, also provoked new ideas and concepts like floating production systems, compliant structures and light-weight platforms. A major incentive for economic field developments was the advent of giant crane vessels. With maximum load capacities of up to 14,000 tollS complete jackets, topsides, foundations, templates etc. can bc installed or removed, mostly by tandem crane operations. Installation costs are reduced up to 40 percent as the saving on steel for "slimline" jackets amounts to 20 perccnt in relation to the conventional launching method. Even greater stec1 weight savings - up to 40 percent - are being made by constructing an integrated deck rather than building a series of modules in individual shipyards [1-8]. further, offshore work requirements - costing five times more than for the same work onshore - are reduced considerably, testing and commissioning of platform decks is accomplished onshore and weather window limitations are less significant. Based on data of 2nd, 3rd and 4th-Generation North Sea platforms Vugts [9] estimates substantial cost savings by favouring an installation by crane vessc1 above traditional launching (Fig. 1).
Fig. 2 presents some data of semisubmersible crane vessels (SSCV), ships or barges [10]. N'ote the dramatic increase of lifting capacity. Amazingly just the load sensitive scmisubmersibles made thc running. Of course, thcir excellent motion behaviour in the seaway is a major advantage and sheer size with options for two cranes of large load capacity, outreach and lifting height combined with a flexible ballasting system outmatches other concepts in delicate offshore lifting operations.
Title: Operational Limitations of Offshore Crane Vessels
Description:
ABSTRACT
The paper analyzes the limiting conditions of crane vessel operations with special emphasis on large semisubmersibles.
As reference structures a barge with 500 t crane capacity, a ship with 1,800 t capacity and a semisubmersible with two revolving 6,000 t cranes, are investigated.
Model tests in irregular seas and specific wave groups demonstrate the significance of coupled resonance motions of vessel and suspended load for crane operations with semisubmersibles.
'With barges and ships resonance is of minor in1.
portance due to high damping.
The mass of the suspended load and the sling length are decisive parameters for the motion characteristics of crane vessels.
The transfer function of the vertical load motion, which is selected as limiting quantity, has been determined experimentally for each of the three vessels.
Depending on this parameter and the maximum allowable load motion the limiting wave heights for crane vessel operations are compiled.
INTRODUCTION
Offshore oil production in deeper and more hostile locations of the North Sea will require an investment of $15 to $20 for each barrel of future oil output.
Consequently, the crude oil price collapse in 1986 - taking the value of a barrel of Brent oil down to $10 - stopped most industrial developments.
The challenge, however, also provoked new ideas and concepts like floating production systems, compliant structures and light-weight platforms.
A major incentive for economic field developments was the advent of giant crane vessels.
With maximum load capacities of up to 14,000 tollS complete jackets, topsides, foundations, templates etc.
can bc installed or removed, mostly by tandem crane operations.
Installation costs are reduced up to 40 percent as the saving on steel for "slimline" jackets amounts to 20 perccnt in relation to the conventional launching method.
Even greater stec1 weight savings - up to 40 percent - are being made by constructing an integrated deck rather than building a series of modules in individual shipyards [1-8].
further, offshore work requirements - costing five times more than for the same work onshore - are reduced considerably, testing and commissioning of platform decks is accomplished onshore and weather window limitations are less significant.
Based on data of 2nd, 3rd and 4th-Generation North Sea platforms Vugts [9] estimates substantial cost savings by favouring an installation by crane vessc1 above traditional launching (Fig.
1).
Fig.
2 presents some data of semisubmersible crane vessels (SSCV), ships or barges [10].
N'ote the dramatic increase of lifting capacity.
Amazingly just the load sensitive scmisubmersibles made thc running.
Of course, thcir excellent motion behaviour in the seaway is a major advantage and sheer size with options for two cranes of large load capacity, outreach and lifting height combined with a flexible ballasting system outmatches other concepts in delicate offshore lifting operations.
Related Results
Operational Dynamics Of An Offshore Crane
Operational Dynamics Of An Offshore Crane
Abstract
A computational method is described for calculating the detailed dynamics of fixed offshore platform cranes based on finite element techniques. The metho...
Crane Load Moment System For Offshore Crane Operations
Crane Load Moment System For Offshore Crane Operations
Abstract
History has shown that dependency upon the crane operator to monitor loads and boom angle or load radius do not allow the margin necessary to perform the...
Motion Characteristics of Crane Vessels in Lifting Operation
Motion Characteristics of Crane Vessels in Lifting Operation
ABSTRACT
This paper deals with motion characteristics of crane vessels in lifting operation. Emphasis is laid here especially on the effect of coupled motion betw...
Vessels from Late Medieval cemeteries in the Central Balkans
Vessels from Late Medieval cemeteries in the Central Balkans
Although a rare occurrence in late medieval cemeteries, vessels have been
found on almost all major sites of the period, such as Novo Brdo, Trgoviste,
Reljina Gradina and the...
The Semi-Submersible Crane Vessel "Balder"
The Semi-Submersible Crane Vessel "Balder"
Abstract
The extreme weather and sea conditions of the Northern North Sea and the consequential generally low performance rate of crane ships and barges in genera...
Inspection of Subsea Conductors Using an Innovative Drop-Down Camera
Inspection of Subsea Conductors Using an Innovative Drop-Down Camera
Abstract
Subsea conductors are the foundational elements of offshore drilling operations, serving a dual purpose as both the structural framework and the main condui...
Benefits of an Integrated Power and Hydrogen Offshore Grid in a Net-Zero North Sea Energy System
Benefits of an Integrated Power and Hydrogen Offshore Grid in a Net-Zero North Sea Energy System
The North Sea Offshore Grid concept has been envisioned as a promising alternative to: 1) ease the integration of offshore wind and onshore energy systems, and 2) increase the cros...
Guest Editorial: Marine Personnel Transfer Requires Industry Attention
Guest Editorial: Marine Personnel Transfer Requires Industry Attention
Each year, millions of crew transfers take place, and, whether by helicopter or vessel, the process is one of the areas of greatest risk in global offshore operations. A recent stu...