Cooperative Planning, Uncertainty and Managerial Control in Concurrent Design
View through CrossRef
We examine whether cooperative planning and uncertainty affect the magnitude of rework in concurrent engineering projects with upstream and downstream operations, and explore the impact of such rework on project delays. Using survey data from a sample of 120 business process (BP) redesign and related information technology (IT) development projects in healthcare and telecommunications, our results indicate that upstream (BP) rework and downstream (IT) rework is mediated and mitigated by cooperative planning through upstream/downstream strategy coupling and cross-functional involvement. In addition, uncertainty related to a lack of firm or industry experience with such projects increases the magnitude of upstream rework but not downstream rework or the amount of cooperative planning. After accounting for project scope, implementation horizon and whether delays are anticipated, we find that project delay is primarily influenced by the magnitude of downstream rework and downstream delay: the magnitude of both upstream and downstream rework significantly increases downstream delay, which significantly increases project delay. However, the magnitude of upstream rework does not directly affect project delay. These results suggest that project delay is under managerial control as cooperative planning is a managerial function that reduces downstream rework, while uncertainty from a lack of experience with the design affecting upstream rework is not directly under managerial control.
Title: Cooperative Planning, Uncertainty and Managerial Control in Concurrent Design
Description:
We examine whether cooperative planning and uncertainty affect the magnitude of rework in concurrent engineering projects with upstream and downstream operations, and explore the impact of such rework on project delays.
Using survey data from a sample of 120 business process (BP) redesign and related information technology (IT) development projects in healthcare and telecommunications, our results indicate that upstream (BP) rework and downstream (IT) rework is mediated and mitigated by cooperative planning through upstream/downstream strategy coupling and cross-functional involvement.
In addition, uncertainty related to a lack of firm or industry experience with such projects increases the magnitude of upstream rework but not downstream rework or the amount of cooperative planning.
After accounting for project scope, implementation horizon and whether delays are anticipated, we find that project delay is primarily influenced by the magnitude of downstream rework and downstream delay: the magnitude of both upstream and downstream rework significantly increases downstream delay, which significantly increases project delay.
However, the magnitude of upstream rework does not directly affect project delay.
These results suggest that project delay is under managerial control as cooperative planning is a managerial function that reduces downstream rework, while uncertainty from a lack of experience with the design affecting upstream rework is not directly under managerial control.
Related Results
New Perspectives for 3D Visualization of Dynamic Reservoir Uncertainty
New Perspectives for 3D Visualization of Dynamic Reservoir Uncertainty
This reference is for an abstract only. A full paper was not submitted for this conference.
Abstract
1 Int...
Reserves Uncertainty Calculation Accounting for Parameter Uncertainty
Reserves Uncertainty Calculation Accounting for Parameter Uncertainty
Abstract
An important goal of geostatistical modeling is to assess output uncertainty after processing realizations through a transfer function, in particular, to...
The uncertainty–investment relationship: scrutinizing the role of firm size
The uncertainty–investment relationship: scrutinizing the role of firm size
PurposeThe objective of this paper is threefold. First, it aims to empirically study whether firm-specific/idiosyncratic uncertainty, macroeconomic/aggregate uncertainty and politi...
KEPASTIAN HUKUM PENGAWASAN KOPERASI TERKAIT KESALAHAN PENGELOLAAN KOPERASI DAN TANGGUNG JAWABNYA.
KEPASTIAN HUKUM PENGAWASAN KOPERASI TERKAIT KESALAHAN PENGELOLAAN KOPERASI DAN TANGGUNG JAWABNYA.
The duties of the Cooperative Supervisor include supervising the implementation of the policy and management of the Cooperative, with the duties attached to his position, of course...
Nonlinear optimal control for robotic exoskeletons with electropneumatic actuators
Nonlinear optimal control for robotic exoskeletons with electropneumatic actuators
Purpose
To provide high torques needed to move a robot’s links, electric actuators are followed by a transmission system with a high transmission rate. For instance, gear ratios of...
Integrated Foundation and Structural Reliability Analysis of a North Sea Structure
Integrated Foundation and Structural Reliability Analysis of a North Sea Structure
ABSTRACT
In cases where the reliability of fixed offshore structures in extreme storms is influenced by both structural and foundation failure, appropriate interp...
Pembelajaran Matematika dengan Pendekatan Cooperative Learning Ditinjau dari Prestasi Belajar, Motivasi, dan Akhlak Mulia Siswa
Pembelajaran Matematika dengan Pendekatan Cooperative Learning Ditinjau dari Prestasi Belajar, Motivasi, dan Akhlak Mulia Siswa
Penelitian ini bertujuan untuk mendeskripsikan keefektifan pembelajaran matematika dengan pendekatan cooperative learning tipe Student Teams-Achievement Divisions (STAD) dan cooper...