INVESTIGATING SITE-RELATED NOTICES IN CONSTRUCTION CONTRACTS

View through CrossRef
Notices issued under the construction contract serve several purposes, the most significant of which is to facilitate the progression of the works. This is done through establishing necessary communications among the project participants by acting in accordance with the callings of the contract conditions. Through an in-depth examination of the notices stipulated under the standard conditions for the construction contract issued by the International Federation of Consulting Engineers (FIDIC), it was found that 43 out of 93 encountered notices deal with issues related to activities taking place on the construction site. The purpose of this paper is to present a detailed analysis of these notices and highlight their operability properties. The analysis focuses on the various characteristics pertaining to this vital group of notices, namely: their types, the participants involved in their administration, their related time bars, and the concerned aspects of the site activities. Results of the performed analysis are twofold: (1) the majority of these notices are found to be of the structured (complex composition) type; and (2) the contractor has the larger share in triggering their associated sub-clauses, and to do so, for the majority of these notices, within numerically stipulated time bars. The main contribution of the presented work is in providing a focused reference that can help contract administration practitioners, dealing with site-related matters, improve the current state of practice.
Title: INVESTIGATING SITE-RELATED NOTICES IN CONSTRUCTION CONTRACTS
Description:
Notices issued under the construction contract serve several purposes, the most significant of which is to facilitate the progression of the works.
This is done through establishing necessary communications among the project participants by acting in accordance with the callings of the contract conditions.
Through an in-depth examination of the notices stipulated under the standard conditions for the construction contract issued by the International Federation of Consulting Engineers (FIDIC), it was found that 43 out of 93 encountered notices deal with issues related to activities taking place on the construction site.
The purpose of this paper is to present a detailed analysis of these notices and highlight their operability properties.
The analysis focuses on the various characteristics pertaining to this vital group of notices, namely: their types, the participants involved in their administration, their related time bars, and the concerned aspects of the site activities.
Results of the performed analysis are twofold: (1) the majority of these notices are found to be of the structured (complex composition) type; and (2) the contractor has the larger share in triggering their associated sub-clauses, and to do so, for the majority of these notices, within numerically stipulated time bars.
The main contribution of the presented work is in providing a focused reference that can help contract administration practitioners, dealing with site-related matters, improve the current state of practice.

Related Results

Architecture between heteronomy and self-generation
Architecture between heteronomy and self-generation
Introduction «I have never worked in the technocratic exaltation, solving a constructive problem and that’s it. I’ve always tried to interpret the space of human life» (Vitto...
Analyzing `Language Features of Construction Contracts from The Multi-Dimensional Perspective
Analyzing `Language Features of Construction Contracts from The Multi-Dimensional Perspective
In recent years, China’s active participation in the international construction market has led to a greater demand for the comprehensive demystification of construction contracts f...
ADMINISTERING CONDITION PRECEDENT NOTICES IN CONSTRUCTION CONTRACTS
ADMINISTERING CONDITION PRECEDENT NOTICES IN CONSTRUCTION CONTRACTS
Notices represent a main area of concern for engineering and architecture professionals involved in construction contract administration, as the failure to satisfy their requiremen...
Management of the development of the accounting and tax accounting system for forward and futures contracts
Management of the development of the accounting and tax accounting system for forward and futures contracts
In the modern conditions of economic development management in Ukraine, forward and futures contracts allow for reducing risks of price fluctuations that are necessary for economic...
Raad Hamza Awad The law applicable to international renewable energy contracts
Raad Hamza Awad The law applicable to international renewable energy contracts
The renewable energy contract is a modern type of contract that requires specific provisions regarding its conclusion, execution, termination, and the applicable law. This is due t...
Eyes on Air
Eyes on Air
Abstract We at ADNOC Logistics & Services have identified the need for a Fully Integrated Inspection and Monitoring Solution to meet our operational, safety and ...
The Nexus Between Construction Contract Risk Assessment and Big Data in China
The Nexus Between Construction Contract Risk Assessment and Big Data in China
The construction market in China is currently showing an increasing trend in terms of project size, complexity, and technical difficulty. With large initial investments and long ca...
Monitoring building operation and maintenance contracts
Monitoring building operation and maintenance contracts
PurposeThe purpose of the paper is to study the use of management tools and their costs for monitoring building operation and maintenance (O&M) service contracts.Design/methodo...

Back to Top