Journey of Permanent Downhole Gauges (PDHGs) Deployment in Oil and Gas Wells, Added Values, and Potential Digitalization Applications
View through CrossRef
Abstract
Objectives, Scope
An Offshore Field developed with a digital Oil Field concept where gauges and meters are digital and connected to company HQ through digital platform, all wells equipped with Permanent downhole Gauges (PDHGs), First batch of PDHGs was activated during field commissioning under projects team at 2018, subsequent 27 wells equipped with PDHGs has no plan in place for activation, a task was initiated to accelerate PDHGs activation of under operation phase, after commissioning the value of gauges is being estimated and proved with a lot of cases related for production and reservoir management.
Methods, And Process
PDHGs are electric devices measures real time pressure and temperature data, permanently installed in oil and gas wells, connected to surface by cable for power supply and data transfer
Task ownership was assigned to Subsurface team to tackle the batch of wells drilled after field commissioning equipped with PDHGs pending gauges pending gauges activation
Actions was taken with coordination with engineering team and field production to have project in place target commissioning of PDHGs with surface facilities coupling reading with the company digital platform to be accessible for subsurface and reservoir team, a lot of optimization approaches was taken to accelerate and give priority for critical wells, vendor work management,
Monitored gauges reading for 24 hrs, share data with reservoir team to confirm data matching reservoir performance
Results, observations, and conclusions
Job execution was conducted successfully, all PDHGs are configured in the digital platform real time
Having real time monitoring ensures defined decision making, opens a new era of reservoir surveillance with fast track action taking Optimized well intervention activities, eliminated memory gauges utilization, estimate cost reduction 10.5 $MMUSDAvoided oil deferment due to wells shut in for well intervention activities 3.7 Million BBLSProducing wells to the limit above saturation pressure by accurate measuring the bottomhole flowing pressureEarly detection of water loading with wells showing water production with quick action taking and well offloadingStimulation with highest surface pressure observing Bottom hole injection pressure away from frac pressureSecuring input data for digital software utilizing artificial intelligence
It is highly recommended to utilize PDHGs in all oil and gas wells, it makes real difference Actual charts and cases will be addressed
Initiative ad added information
PDHGs provide the chance for downhole data connection with software covering reservoir analysis and field operation optimization
Wells interference can be clearly detected on spot to take the proper action
Scale accumulation, choke plugging/ malfunction situations can be proven by gauges reading
Title: Journey of Permanent Downhole Gauges (PDHGs) Deployment in Oil and Gas Wells, Added Values, and Potential Digitalization Applications
Description:
Abstract
Objectives, Scope
An Offshore Field developed with a digital Oil Field concept where gauges and meters are digital and connected to company HQ through digital platform, all wells equipped with Permanent downhole Gauges (PDHGs), First batch of PDHGs was activated during field commissioning under projects team at 2018, subsequent 27 wells equipped with PDHGs has no plan in place for activation, a task was initiated to accelerate PDHGs activation of under operation phase, after commissioning the value of gauges is being estimated and proved with a lot of cases related for production and reservoir management.
Methods, And Process
PDHGs are electric devices measures real time pressure and temperature data, permanently installed in oil and gas wells, connected to surface by cable for power supply and data transfer
Task ownership was assigned to Subsurface team to tackle the batch of wells drilled after field commissioning equipped with PDHGs pending gauges pending gauges activation
Actions was taken with coordination with engineering team and field production to have project in place target commissioning of PDHGs with surface facilities coupling reading with the company digital platform to be accessible for subsurface and reservoir team, a lot of optimization approaches was taken to accelerate and give priority for critical wells, vendor work management,
Monitored gauges reading for 24 hrs, share data with reservoir team to confirm data matching reservoir performance
Results, observations, and conclusions
Job execution was conducted successfully, all PDHGs are configured in the digital platform real time
Having real time monitoring ensures defined decision making, opens a new era of reservoir surveillance with fast track action taking Optimized well intervention activities, eliminated memory gauges utilization, estimate cost reduction 10.
5 $MMUSDAvoided oil deferment due to wells shut in for well intervention activities 3.
7 Million BBLSProducing wells to the limit above saturation pressure by accurate measuring the bottomhole flowing pressureEarly detection of water loading with wells showing water production with quick action taking and well offloadingStimulation with highest surface pressure observing Bottom hole injection pressure away from frac pressureSecuring input data for digital software utilizing artificial intelligence
It is highly recommended to utilize PDHGs in all oil and gas wells, it makes real difference Actual charts and cases will be addressed
Initiative ad added information
PDHGs provide the chance for downhole data connection with software covering reservoir analysis and field operation optimization
Wells interference can be clearly detected on spot to take the proper action
Scale accumulation, choke plugging/ malfunction situations can be proven by gauges reading.
Related Results
Developments in Appalachian Area in 1943
Developments in Appalachian Area in 1943
ABSTRACT
New York. The expected increase in wildcat drilling in New York state proved true in wells drilled but was utterly disappointing in results obtained. In ...
Survey Of Horizontal Gas Well Activity
Survey Of Horizontal Gas Well Activity
Abstract
This paper presents the results of a survey on horizontal gas well activity throughout the world. The survey was conducted for the Gas Research Institute...
Innovative Rigless Well Test Solution with Powered Sub-Surface Shut-In Wireless Telemetry System to Enhance Dynamic Reservoir Characterization Cost-Effectively
Innovative Rigless Well Test Solution with Powered Sub-Surface Shut-In Wireless Telemetry System to Enhance Dynamic Reservoir Characterization Cost-Effectively
Abstract
A key part of dynamic reservoir characterization is pressure transient analysis, which is essential in understanding near wellbore and far field formation p...
Integrating Real-time Downhole Data to Enhance Gas-lift Completion Strategies and Perforation Practices
Integrating Real-time Downhole Data to Enhance Gas-lift Completion Strategies and Perforation Practices
Abstract
This paper discusses the use of downhole gauges not only for monitoring pressure and temperature, but also production-optimization, enhancing completion des...
Challenges in Downhole Multiphase Measurements
Challenges in Downhole Multiphase Measurements
Abstract
Permanent downhole multi-phase monitoring (DMM) can give several advantages in field development, such as increased flexibility in the development of mul...
Permanent Downhole Gauges: A Key To Optimize Deepsea Production
Permanent Downhole Gauges: A Key To Optimize Deepsea Production
ABSTRACT
This paper shows the Brazilian 14 year experience (from 1977 to 1991), concerning 45 permanent installations of downhole pressure gauges, 41 installed in...
Downhole Gas Separation and Injection Powered by a Downhole Turbo Expander
Downhole Gas Separation and Injection Powered by a Downhole Turbo Expander
Abstract
A downhole gas compressor and turbine expander are being developed to inject excess gas into North Slope fields. North Slope oil fields and some oil and con...
A Novel Approach Utilizing Dual String with ESP System to Enable Gas Separator Configuration with Downhole Packers
A Novel Approach Utilizing Dual String with ESP System to Enable Gas Separator Configuration with Downhole Packers
Abstract
The utilization of electrical submersible pumps (ESP) in oil production has been established in the energy industry. Many factors play major roles in select...